Gas Transmission Northwest LLC; Notice of Availability of the Draft Environmental Impact Statement for the Proposed GTN Xpress Project
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
July 7, 2022
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 129 (Thursday, July 7, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 129 (Thursday, July 7, 2022)]
[Notices]
[Pages 40516-40517]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-14457]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-2-000]
Gas Transmission Northwest LLC; Notice of Availability of the
Draft Environmental Impact Statement for the Proposed GTN Xpress
Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a draft environmental impact statement (EIS)
for the GTN XPress Project (Project), proposed by Gas Transmission
Northwest LLC (GTN) in the above-referenced docket. GTN proposes to
modify existing compressor stations in Idaho, Washington, and Oregon.
This Project would increase the capacity of GTN's existing natural gas
transmission system by about 150 million standard cubic feet per day
between Idaho and Oregon. According to GTN, the Project is necessary to
serve the growing market demand its system is experiencing.
The draft EIS assesses the potential environmental effects of
modifying and installing new facilities at the existing compressor
stations in accordance with the requirements of the National
Environmental Policy Act (NEPA). The FERC staff concludes that approval
of the proposed Project, with the mitigation measures recommended in
the EIS, would result in some adverse environmental impacts, but none
that are considered significant. Regarding climate change impacts, this
EIS is not characterizing the Project's greenhouse gas emissions as
significant or insignificant because the Commission is conducting a
generic proceeding to determine whether and how the Commission will
conduct significance determinations going forward.\1\ The EIS also
concludes that no system or other alternative would meet the Project
objectives while providing a significant environmental advantage over
the Project as proposed.
---------------------------------------------------------------------------
\1\ Consideration of Greenhouse Gas Emissions in Natural Gas
Infrastructure Project Reviews, 178 FERC ] 61,108 (2022); 178 FERC ]
61,197 (2022).
---------------------------------------------------------------------------
The U.S. Environmental Protection Agency is participating as
cooperating agency in the preparation of the EIS. A cooperating agency
has jurisdiction by law or special expertise with respect to resources
potentially affected by the proposal and participates in the NEPA
analysis.
The Commission mailed a copy of the Notice of Availability of the
draft EIS to federal, state, and local government representatives and
agencies; elected officials; environmental and public interest groups;
Indian tribes; potentially affected landowners and other interested
individuals and groups; and newspapers and libraries in the Project
area. The draft EIS is only available in electronic format. It may be
viewed and downloaded from the FERC's website (<a href="http://www.ferc.gov">www.ferc.gov</a>), on the
natural gas environmental documents page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). In
addition, the draft EIS may be accessed by using the eLibrary link on
the FERC's website. Click on the eLibrary link (<a href="https://elibrary.ferc.gov/eLibrary/search">https://elibrary.ferc.gov/eLibrary/search</a>) select ``General Search'' and enter
the docket number in the ``Docket Number'' field, excluding the last
three digits (i.e. CP22-2). Be sure you have selected an appropriate
date range. For assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#bef8dbccddf1d0d2d7d0dbedcbceced1cccafed8dbccdd90d9d1c8"><span class="__cf_email__" data-cfemail="d197b4a3b29ebfbdb8bfb482a4a1a1bea3a591b7b4a3b2ffb6bea7">[email protected]</span></a> or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659.
The draft EIS is not a decision document. It presents Commission
staff's independent analysis of the environmental issues for the
Commission to consider when addressing the merits of all issues in this
proceeding. Any person wishing to comment on the draft EIS may do so.
Your comments should focus on the draft EIS' disclosure and discussion
of
[[Page 40517]]
potential environmental effects, reasonable alternatives, and measures
to avoid or lessen environmental impacts. To ensure consideration of
your comments on the proposal in the final EIS, it is important that
the Commission receive your comments on or before 5:00 p.m. Eastern
Time on August 22, 2022.
For your convenience, there are three methods you can use to submit
your comments to the Commission. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or <a href="/cdn-cgi/l/email-protection#c187a4b3a28eafada8afa492b4b1b1aeb3b581a7a4b3a2efa6aeb7"><span class="__cf_email__" data-cfemail="9ddbf8effed2f3f1f4f3f8cee8ededf2efe9ddfbf8effeb3faf2eb">[email protected]</span></a>. Please carefully follow these
instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to
FERC Online. This is an easy method for submitting brief, text-only
comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to
FERC Online. With eFiling, you can provide comments in a variety of
formats by attaching them as a file with your submission. New eFiling
users must first create an account by clicking on ``eRegister.'' If you
are filing a comment on a particular project, please select ``Comment
on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP22-2-
000) on your letter. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
Any person seeking to become a party to the proceeding must file a
motion to intervene pursuant to Rule 214 of the Commission's Rules of
Practice and Procedures (18 CFR part 385.214). Motions to intervene are
more fully described at <a href="https://www.ferc.gov/how-intervene">https://www.ferc.gov/how-intervene</a>. Only
intervenors have the right to seek rehearing or judicial review of the
Commission's decision. The Commission grants affected landowners and
others with environmental concerns intervenor status upon showing good
cause by stating that they have a clear and direct interest in this
proceeding which no other party can adequately represent. Simply filing
environmental comments will not give you intervenor status, but you do
not need intervenor status to have your comments considered.
Questions?
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (<a href="http://www.ferc.gov">www.ferc.gov</a>) using the eLibrary link. The eLibrary link
also provides access to the texts of all formal documents issued by the
Commission, such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to
register for eSubscription.
Dated: June 30, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022-14457 Filed 7-6-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>