Notice2022-26091
Great Lakes Hydro America. LLC; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
November 30, 2022
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 229 (Wednesday, November 30, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 229 (Wednesday, November 30, 2022)]
[Notices]
[Pages 73553-73554]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-26091]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2327-049]
Great Lakes Hydro America. LLC; Notice of Application Accepted
for Filing and Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Temporary Variance from Reservoir Elevation.
b. Project No: P-2327-049.
c. Date Filed: November 15, 2022.
d. Applicant: Great Lakes Hydro America. LLC.
e. Name of Project: Cascade Project.
f. Location: The project is located on the Androscoggin River, in
Coos County, New Hampshire.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Kyle Murphy, Brookfield Renewable, 150 Main
Street, Lewiston, Maine 04240, (207) 458-5861.
i. FERC Contact: Zeena Aljibury, (202) 502-6065,
<a href="/cdn-cgi/l/email-protection#ea908f8f848bc48b868083889f9893aa8c8f9889c48d859c"><span class="__cf_email__" data-cfemail="770d1212191659161b1d1e1502050e371112051459101801">[email protected]</span></a>.
j. Deadline for filing comments, motions to intervene, and protests
is 30 days from the issuance date of this notice by the Commission.
The Commission strongly encourages electronic filing. Please file
motions to intervene, protests, comments, or recommendations using the
[[Page 73554]]
Commission's eFiling system at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
<a href="http://www.ferc.gov/docs-filing/ecomment.asp">http://www.ferc.gov/docs-filing/ecomment.asp</a>. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#e7a1a2b5a4a8898b8e8982b4929797889593a781829584c9808891"><span class="__cf_email__" data-cfemail="94d2d1c6d7dbfaf8fdfaf1c7e1e4e4fbe6e0d4f2f1e6f7baf3fbe2">[email protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. The first page of any filing should include the docket
number P-2327-049. Comments emailed to Commission staff are not
considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
k. Description of Request: Great Lakes Hydro America LLC.
(applicant) requests Commission approval for a temporary variance from
the normal reservoir elevation to conduct concrete repairs to the
forebay headgate structure which were identified in the 11th (2019)
Part 12 Inspection Recommendations. The applicant requests to draw down
the head pond from elevation of 901.4 feet to 897.2 feet (i.e., 4.2
feet from normal operating level) for a period of approximately twelve
weeks beginning in June 2023 to dewater the concrete areas in need of
repair. The applicant would lower the head pond at a rate not to exceed
3 inches per hour to avoid potential fish stranding and maintain the
minimum required bypass flow of 6 cubic feet per second via leakage
(consistent with operations during routine flashboard replacement).
Once the repairs are completed, the head pond will be refilled at a
rate not to exceed 3 inches per hour. The applicant requests the
temporary variance to remain into effect until the end of September
2023.
l. Locations of the Application: This filing may be viewed on the
Commission's website at <a href="http://www.ferc.gov">http://www.ferc.gov</a> using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. You may also register
online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be
notified via email of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or email
<a href="/cdn-cgi/l/email-protection#6d2b283f2e2203010403083e181d1d021f192d0b081f0e430a021b"><span class="__cf_email__" data-cfemail="6c2a293e2f2302000502093f191c1c031e182c0a091e0f420b031a">[email protected]</span></a>, for TTY, call (202) 502-8659. Agencies may
obtain copies of the application directly from the applicant.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, 211,
214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO
INTERVENE'' as applicable; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person commenting, protesting or intervening; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis. Any filing made by an intervenor must be accompanied
by proof of service on all persons listed in the service list prepared
by the Commission in this proceeding, in accordance with 18 CFR
385.2010.
Dated: November 23, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-26091 Filed 11-29-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on November 30, 2022.