Proposed Rule2022-13470

Improvements to Generator Interconnection Procedures and Agreements

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
July 5, 2022

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Abstract

The Federal Energy Regulatory Commission (Commission) is issuing a Notice of Proposed Rulemaking (NOPR) proposing reforms to its pro forma Large Generator Interconnection Procedures, pro forma Small Generator Interconnection Procedures, pro forma Large Generator Interconnection Agreement, and pro forma Small Generator Interconnection Agreement to address interconnection queue backlogs, improve certainty, and prevent undue discrimination for new technologies. The reforms are intended to ensure that the generator interconnection process is just and reasonable and not unduly discriminatory or preferential. The Commission invites all interested persons to submit comments on the proposed reforms, including proposed revisions to the pro forma interconnection procedures and agreements, and in response to specific questions.

Full Text

<html>
<head>
<title>Federal Register, Volume 87 Issue 127 (Tuesday, July 5, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 127 (Tuesday, July 5, 2022)]
[Proposed Rules]
[Pages 39934-40032]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-13470]



[[Page 39933]]

Vol. 87

Tuesday,

No. 127

July 5, 2022

Part II





Department of Energy





-----------------------------------------------------------------------





Federal Energy Regulatory Commission





-----------------------------------------------------------------------





18 CFR Part 35





Improvements to Generator Interconnection Procedures and Agreements; 
Proposed Rule

Federal Register / Vol. 87, No. 127 / Tuesday, July 5, 2022 / 
Proposed Rules

[[Page 39934]]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

18 CFR Part 35

[Docket No. RM22-14-000]


Improvements to Generator Interconnection Procedures and 
Agreements

AGENCY: Federal Energy Regulatory Commission.

ACTION: Notice of proposed rulemaking.

-----------------------------------------------------------------------

SUMMARY: The Federal Energy Regulatory Commission (Commission) is 
issuing a Notice of Proposed Rulemaking (NOPR) proposing reforms to its 
pro forma Large Generator Interconnection Procedures, pro forma Small 
Generator Interconnection Procedures, pro forma Large Generator 
Interconnection Agreement, and pro forma Small Generator 
Interconnection Agreement to address interconnection queue backlogs, 
improve certainty, and prevent undue discrimination for new 
technologies. The reforms are intended to ensure that the generator 
interconnection process is just and reasonable and not unduly 
discriminatory or preferential. The Commission invites all interested 
persons to submit comments on the proposed reforms, including proposed 
revisions to the pro forma interconnection procedures and agreements, 
and in response to specific questions.

DATES: Comments are due October 13, 2022 and Reply Comments are due 
November 14, 2022.

ADDRESSES: Comments, identified by docket number, may be filed in the 
following ways. Electronic filing through <a href="https://www.ferc.gov">https://www.ferc.gov</a> is 
preferred.
    <bullet> Electronic Filing: Documents must be filed in acceptable 
native applications and print-to-PDF, but not in scanned or picture 
format.
    <bullet> For those unable to file electronically, comments may be 
filed by U.S. Postal Service mail or by hand (including courier) 
delivery.
    [cir] Mail via U.S. Postal Service only: Addressed to: Federal 
Energy Regulatory Commission, Office of the Secretary, 888 First Street 
NE, Washington, DC 20426.
    [cir] For delivery via any other carrier (including courier): 
Deliver to: Federal Energy Regulatory Commission, Office of the 
Secretary, 12225 Wilkins Avenue, Rockville, MD 20852.
    The Comment Procedures Section of this document contains more 
detailed filing procedures.

FOR FURTHER INFORMATION CONTACT: 

Tristan Kessler (Technical Information), Office of Energy Policy and 
Innovation, 888 First Street NE, Washington, DC 20426, (202) 502-6608, 
<a href="/cdn-cgi/l/email-protection#88fcfae1fbfce9e6a6e3edfbfbe4edfac8eeedfaeba6efe7fe"><span class="__cf_email__" data-cfemail="d2a6a0bba1a6b3bcfcb9b7a1a1beb7a092b4b7a0b1fcb5bda4">[email&#160;protected]</span></a>
Franklin Jackson (Technical Information), Office of Energy Market 
Regulation, 888 First Street NE, Washington, DC 20426, (202) 502-6464, 
<a href="/cdn-cgi/l/email-protection#87e1f5e6e9ecebeee9a9ede6e4ecf4e8e9c7e1e2f5e4a9e0e8f1"><span class="__cf_email__" data-cfemail="432531222d282f2a2d6d29222028302c2d03252631206d242c35">[email&#160;protected]</span></a>
Sarah Greenberg (Legal Information), Office of the General Counsel, 888 
First Street NE, Washington, DC 20426, (202) 502-6230, 
<a href="/cdn-cgi/l/email-protection#3f4c5e4d5e5711584d5a5a515d5a4d587f595a4d5c11585049"><span class="__cf_email__" data-cfemail="12617360737a3c756077777c7077607552747760713c757d64">[email&#160;protected]</span></a>

SUPPLEMENTARY INFORMATION:

Table of Contents

 
                                                               Paragraph
                                                                 Nos.
 
