Notice2022-14254

Notice of Segregation of Public Land for the Golden Currant Solar Project, Clark County, Nevada

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
July 5, 2022
Effective
July 5, 2022

Issuing agencies

Interior DepartmentLand Management Bureau

Abstract

Through this notice the Bureau of Land Management (BLM) is segregating public lands included in the right-of-way application for the Golden Currant Solar Project, from appropriation under the public land laws, including the Mining Law, but not the Mineral Leasing or Material Sales Acts, for a period of 2 years from the date of publication of this notice, subject to valid existing rights. This segregation is to allow for the orderly administration of the public lands to facilitate consideration of development of renewable energy resources. The public lands segregated by this notice totals 5,571.82 acres.

Full Text

<html>
<head>
<title>Federal Register, Volume 87 Issue 127 (Tuesday, July 5, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 127 (Tuesday, July 5, 2022)]
[Notices]
[Page 39866]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-14254]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

[LLNVS00000.L51010000.ER0000.LVRWF2108350.21X; N-100225; MO#4500162243]


Notice of Segregation of Public Land for the Golden Currant Solar 
Project, Clark County, Nevada

AGENCY: Bureau of Land Management, Department of Interior.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: Through this notice the Bureau of Land Management (BLM) is 
segregating public lands included in the right-of-way application for 
the Golden Currant Solar Project, from appropriation under the public 
land laws, including the Mining Law, but not the Mineral Leasing or 
Material Sales Acts, for a period of 2 years from the date of 
publication of this notice, subject to valid existing rights. This 
segregation is to allow for the orderly administration of the public 
lands to facilitate consideration of development of renewable energy 
resources. The public lands segregated by this notice totals 5,571.82 
acres.

DATES: This segregation for the lands identified in this notice is 
effective on July 5, 2022.

FOR FURTHER INFORMATION CONTACT: For further information and/or to have 
your name added to the mailing list, send requests to: Jessica Headen, 
Southern Nevada District Energy & Infrastructure Team, at telephone 
(702) 515-5206; address 4701 North Torrey Pines Drive, Las Vegas, NV 
89130-2301; or email <a href="/cdn-cgi/l/email-protection#e6a4aaabb9a8b0b9b5a8a2b9a3888394819fb694898c83859295a6848a8bc8818990"><span class="__cf_email__" data-cfemail="e0a2acadbfaeb6bfb3aea4bfa58e85928799b0928f8a85839493a0828c8dce878f96">[email&#160;protected]</span></a>. Individuals in 
the United States who are deaf, deafblind, hard of hearing, or have a 
speech disability may dial 711 (TTY, TDD, or TeleBraille) to access 
telecommunications relay services. Individuals outside the United 
States should use the relay services offered within their country to 
make international calls to the point-of-contact in the United States.

SUPPLEMENTARY INFORMATION: Regulations found at 43 CFR 2091.3-1(e) and 
2804.25(f) allow the BLM to temporarily segregate public lands within a 
right-of-way application area for solar energy development from the 
operation of the public land laws, including the Mining Law, by 
publication of a Federal Register notice. The BLM uses this temporary 
segregation authority to preserve its ability to approve, approve with 
modifications, or deny proposed rights-of-way, and to facilitate the 
orderly administration of the public lands. This temporary segregation 
is subject to valid existing rights, including existing mining claims 
located before this segregation notice. Licenses, permits, cooperative 
agreements, or discretionary land use authorizations of a temporary 
nature which would not impact lands identified in this notice may be 
allowed with the approval of an authorized officer of the BLM during 
the segregation period. The lands segregated under this notice are 
legally described as follows:

Mount Diablo Meridian, Nevada

T. 22 S., R. 55 E.,
    Sec. 2, S\1/2\NW\1/4\, and SW\1/4\;
    Sec. 3, SE\1/4\NE\1/4\, and E\1/2\SE\1/4\;
    Sec. 7, lots 3 and 4, E\1/2\SW\1/4\, and SE\1/4\;
    Sec. 8, S\1/2\;
    Sec. 9, S\1/2\;
    Sec. 10, NE\1/4\, SE\1/4\NW\1/4\, and SW\1/4\;
    Sec. 15, NW\1/4\NW\1/4\;
    Sec. 16, N\1/2\, SW\1/4\, N\1/2\SE\1/4\, and SW\1/4\SE\1/4\;
    Sec. 17 thru 20;
    Sec. 21, NW\1/4\, and NW\1/4\SW\1/4\;
    Sec. 29, N\1/2\NE\1/4\, SW\1/4\NE\1/4\, and NW\1/4\;
    Sec. 30, lot 1, NE\1/4\, and NE\1/4\NW\1/4\.

    The area described contains 5,571.82 acres, according to the 
official plats of the surveys of the said lands on file with the 
BLM.

    As provided in the regulations, the segregation of lands in this 
notice will not exceed 2 years from the date of publication unless 
extended for an additional 2 years through publication of a new notice 
in the Federal Register. The segregation period will terminate and the 
land will automatically reopen to appropriation under the public land 
laws, including the mining laws, at the earliest of the following 
dates: upon issuance of a decision by the authorized officer granting, 
granting with modifications, or denying the application for a right-of-
way; without further administrative action at the end of the 
segregation provided for in the Federal Register notice initiating the 
segregation; or upon publication of a Federal Register notice 
terminating the segregation.
    Upon termination of the segregation of these lands, all lands 
subject to this segregation would automatically reopen to appropriation 
under the public land laws, including the mining laws.
    Authority: 43 CFR 2091.3-1(e) and 43 CFR 2804.25(f).

Stephen Leslie,
Assistant Field Manager--Las Vegas Field Office.
[FR Doc. 2022-14254 Filed 7-1-22; 8:45 am]
BILLING CODE 4310-HC-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on July 5, 2022.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.