Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 148 (Wednesday, August 3, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 148 (Wednesday, August 3, 2022)]
[Notices]
[Page 47412]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-16593]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15278-000]
Rye Sutton Hydroelectric, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On June 6, 2022, Rye Sutton Hydroelectric, LLC, filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of
hydropower at the existing U.S. Army Corps of Engineers' (Corps) Sutton
Dam located on the Elk River in Braxton County, West Virginia. The sole
purpose of a preliminary permit, if issued, is to grant the permit
holder priority to file a license application during the permit term. A
preliminary permit does not authorize the permit holder to perform any
land-disturbing activities or otherwise enter upon lands or waters
owned by others without the owners' express permission.
The proposed Sutton Dam Hydroelectric Project would consist of the
following: (1) a new 40-foot-wide, 60-foot-long powerhouse to be
located downstream of the Corps dam along the southern bank; (2) a new
multiple-port intake structure against the upstream face of the dam;
(3) a new 12-foot-diameter, approximately 300-foot-long steel penstock;
(4) two turbine-generator units with a total generating capacity of 6
megawatts; (5) a new 100-foot-wide by 300-foot-long tailrace; (6) a new
substation with a step-up transformer; (7) a new 550-foot-long, 12-
kilovolt transmission line; and (8) appurtenant facilities. The
proposed project would have an estimated annual generation of 24,000
megawatt-hours.
Applicant Contact: Michael Rooney, Rye Development, LLC, 100 S.
Olive Street, West Palm Beach, FL 33401; phone: (412) 400-4186; Erik
Steimle, Rye Development, LLC, 100 S. Olive Street, West Palm Beach, FL
33401; phone: (503) 998-0230.
FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a>. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at <a href="https://ferconline.ferc.gov/QuickComment.aspx">https://ferconline.ferc.gov/QuickComment.aspx</a>. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#1c5a594e5f5372707572794f696c6c736e685c7a796e7f327b736a"><span class="__cf_email__" data-cfemail="7b3d3e293834151712151e280e0b0b14090f3b1d1e0918551c140d">[email protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's website at <a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>.
Enter the docket number (P-15278) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: July 28, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-16593 Filed 8-2-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on August 3, 2022.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.