I. Introduction.............................................           1
    A. Background...........................................           7
        1. The Commission's Pro Forma Generator                        7
         Interconnection Procedures.........................
        2. 2008 Order on RTO/ISO Interconnection Queuing              12
         Practices..........................................
        3. Order No. 845....................................          13
        4. Transmission Planning and Cost Allocation ANOPR..          14
        5. Joint Federal-State Task Force on Electric                 16
         Transmission.......................................
    B. Need for Reform......................................          18
II. Proposed Reforms........................................          37
    A. Reforms To Implement a First-Ready, First-Served               37
     Cluster Study Process..................................
        1. Interconnection Information Access...............          40
        2. Cluster Study....................................          53
        3. Allocation of Cluster Study Costs................          80
        4. Allocation of Cluster Network Upgrade Costs......          84
        5. Shared Network Upgrades..........................          90
        6. Increased Financial Commitments and Readiness             102
         Requirements.......................................
        7. Transition Process...............................         149
    B. Reforms To Increase the Speed of Interconnection              161
     Queue Processing.......................................
        1. Elimination of the Reasonable Efforts Standard...         161
        2. Affected Systems.................................         174
        3. Optional Resource Solicitation Study.............         216
    C. Reforms To Incorporate Technological Advancements             238
     Into the Interconnection Process.......................
        1. Increasing Flexibility in the Generator                   238
         Interconnection Process............................
        2. Incorporating Alternative Transmission                    289
         Technologies Into the Generator Interconnection
         Process............................................
        3. Modeling and Performance Requirements for Non-            303
         Synchronous Generating Facilities..................
III. Proposed Compliance Procedures.........................         342
IV. Information Collection Statement........................         345
V. Environmental Analysis...................................         359
VI. Regulatory Flexibility Act..............................         360
VII. Comment Procedures.....................................         364
VIII. Document Availability.................................         368
Appendix A: Interconnection Study Metrics...................
Appendix B: Compilation of proposed changes to the pro forma
 LGIP.
Appendix C: Compilation of proposed changes to the pro forma
 SGIP.
Appendix D: Compilation of proposed changes to the pro forma
 LGIA.
Appendix E: Compilation of proposed changes to the pro forma
 SGIA.
 


[[Page 39935]]

I. Introduction

    1. Pursuant to our authority under section 206 of the Federal Power 
Act (FPA),\1\ we are proposing reforms in this Notice of Proposed 
Rulemaking (NOPR) to the Commission's pro forma Large Generator 
Interconnection Procedures (LGIP), pro forma Small Generator 
Interconnection Procedures (SGIP), pro forma Large Generator 
Interconnection Agreement (LGIA), and pro forma Small Generator 
Interconnection Agreement (SGIA) to address interconnection queue 
backlogs, improve certainty, and prevent undue discrimination for new 
technologies.
---------------------------------------------------------------------------

    \1\ 16 U.S.C. 824e. Section 206 of the FPA requires that 
whenever the Commission finds any rate, term, or condition for the 
transmission of electric energy in interstate commerce or the sale 
of such energy at wholesale in interstate commerce to be unjust, 
unreasonable, unduly discriminatory, or preferential, the Commission 
must establish a just and reasonable and not unduly discriminatory 
or preferential replacement rate, term, or condition.
---------------------------------------------------------------------------

    2. Nineteen years ago the Commission issued Order No. 2003,\2\ in 
which the Commission required all public utilities that own, control, 
or operate facilities used for transmitting electric energy in 
interstate commerce to have on file standard procedures and a standard 
agreement for interconnecting generating facilities larger than 20 MW 
(called the pro forma LGIP, and the pro forma LGIA).\3\ The Commission 
stated its expectation that the changes would prevent undue 
discrimination, preserve reliability, increase energy supply, and lower 
wholesale prices for customers by increasing the amount and variety of 
new generation that would compete in the wholesale electricity 
market.\4\ The Commission further stated that the standard procedures 
would facilitate market entry for generation competitors by reducing 
interconnection costs and time.\5\ In Order No. 2006,\6\ the Commission 
adopted standard procedures and a standard agreement for 
interconnecting generating facilities no larger than 20 MW (called the 
pro forma SGIP, and the pro forma SGIA), citing the same purposes 
outlined in Order No. 2003.\7\
---------------------------------------------------------------------------

    \2\ Standardization of Generator Interconnection Agreements & 
Proc., Order No. 2003, 68 FR 49845 (Aug. 19, 2003), 104 FERC ] 
61,103 (2003), order on reh'g, Order No. 2003-A, 69 FR 15932 (Mar. 
5, 2004), 106 FERC ] 61,220, order on reh'g, Order No. 2003-B, 70 FR 
265 (Jan. 19, 2005), 109 FERC ] 61,287 (2004), order on reh'g, Order 
No. 2003-C, 70 FR 37661 (July 18, 2005), 111 FERC ] 61,401 (2005), 
aff'd sub nom. Nat'l Ass'n of Regul. Util. Comm'rs v. FERC, 475 F.3d 
1277 (D.C. Cir. 2007) (NARUC v. FERC).
    \3\ Order No. 2003, 104 FERC ] 61,103 at P 2.
    \4\ Id. P 1.
    \5\ Id. P 12.
    \6\ Standardization of Small Generator Interconnection 
Agreements & Proc., Order No. 2006, 70 FR 34189 (June 13, 2005), 111 
FERC ] 61,220, order on reh'g, Order No. 2006-A, 70 FR 71760 (Nov. 
30, 2005), 113 FERC ] 61,195 (2005), order granting clarification, 
Order No. 2006-B, 71 FR 42587 (July 27, 2006), 116 FERC ] 61,046 
(2006).
    \7\ Order No. 2006, 111 FERC ] 61,220 at PP 15, 36.
---------------------------------------------------------------------------

