Kaukauna Utilities; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
August 4, 2022
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 149 (Thursday, August 4, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 149 (Thursday, August 4, 2022)]
[Notices]
[Pages 47738-47739]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-16713]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2715-026]
Kaukauna Utilities; Notice of Application Tendered for Filing
With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2715-026.
c. Date filed: July 22, 2022.
d. Applicant: Kaukauna Utilities.
e. Name of Project: Combined Locks Hydroelectric Project (Combined
Locks Project).
f. Location: On the Lower Fox River in the Village of Combined
Locks and the Village of Little Chute, Outagamie County, Wisconsin. The
project does not include any federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Zachary Moureau, Environmental & Compliance
Manager, Kaukauna Utilities, 777 Island Street, Kaukauna, WI 54130-
7077; (920) 462-0238; <a href="/cdn-cgi/l/email-protection#e79d8a889295828692a78c92cadb86c78f958281da" http: wi.org">wi.org</a>">zmoureau@ku-<a href="http://wi.org">wi.org</a></a>.
i. FERC Contact: Patrick Ely at <a href="/cdn-cgi/l/email-protection#04746570766d676f2a61687d44626176672a636b72"><span class="__cf_email__" data-cfemail="34445540465d575f1a51584d74525146571a535b42">[email protected]</span></a> or (202) 502-
8570.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: September 20, 2022.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. For assistance, please contact FERC Online Support
at <a href="/cdn-cgi/l/email-protection#a9efecfbeae6c7c5c0c7ccfadcd9d9c6dbdde9cfccdbca87cec6df"><span class="__cf_email__" data-cfemail="195f5c4b5a56777570777c4a6c6969766b6d597f7c6b7a377e766f">[email protected]</span></a>, (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, you may submit a paper
copy. Submissions sent via the U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent
via any other carrier must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first page of any filing should include
docket number P-2715-026.
m. The application is not ready for environmental analysis at this
time.
n. The Combined Locks Project consists of: (1) a concrete and
cyclopean stone dam approximately 654 feet long and 27 feet high with
additional 24 inch nominal flashboards mounted upon the
[[Page 47739]]
spillway crest at elevation 674.6 feet International Great Lakes Datum
of 1985 (IGLD85); (2) a 126.9-acre reservoir at normal full pool
elevation 676.7 feet IGLD85; (3) a powerhouse approximately 65 feet
wide by 130 feet long housing two 3.1-megawatt (MW) generators, for a
total authorized capacity of 6.2 MW; (4) a tailrace channel; (5) a 265-
foot-long, 4.16-kilovolt (kV) interconnection line from the powerhouse
to transformer and 1,442-foot-long, 12.47-kV interconnection line from
the transformer to the substation; and (6) appurtenant facilities.
o. A copy of the application may be viewed on the Commission's
website at <a href="http://www.ferc.gov">http://www.ferc.gov</a> using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. At this time, the Commission has
suspended access to the Commission's Public Reference Room, due to the
proclamation declaring a National Emergency concerning the Novel
Coronavirus Disease (COVID-19), issued by the President on March 13,
2020. For assistance, contact FERC Online Support.
You may also register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)--September 2022
Request Additional Information (if necessary)--September 2022
Issue Scoping Document 1 for comments--March 2023
Issue Scoping Document 2 (if necessary)--July 2023
Issue Notice of Ready for Environmental Analysis--July 2023
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: July 29, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-16713 Filed 8-3-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on August 4, 2022.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.