Notice2022-14109

Power Authority of the State of New York; Erie Boulevard Hydropower, L.P.; Notice of Intent To Prepare an Environmental Assessment

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
July 1, 2022

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 87 Issue 126 (Friday, July 1, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 126 (Friday, July 1, 2022)]
[Notices]
[Pages 39510-39511]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-14109]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3211-010; Project No. 2701-061]


Power Authority of the State of New York; Erie Boulevard 
Hydropower, L.P.; Notice of Intent To Prepare an Environmental 
Assessment

    On July 31, 2020, the Power Authority of the State of New York 
(NYPA) filed an application for a new major license for the 9-megawatt 
Hinckley (Gregory B.

[[Page 39511]]

Jarvis) Hydroelectric Project (Hinckley-Jarvis Project; FERC No. 3211). 
The Hinckley-Jarvis Project is located on West Canada Creek near the 
Hamlet of Hinckley in the counties of Oneida and Herkimer, New York. On 
February 26, 2021, Erie Boulevard Hydropower, L.P. (Erie) filed an 
application for a new major license for the 39.75-megawatt West Canada 
Creek Hydroelectric Project (West Canada Creek Project; FERC No. 2701). 
The West Canada Creek Project is also located on West Canada Creek, 
downstream of the Hinckley-Jarvis Project, in the counties of Oneida 
and Herkimer, New York. No federal or tribal lands occur within or 
adjacent to either project's boundary.
    In accordance with the Commission's regulations, on January 12, 
2022, Commission staff issued separate notices that both the Hinckley-
Jarvis and West Canada Creek projects were ready for environmental 
analysis (REA Notice).\1\ Based on the information in the projects' 
records, including comments filed on the REA Notices, staff does not 
anticipate that licensing the projects would constitute a major federal 
action significantly affecting the quality of the human environment. 
However, because the Hinckley-Jarvis and West Canada Creek projects are 
located adjacent to each other in the same river basin and include 
similar issues, it is the Commission's intent to continue to process 
these relicense applications concurrently. Therefore, staff intends to 
prepare a draft and final multi-project Environmental Assessment (EA) 
on the applications to relicense the Hinckley-Jarvis and West Canada 
Creek projects.
---------------------------------------------------------------------------

    \1\ On March 1, 2022, NYPA requested that the deadline for 
filing motions to intervene and protests, comments, recommendations, 
preliminary terms and conditions, and preliminary fishway 
prescriptions be extended until June 11, 2022, in order to allow 
parties to work on a settlement agreement. On March 3, 2022, Erie 
requested a similar extension. Commission staff granted both 
requests for extension in letters issued on March 10, 2022.
---------------------------------------------------------------------------

    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The applications will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Commission issues draft EA................  December 2022.
Comments due on draft EA..................  January 2023.
Commission issues final EA................  June 2023.\2\
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Emily Carter 
at (202) 502-6512 or <a href="/cdn-cgi/l/email-protection#cca9a1a5a0b5e2afadbeb8a9be8caaa9beafe2aba3ba"><span class="__cf_email__" data-cfemail="9afff7f3f6e3b4f9fbe8eeffe8dafcffe8f9b4fdf5ec">[email&#160;protected]</span></a>.
---------------------------------------------------------------------------

    \2\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare a draft and 
final EA for the Hinckley-Jarvis and West Canada Creek projects. 
Therefore, in accordance with CEQ's regulations, the final EA must 
be issued within 1 year of the issuance date of this notice.

    Dated: June 28, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-14109 Filed 6-30-22; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on July 1, 2022.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.