    3. The electricity sector has transformed significantly since the 
issuance of Order Nos. 2003 and 2006. The growth of new resources 
seeking to interconnect to the transmission system and the differing 
characteristics of those resources have created new challenges for the 
generator interconnection process. These new challenges are creating 
large interconnection queue backlogs and uncertainty regarding the cost 
and timing of interconnecting to the transmission system, potentially 
increasing costs for consumers. Backlogs in the generator 
interconnection process, in turn, can create reliability issues as 
needed new generating facilities are unable to come online in an 
efficient and timely manner. Therefore, we believe that it may be 
appropriate to reform the Commission's standard interconnection 
procedures and agreements to ensure that interconnection customers are 
able to interconnect to the transmission system in a reliable, 
efficient, transparent, and timely manner, thereby ensuring that rates, 
terms, and conditions for Commission-jurisdictional services remain 
just and reasonable and not unduly discriminatory or preferential.
    4. Accordingly, we propose in this NOPR reforms to the Commission's 
pro forma LGIP and pro forma LGIA. Specifically, as explained in detail 
in this NOPR, we propose reforms to: (1) implement a first-ready, 
first-served cluster study process; \8\ (2) increase the speed of 
interconnection queue processing; and (3) incorporate technological 
advancements into the interconnection process.
---------------------------------------------------------------------------

    \8\ A first-ready, first-served cluster study process includes 
the following elements: increased access to information prior to 
entering the queue; a mechanism to study interconnection requests in 
groups; and increased financial commitments and readiness 
requirements to enter and proceed through the queue. To contrast, 
the existing first-come, first-served serial study process assigns 
interconnection requests an individual queue position based solely 
on the date of entry into the queue and does not include access to 
information prior to entering the queue.
---------------------------------------------------------------------------

    5. We also propose reforms to the pro forma SGIP and pro forma 
SGIA. Specifically, as explained in detail in this NOPR, for small 
generators we propose reforms to incorporate alternative transmission 
technologies into the interconnection process and to provide modeling 
and performance requirements for non-synchronous generators. In 
addition, we seek comment on whether the other reforms proposed in this 
NOPR should be applied to the pro forma SGIP and pro forma SGIA.
    6. We recognize that transmission providers have undertaken efforts 
to address interconnection queue management issues. This NOPR is not 
intended to divert or slow the potential progress represented by those 
efforts. We will review any filings that result from those efforts 
based on the record before us in those proceedings and not based on 
whether they comply with the proposed reforms in this NOPR. We note 
that any compliance obligations arising out of any final rule in this 
docket on the issues addressed herein will be evaluated in light of the 
independent entity variation for RTO/ISO regions and the consistent 
with or superior to standard for non-RTO regions.

A. Background

1. The Commission's Pro Forma Generator Interconnection Procedures
    7. In Order No. 2003, the Commission recognized a need for a 
standard set of interconnection procedures for transmission providers 
\9\ and a single, uniformly applicable interconnection agreement for 
large generating facilities.\10\ The Commission noted that generator 
interconnection is a ``critical component of open access transmission 
service and thus is subject to the requirement that utilities offer 
comparable service under the [pro forma] OATT.'' \11\ The Commission 
found that it was appropriate to establish a standard set of generator 
interconnection procedures to

[[Page 39936]]

``minimize opportunities for undue discrimination and expedite the 
development of new generation, while protecting reliability and 
ensuring that rates are just and reasonable.'' \12\ To this end, the 
Commission adopted the pro forma LGIP and pro forma LGIA and amended 
its regulations to require all transmission providers to incorporate 
these standard procedures and agreement into their OATTs.\13\
---------------------------------------------------------------------------

    \9\ In this order, transmission provider ``shall mean the public 
utility (or its designated agent) that owns, controls, or operates 
transmission or distribution facilities used for the transmission of 
electric energy in interstate commerce and provides transmission 
service under the [Transmission Provider's Tariff]. The term . . . 
should be read to include the Transmission Owner when the 
Transmission Owner is separate from the Transmission Provider.'' Pro 
forma LGIP section 1; pro forma LGIA art. 1; pro forma SGIP attach. 
1; pro forma SGIA attach. 1. Therefore, unless otherwise noted, 
``transmission provider'' refers only to public utility transmission 
providers. FPA section 201(e) defines ``public utility'' to mean 
``any person who owns or operates facilities subject to the 
jurisdiction of the Commission under this subchapter.'' 16 U.S.C. 
824(e). A non-public utility that seeks voluntary compliance with 
the reciprocity condition of an Open Access Transmission Tariff 
(OATT) may satisfy that condition by filing an OATT, which includes 
the pro forma LGIP, the pro forma SGIP, the pro forma LGIA, and the 
pro forma SGIA. See Order No. 2003, 104 FERC ] 61,103 at PP 1, 616; 
Order No. 2006, 111 FERC ] 61,220 at P 1.
    \10\ Order No. 2003, 104 FERC ] 61,103 at P 11. Large generating 
facilities are defined to mean ``a Generating Facility having a 
Generating Facility Capacity of more than 20 MW.'' Pro forma LGIP 
section 1.
    \11\ Order No. 2003, 104 FERC ] 61,103 at P 9 (citing Tenn. 
Power Co., 90 FERC ] 61,238 (2000)).
    \12\ Id. P 11.
    \13\ 18 CFR 35.28(f)(1).
---------------------------------------------------------------------------

    8. To initiate the generator interconnection process set forth in 
the Commission's pro forma LGIP,\14\ the interconnection customer 
submits an interconnection request for its proposed generating facility 
that includes preliminary documentation of the site of the proposed 
generating facility, certain technical information about the proposed 
generating facility, and the expected commercial operation date of the 
proposed generating facility, along with a refundable deposit of 
$10,000.\15\ After the transmission provider determines that the 
interconnection request is complete, the interconnection request enters 
the transmission provider's interconnection queue with other pending 
interconnection requests and is assigned a queue position based on the 
time and date of its receipt.\16\ The queue position determines the 
order in which the transmission provider studies the interconnection 
requests in its queue.\17\
---------------------------------------------------------------------------

