Notice2022-24529
Northern Natural Gas Company; Notice of Availability of the Environmental Assessment for the Proposed Des Moines A-Line Capacity Replacement Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
November 10, 2022
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 217 (Thursday, November 10, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 217 (Thursday, November 10, 2022)]
[Notices]
[Pages 67889-67890]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-24529]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-26-000]
Northern Natural Gas Company; Notice of Availability of the
Environmental Assessment for the Proposed Des Moines A-Line Capacity
Replacement Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared an environmental assessment (EA) for the Des
Moines A-Line Capacity Replacement Project (Project), in Boone, Dallas
and Polk Counties, Iowa, proposed by Northern Natural Gas Company
(Northern) in the above-referenced docket. Northern requests
authorization from the Commission to abandon about 29.6 miles of its
existing 16-inch-diameter Des Moines A-line. This old pipeline, which
was originally built in the 1940s, includes mechanical joints and
acetylene welds, so that it cannot be inspected with in-line tools.
Northern would install a total of about 9.07 miles of new 20-inch-
diameter pipeline, in two separate segments, as an extension of its
existing C-line. The C-line extension would allow replacement of a
total of about 340 million cubic feet per day of natural gas that would
have flowed through the A-line to be abandoned.
The EA assesses the potential environmental effects of the
construction and operation of the Project in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the proposed project, with appropriate
mitigating measures, would not constitute a major federal action
significantly affecting the quality of the human environment.
The Commission mailed a copy of the Notice of Availability of the
EA to federal, state, and local government representatives and
agencies; elected
[[Page 67890]]
officials; non-governmental organizations, environmental, and public
interest groups; potentially interested Indian tribes; affected
landowners; and newspapers and libraries in the project area. The EA is
only available in electronic format. It may be viewed and downloaded
from the FERC's website (<a href="http://www.ferc.gov">www.ferc.gov</a>), on the natural gas
environmental documents page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). In addition, the EA
may be accessed by using the eLibrary link on the FERC's website. Click
on the eLibrary link (<a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>),
select ``General Search'' and enter the docket number in the ``Docket
Number'' field, (i.e. CP22-26). Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at <a href="/cdn-cgi/l/email-protection#d395b6a1b09cbdbfbabdb680a6a3a3bca1a793b5b6a1b0fdb4bca5"><span class="__cf_email__" data-cfemail="e1a7849382ae8f8d888f84b29491918e9395a187849382cf868e97">[email protected]</span></a> or toll free at (866) 208-3676,
or for TTY, contact (202) 502-8659.
The EA is not a decision document. It presents Commission staff's
independent analysis of the environmental issues for the Commission to
consider when addressing the merits of all issues in this proceeding.
Any person wishing to comment on the EA may do so. Your comments should
focus on the EA's disclosure and discussion of potential environmental
effects, reasonable alternatives, and measures to avoid or lessen
environmental impacts. The more specific your comments, the more useful
they will be. To ensure consideration of your comments on the proposal,
it is important that the Commission receive your comments on or before
5:00 p.m. Eastern Time on December 5, 2022.
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or <a href="/cdn-cgi/l/email-protection#81c7e4f3e2ceefede8efe4d2f4f1f1eef3f5c1e7e4f3e2afe6eef7"><span class="__cf_email__" data-cfemail="0c4a697e6f4362606562695f797c7c637e784c6a697e6f226b637a">[email protected]</span></a>. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to
FERC Online. This is an easy method for submitting brief, text-only
comments on a project;
(2) You can also file your comments electronically using the
eFiling feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the
link to FERC Online. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP22-
26) on your letter. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
Filing environmental comments will not give you intervenor status,
but you do not need intervenor status to have your comments considered.
Only intervenors have the right to seek rehearing or judicial review of
the Commission's decision. At this point in this proceeding, the
timeframe for filing timely intervention requests has expired. Any
person seeking to become a party to the proceeding must file a motion
to intervene out-of-time pursuant to Rule 214(b)(3) and (d) of the
Commission's Rules of Practice and Procedures (18 CFR 385.214(b)(3) and
(d)) and show good cause why the time limitation should be waived.
Motions to intervene are more fully described at <a href="https://www.ferc.gov/how-intervene">https://www.ferc.gov/how-intervene</a>.
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the eLibrary link. The eLibrary link
also provides access to the texts of all formal documents issued by the
Commission, such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to
register for eSubscription.
Dated: November 4, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-24529 Filed 11-9-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on November 10, 2022.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.