    \14\ While we provide a broad description of the process in the 
Commission's pro forma LGIP as background here, we recognize that 
many transmission providers have adopted (and the Commission has 
accepted) variations to many of the terms in the Commission's pro 
forma LGIP and pro forma LGIA. Consequently, some or many of the 
details of a particular transmission provider's generator 
interconnection procedures may vary considerably from the broad 
description provided here.
    \15\ Order No. 2003, 104 FERC ] 61,103 at P 35; pro forma LGIP 
sections 3.1, 3.4.
    \16\ Pro forma LGIP section 4.1.
    \17\ Id.
---------------------------------------------------------------------------

    9. Transmission providers must schedule a scoping meeting with the 
interconnection customer to discuss possible points of interconnection 
for the proposed generating facility and exchange technical 
information, which is followed by a series of interconnection studies 
to evaluate the proposed interconnection in detail.\18\ Transmission 
providers study interconnection requests in three phases: (1) the 
Interconnection Feasibility Study (feasibility study); \19\ (2) the 
Interconnection System Impact Study (system impact study); \20\ and (3) 
the Interconnection Facilities Study (facilities study).\21\ These 
studies contain the power flow, short circuit, and stability analyses 
necessary to: (1) identify any adverse impacts on the transmission 
providers' transmission system or any affected systems; \22\ (2) 
determine the interconnection facilities and network upgrades \23\ 
needed to reliably interconnect the generating facility; and (3) 
estimate the interconnection customer's cost responsibility for these 
facilities.\24\ The pro forma LGIP requires that transmission providers 
use reasonable efforts to complete: (1) feasibility studies within 45 
days; (2) system impact studies within 90 days; and (3) facilities 
studies within 90 or 180 days, depending on the interconnection 
customer's requested accuracy margin.\25\
---------------------------------------------------------------------------

    \18\ Order No. 2003, 104 FERC ] 61,103 at P 36; pro forma LGIP 
sections 3.4.4; 6-8.
    \19\ The pro forma LGIP defines a feasibility study as ``a 
preliminary evaluation of the system impact and cost of 
interconnecting the Generating Facility to the Transmission 
Provider's Transmission System.'' The scope of a feasibility study 
is described in section 6 of the pro forma LGIP. Pro forma LGIP 
sections 1, 6.
    \20\ The pro forma LGIP defines a system impact study as ``an 
engineering study that evaluates the impact of the proposed 
interconnection on the safety and reliability of Transmission 
Provider's Transmission System and, if applicable, an Affected 
System.'' In particular, a system impact study identifies and 
details ``the system impacts that would result if the Generating 
Facility were interconnected without project modifications or system 
modifications, focusing on the Adverse System Impacts identified in 
the [feasibility study], or to study potential impacts, including 
but not limited to those identified in the Scoping Meeting.'' Id. 
section 1.
    \21\ The pro forma LGIP defines a facilities study as ``a study 
conducted by the Transmission Provider or a third-party consultant 
for the Interconnection Customer to determine a list of facilities 
(including Transmission Provider's Interconnection Facilities and 
Network Upgrades as identified in the [system impact study]), the 
cost of those facilities, and the time required to interconnect the 
Generating Facility with the Transmission Provider's Transmission 
System.'' The scope of a facilities study is described in section 8 
of the pro forma LGIP. Id. sections 1, 8.
    \22\ An affected system is an electric system other than the 
transmission provider's transmission system that may be affected by 
the proposed interconnection. Id. section 1; pro forma LGIA art. 1.
    \23\ For purposes of this NOPR, unless otherwise noted, 
``network upgrades'' refers to interconnection-related network 
upgrades. More specifically, the pro forma LGIP and pro forma LGIA 
state that ``Network Upgrades shall mean the additions, 
modifications, and upgrades to the Transmission Provider's 
Transmission System required at or beyond the point at which the 
Interconnection Facilities connect to the Transmission Provider's 
Transmission System to accommodate the interconnection of the Large 
Generating Facility to the Transmission Provider's Transmission 
System.'' Pro forma LGIP section 1 (Definitions); pro forma LGIA 
art. 1 (Definitions).
    \24\ Order No. 2003, 104 FERC ] 61,103 at PP 35-37; pro forma 
LGIP sections 6-8. The interconnection customer is responsible for 
the actual costs of interconnection studies and any necessary re-
studies. Pro forma LGIP section 13.3.
    \25\ Id. sections 6.3, 7.4, 8.3.
---------------------------------------------------------------------------

    10. At the completion of the facilities study, the pro forma LGIP 
requires the transmission provider to issue a report on the best 
estimate of the costs to effectuate the requested interconnection and 
provide a draft generator interconnection agreement to the 
interconnection customer.\26\ If the interconnection customer wishes to 
proceed, after negotiations, the interconnection customer enters into a 
generator interconnection agreement with the transmission provider or, 
in specific circumstances, requests that the transmission provider file 
the agreement with the Commission unexecuted.\27\ The transmission 
provider is responsible for the construction of all network upgrades, 
but, as further discussed below, the interconnection customer has the 
option to build these facilities in certain circumstances.\28\
---------------------------------------------------------------------------

    \26\ Order No. 2003, 104 FERC ] 61,103 at P 38. Section 11.1 of 
the pro forma LGIP requires the transmission provider to tender a 
draft LGIA to the interconnection customer ``in the form of 
Transmission Provider's FERC-approved standard form LGIA.''
    \27\ If the transmission provider and interconnection customer 
execute an LGIA that conforms to the transmission provider's FERC-
approved standard form LGIA, the agreement does not need to be filed 
with the Commission (if the transmission provider has such a 
standard form LGIA on file and submits an Electronic Quarterly 
Report). Alternatively, the transmission provider must file an LGIA 
with the Commission for review and approval if: (1) the 
interconnection customer determines that negotiations with the 
transmission provider over the terms of an LGIA are at an impasse 
and requests submission of the unexecuted LGIA with the Commission; 
or (2) the LGIA does not conform to the transmission provider's 
FERC-approved standard form LGIA. See Order No. 2003-A, 106 FERC ] 
61,220 at P 201; pro forma LGIP sections 11.2-11.3.
    \28\ Order No. 2003, 104 FERC ] 61,103 at PP 351-354; pro forma 
LGIA art. 5.1.3.
---------------------------------------------------------------------------

    11. Similar to Order No. 2003, in Order No. 2006, the Commission 
recognized the need for standardized interconnection procedures and 
agreements for small generating facilities with a capacity of 20 MW or 
less.\29\ In addition to establishing a pro forma interconnection study 
process for small generating facilities similar to the process for 
large generation established in Order No. 2003, the Commission 
included: (1) a ``Fast Track Process'' \30\ that uses technical screens 
to evaluate a certified small generating facility no larger than 2 MW; 
and (2) a ``10 kW Inverter Process'' \31\ that uses the same technical 
screens to evaluate a certified inverter-based small generating 
facility no larger than 10 kW.\32\ The Commission later issued Order 
No.

[[Page 39937]]

792,\33\ in which the Commission revised the pro forma SGIP and pro 
forma SGIA to provide for interconnection customers to receive point of 
interconnection information in advance of submitting an interconnection 
request, increase the threshold for participation in the Fast Track 
Process to 5 MW, and to specifically include electric storage 
devices.\34\
---------------------------------------------------------------------------

    \29\ Order No. 2006, 111 FERC ] 61,220 at P 36.
    \30\ Pro forma SGIP section 2.1.
    \31\ Id. attach. 5.
    \32\ Order No. 2006, 111 FERC ] 61,220 at PP 36, 38-39.
    \33\ Small Generator Interconnection Agreements & Procs., Order 
No. 792, 78 FR 73240 (Dec. 5, 2013), 145 FERC ] 61,159 (2013), 
clarifying, Order No. 792-A, 146 FERC ] 61,214 (2014).
    \34\ See Order No. 792, 145 FERC ] 61,159 at P 1.
---------------------------------------------------------------------------

2. 2008 Order on RTO/ISO Interconnection Queuing Practices
    12. In response to concerns voiced to the Commission about 
interconnection queue management, in 2007, the Commission held a 
technical conference,\35\ and later issued an order \36\ addressing 
interconnection queue issues in RTOs/ISOs. In the order, the Commission 
noted that some transmission providers were not processing their 
interconnection queues within the timelines established in the pro 
forma LGIP, and in certain cases, were greatly exceeding them.\37\ The 
Commission stated that, although it ``may need to [impose solutions] if 
the RTOs and ISOs do not act themselves,'' each RTO/ISO would have an 
opportunity to work with its stakeholders to develop its own 
solutions.\38\ As further discussed below, following the order, 
multiple RTOs/ISOs submitted queue reform proposals to the Commission, 
some of which moved away from a so-called ``first-come, first-served'' 
approach (whereby interconnection requests are processed in the order 
they are received) to a so-called ``first-ready, first-served'' 
approach (whereby interconnection requests are processed based on when 
interconnection customers meet certain project development 
milestones).\39\
---------------------------------------------------------------------------

    \35\ Interconnection Queuing Practices, Docket No. AD08-2-000, 
Notice of Technical Conference (issued Nov. 2, 2007).
    \36\ Interconnection Queuing Practices, 122 FERC ] 61,252 (2008) 
(2008 Technical Conference Order).
    \37\ Id. P 3.
    \38\ Id. P 8.
    \39\ See, e.g., Sw. Power Pool, Inc., 128 FERC ] 61,114 (2009) 
(SPP); Midwest Ind. Sys. Operator, Inc., 124 FERC ] 61,183 (2008); 
Cal. Ind. Sys. Operator Corp., 124 FERC ] 61,292 (2008).
---------------------------------------------------------------------------

3. Order No. 845
    13. In 2018, the Commission issued Order No. 845,\40\ in which the 
Commission made the most comprehensive revisions to the pro forma LGIP 
and pro forma LGIA since their adoption in Order No. 2003. In Order No. 
845, the Commission concluded that reforms to the pro forma LGIP and 
pro forma LGIA were needed to mitigate concerns regarding systemic 
inefficiencies, remedy discriminatory practices, and address recent 
developments, including changes in the resource mix and emergence of 
new technologies.\41\ The Commission therefore adopted reforms designed 
to improve certainty for interconnection customers, promote more 
informed interconnection decisions, and enhance the generator 
interconnection process.\42\ Among other things, the Commission: (1) 
expanded the interconnection customer's option to build certain network 
upgrades; (2) revised the definition of generating facility to include 
electric storage resources; \43\ (3) established reporting requirements 
for aggregate interconnection study performance; (4) allowed 
interconnection customers to request a level of interconnection service 
that is lower than their generating facility capacity; (5) required 
transmission providers to allow provisional interconnection service 
that provides for limited operation of a generating facility prior to 
completion of the full generator interconnection process; (6) required 
transmission providers to create a process for interconnection 
customers to use surplus interconnection service \44\ at existing 
points of interconnection; and (7) required transmission providers to 
assess and, if necessary, study, an interconnection customer's 
technology changes without affecting the interconnection customer's 
queue position.\45\
---------------------------------------------------------------------------

    \40\ Reform of Generator Interconnection Procs & Agreements, 
Order No. 845, 83 FR 21342 (May 09, 2018), 163 FERC ] 61,043 (2018), 
order on reh'g, Order No. 845-A, 166 FERC ] 61,137, 84 FR 8156 (Mar. 
06, 2019), order on reh'g, Order No. 845-B, 168 FERC ] 61,092 
(2019).
    \41\ Order No. 845, 163 FERC ] 61,043 at P 7.
    \42\ Id. P 2.
    \43\ Generating Facilities ``shall mean Interconnection 
Customer's device for the production and/or storage for later 
injection of electricity identified in the Interconnection Request, 
but shall not include the Interconnection Customer's Interconnection 
Facilities.'' Pro forma LGIP section 1.
    \44\ The pro forma LGIP defines surplus interconnection service 
as ``any unneeded portion of Interconnection Service established in 
a Large Generator Interconnection Agreement, such that if Surplus 
Interconnection Service is utilized the total amount of 
Interconnection Service at the Point of Interconnection would remain 
the same.'' Pro forma LGIP section 1.
    \45\ Order No. 845, 163 FERC ] 61,043 at PP 3-5.
---------------------------------------------------------------------------

4. Transmission Planning and Cost Allocation ANOPR
    14. On July 15, 2021, the Commission issued an Advance Notice of 
Proposed Rulemaking (ANOPR) in Docket No. RM21-17-000, presenting 
potential reforms to the Commission's requirements governing the 
regional transmission planning and cost allocation and generator 
interconnection processes.\46\ Specific to the generator 
interconnection process, the Commission sought comment on whether and 
which reforms may be necessary to ensure a more purposeful integration 
of the generator interconnection process with the regional transmission 
planning and cost allocation processes, establish a faster and more 
efficient interconnection queueing process, and promote a more 
efficient and cost-effective allocation of interconnection-related 
network upgrade costs.\47\ For instance, the Commission noted that the 
cost of interconnection-related network upgrades can depend largely on 
both the timing of when the interconnection customer enters the 
interconnection queue and where the interconnection customer proposes 
to interconnect its generating facility. Therefore, the Commission 
noted, interconnection customers may submit multiple interconnection 
requests in an effort to determine the most favorable point of 
interconnection \48\ that minimizes their interconnection-related 
network upgrade costs.\49\ The Commission stated that this practice, in 
turn, may lead to late-stage withdrawals of the excess interconnection 
requests, which can then impede the transmission provider's ability to 
process its interconnection queue in an efficient manner. As a result, 
the Commission stated that it may be time to consider reforms to 
generator interconnection process that would make them more efficient 
and ensure that generation facilities that are more ``ready'' than 
others are not unduly delayed in the interconnection queue.
---------------------------------------------------------------------------

    \46\ Bldg. for the Future Through Elec. Reg'l Transmission Plan. 
& Cost Allocation & Generator Interconnection, 86 FR 40266 (July 15, 
2021), 176 FERC ] 61,024 (2021) (ANOPR).
    \47\ Id. P 5.
    \48\ Point of Interconnection refers to ``the point, as set 
forth in Appendix A to the Standard Large Generator Interconnection 
Agreement, where the Interconnection Facilities connect to the 
Transmission Provider's Transmission System.'' Pro forma LGIP 
section 1.
    \49\ ANOPR, 176 FERC ] 61,024 at P 41.
---------------------------------------------------------------------------

    15. On April 21, 2022, the Commission issued a Notice of Proposed 
Rulemaking (Transmission Planning and Cost Allocation NOPR) proposing 
reforms to its existing regional transmission planning and cost 
allocation requirements in the same proceeding as it issued the ANOPR. 
While the Transmission Planning and Cost Allocation NOPR did not 
address many of the concerns raised by the Commission in the ANOPR with 
respect

[[Page 39938]]

to the generator interconnection queue process, the Commission noted in 
the Transmission NOPR that it would continue to review the record and 
that it expected to address possible inadequacies through subsequent 
proceedings that propose reforms, as warranted, related to that 
topic.\50\ We are now taking that next step with the reforms we propose 
in this NOPR.
---------------------------------------------------------------------------

    \50\ Bldg. for the Future Through Elec. Reg'l Transmission Plan. 
& Cost Allocation & Generator Interconnection, 87 FR 26504 (May 04, 
2022), 179 FERC ] 61,028, at P 10 (2022) (Transmission Planning and 
Cost Allocation NOPR).
---------------------------------------------------------------------------

5. Joint Federal-State Task Force on Electric Transmission
    16. On June 17, 2021, the Commission established a Joint Federal-
State Task Force on Electric Transmission (Task Force) to formally 
explore broad categories of transmission-related topics.\51\ The 
Commission explained that the development of new transmission 
infrastructure implicates a host of different issues, including 
generator interconnection. The Task Force is comprised of all FERC 
Commissioners as well as representatives from 10 state commissions 
nominated by the National Association of Regulatory Utility 
Commissioners (NARUC), with two originating from each NARUC region.\52\ 
The Task Force will convene for multiple formal meetings and has thus 
far met three times--on November 10, 2021, on February 16, 2022, and on 
May 6, 2022.
---------------------------------------------------------------------------

    \51\ Joint Fed.-State Task Force on Elec. Transmission, 175 FERC 
] 61,224, at PP 1, 6 (2021).
    \52\ An up-to-date list of Task Force members, as well as 
additional information on the Task Force, is available on the 
Commission's website at: <a href="https://www.ferc.gov/TFSOET">https://www.ferc.gov/TFSOET</a>. Public 
materials related to the Task Force, including transcripts from 
public meetings, are available in the Commission's eLibrary in 
Docket No. AD21-15-000.
---------------------------------------------------------------------------

    17. The discussion at the May meeting focused on interconnection 
issues, including generator interconnection queue processes and 
backlogs. The Task Force Members discussed: the primary challenges 
preventing more efficient processing of interconnection queues; 
specific improvements to interconnection processes (such as tighter 
applicant requirements to enter and remain in the queue, clustering, 
fast tracking, tighter deadlines on transmission providers completing 
studies, and minimizing reiterative studies); and how to balance near 
term improvements to the interconnection procedures with longer-term 
regional transmission planning and development.\53\
---------------------------------------------------------------------------

    \53\ Joint Fed.-State Task Force on Elec. Transmission, Notice 
of Meeting, Docket No. AD21-15-000 (issued Apr. 22, 2022) (attaching 
agenda).
---------------------------------------------------------------------------

B. Need for Reform

    18. Under the Commission's pro forma LGIP, the interconnection 
study process for large generating facilities is a serial first-come, 
first-served study process by which transmission providers study 
interconnection requests individually in the order the transmission 
provider received them.\54\ The Commission adopted these procedures at 
a time when most interconnection requests were for large traditional 
generating facilities that would use readily available transmission 
capacity. In the 2008 Technical Conference Order, the Commission 
acknowledged that, while the generator interconnection process set 
forth in the pro forma LGIP made sense at the time that the Commission 
adopted it, it has since led to some unexpected consequences, 
particularly for transmission systems with numerous interconnection 
customers and limited excess transmission capacity.\55\ The Commission 
also explained that surges in the volume of new types of generating 
facilities, principally renewable generation, were placing stress on 
interconnection queue management because such generating facilities can 
be constructed and placed into operation more quickly than traditional 
types of generating facilities. The increase in the number of 
interconnection requests and limited transmission capacity have not 
subsided since the issuance of the 2008 Technical Conference Order. 
Although in Order No. 845, the Commission attempted to address 
interconnection queue backlogs,\56\ the interconnection queue backlog 
has persisted and worsened. Indeed, as of the end of 2021, there were 
over 8,100 active interconnection requests in interconnection queues 
throughout the United States, representing over 1,000 GW of generation 
and an estimated 420 GW of electric storage.\57\ This is more than 
triple the total volume, in gigawatts, of generation and electric 
storage in interconnection queues nationwide just five years 
earlier.\58\
---------------------------------------------------------------------------

    \54\ Pro forma LGIP section 4.1.
    \55\ 2008 Technical Conference Order, 122 FERC ] 61,252 at P 15.
    \56\ Order No. 845, 163 FERC ] 61,043 at P 24.
    \57\ Joseph Rand et al., Lawrence Berkeley Nat'l Lab'y, Queued 
Up: Characteristics of Power Plants Seeking Transmission 
Interconnection as of the End of 2021, at 26 (Apr. 2022), <a href="https://emp.lbl.gov/sites/default/files/queued_up_2021_04-13-2022.pdf">https://emp.lbl.gov/sites/default/files/queued_up_2021_04-13-2022.pdf</a> 
(Queued Up).
    \58\ See Ryan Wiser et al., Lawrence Berkeley Nat'l Lab'y, Wind 
Energy Techs. Office, Land-Based Wind Market Report: 2021 Edition, 
at 10 (Aug. 2021), <a href="https://www.energy.gov/eere/wind/articles/land-based-wind-market-report-2021-edition-released">https://www.energy.gov/eere/wind/articles/land-based-wind-market-report-2021-edition-released</a>.
---------------------------------------------------------------------------

    19. The continued use of the Commission's pro forma LGIP in the 
face of dramatic increases in interconnection requests is leading to a 
growing backlog of interconnection requests for many transmission 
providers. Based on Commission staff's compilation of information 
posted by transmission providers for 2021, nationwide, almost 1,900 
interconnection requests were awaiting interconnection studies that had 
not been performed as of the tariff-defined deadline.\59\ These 
interconnection queue backlogs and study delays create uncertainty and 
inhibit project developers' ability to interconnect generating 
facilities to the transmission system.\60\ In addition, as 
interconnection studies fall behind, the amount of time subsequent 
interconnection requests spend in the interconnection queue rises.\61\
---------------------------------------------------------------------------

    \59\ See app. A (compiling data publicly posted by transmission 
providers in compliance with Order No. 845); see also Order No. 845, 
163 FERC ] 61,043 at P 305. This is based on informational reports 
submitted by transmission providers in compliance with Order No. 
845.
    \60\ See Joint Fed.-State Task Force on Elec. Transmission, 
Technical Conference, Docket No. AD21-15-000, Tr. 15:21-16:1 (Ted 
Thomas) (May 6, 2022) (May Joint Task Force Tr.) (``Houston, we have 
a problem. As stated in the NARUC ANOPR comments, existing methods 
for interconnecting new resources to the transmission grid are 
inadequate and inefficient because of the time necessary to 
interconnect new resources and the corresponding network upgrade 
costs.'').
    \61\ For the four RTOs/ISOs (California Independent System 
Operator Corporation (CAISO), Electric Reliability Council of Texas 
(ERCOT), New York Independent System Operator, Inc. (NYISO), and PJM 
Interconnection, L.L.C (PJM) and one utility (Arizona Public Service 
Company)) for which data was available, the average time projects 
spent in interconnection queues before being constructed increased 
from ~2.1 years for projects built between 2000 and 2010 to ~3.7 
years for those built between 2011 and 2021. Queued Up at 3. As of 
the end of 2021, only 13% of total capacity in interconnection 
queues had an executed generator interconnection agreement. Id. at 
17. See also May Joint Task Force Tr. 23:18-25 (Jason Stanek) 
(expressing frustration with the status quo and agreement that it is 
``no longer tenable'' considering the inability of generators to 
interconnect in a timely manner, e.g., there are ``2,500 projects 
under study [in the MACRUC region] and about a half of them have 
been in the queue since at least 2001'').
---------------------------------------------------------------------------

    20. Numerous factors appear to contribute to these interconnection 
queue backlogs. Increasing volumes of interconnection requests are 
entering the interconnection queue due to a confluence of the rapidly 
changing

[[Page 39939]]

resource mix,\62\ market forces,\63\ and emerging technologies.\64\ At 
the same time, available transmission capacity appears to have been 
exhausted in many regions. As the Commission observed in the 
Transmission Planning and Cost Allocation NOPR, ``[t]he evidence 
suggests that long-term regional transmission planning and cost 
allocation to identify and plan for transmission needs . . . is not 
occurring in most transmission planning regions on a regular or 
consistent basis.'' \65\ Instead, the Commission added, significant 
transmission expansion appears to be happening in an incremental 
fashion, in response to individual interconnection requests.\66\ This 
reactive approach to transmission expansion adds to the challenge many 
proposed projects face to successfully complete the interconnection 
queue process and reach commercial operation. Therefore, the number of 
projects waiting in the interconnection queue is increasing. Further, 
transmission providers report that there is a nationwide shortage of 
qualified engineers to keep pace with the increasing number of 
interconnection requests in the queue and associated interconnection 
studies.\67\ Many, if not all, of these drivers are either ongoing or 
increasing. Thus, we are concerned that, without reforms to the 
generator interconnection process, existing interconnection queue 
backlogs are likely to intensify.
---------------------------------------------------------------------------

    \62\ Corporations purchased over 30 GW of clean energy through 
power purchase agreements in 2021, up nearly 24% from 2020. U.S.-
based purchases represented 17 GW of the power purchase agreements 
executed in 2021. Bloomberg New Energy Finance, Corporate Clean 
Energy Buying Tops 30GW Mark in Record Year (Jan. 31, 2022), https:/
/about.bnef.com/blog/corporate-clean-energy-buying-tops-30gw-mark-
in-record-year/
#:~:text=Corporate%20Clean%20Energy%20Buying%20Tops%2030GW%20Mark%20i
n%20Record%20Year,-
January%2031%2C%202022&text=New%20York%20and%20London%2C%20January,re
search%20firm%20BloombergNEF%20 (BNEF).
    \63\ From 2009 to 2021, the levelized cost of energy from 
unsubsidized utility scale wind and solar photovoltaic facilities 
dropped 72% and 90%, respectively. Lazard, Lazard's Levelized Cost 
of Energy Analysis--Version 15.0, at 9 (Oct. 2021), <a href="https://www.lazard.com/perspective/levelized-cost-of-energy-levelized-cost-of-storage-and-levelized-cost-of-hydrogen/">https://www.lazard.com/perspective/levelized-cost-of-energy-levelized-cost-of-storage-and-levelized-cost-of-hydrogen/</a> (Lazard's LCOE).
    \64\ For instance, 42% (285 GW) of solar and 8% (17 GW) of wind 
projects currently in the queue include are proposed as hybrid 
resources including electric storage. Queued Up at 18.
    \65\ Transmission Planning and Cost Allocation NOPR, 179 FERC ] 
61,028 at P 36.
    \66\ Id.
    \67\ For example, CAISO stated in its recent proposal to extend 
its interconnection study deadlines to accommodate its 
interconnection queue cluster 14 that neither CAISO nor the 
participating transmission owners could increase staffing as few 
experts are available to hire. Cal. Indep. Sys. Operator Corp., 176 
FERC ] 61,207, at PP 7, 21 (2021). The Midcontinent Independent 
System Operator (MISO) has indicated that it similarly has 
experienced delays in performance of interconnection studies by 
outside consultants. See MISO, Informational Report, Transmittal, 
Docket No. ER19-1960, at 12 (filed Nov. 16, 2020).
---------------------------------------------------------------------------

    21. In recent years, numerous transmission providers have responded 
to the types of trends and challenges outlined above by seeking to 
reform their interconnection queue processes.\68\ Since 2018, the 
Commission has approved proposals from five non-independent 
transmission providers to transition from the serial first-come, first-
served study process set forth in the pro forma LGIP to a first-ready, 
first-served cluster study process that imposes increasing readiness 
requirements to advance through the study phases.\69\ Meanwhile, 
several RTOs/ISOs, including MISO and Southwest Power Pool (SPP), have 
proposed refinements to the cluster study processes in their regions 
that the Commission had previously approved.\70\
---------------------------------------------------------------------------

    \68\ See May Joint Task Force Tr. 88:10-12 (Ted Thomas) (``[T]he 
RTOs have been working on these interconnection issues and we don't 
have a solution yet.'').
    \69\ Dominion Energy S.C., Inc., Docket No. ER22-301-000 (Dec. 
28, 2021) (delegated order) (Dominion); Duke Energy Carolinas, LLC, 
176 FERC ] 61,075 (2021) (Duke); PacifiCorp, 171 FERC ] 61,112 
(2020); Pub. Serv. Comm'n of Colo., 169 FERC ] 61,182 (2019) (PSCo); 
Tri-State Generation & Transmission Ass'n, Inc., 173 FERC ] 61,015 
(2020) (2020 Tri-State Order).
    \70\ See, e.g., Midcontinent Indep. Sys. Operator, Inc., 178 
FERC ] 61,141 (2022); Sw. Power Pool, Inc., 178 FERC ] 61,015 
(2022).
---------------------------------------------------------------------------

    22. As the factors contributing to interconnection queue backlogs 
and study delays continue and even increase, it has become more 
apparent that the Commission's existing generator interconnection 
procedures and agreements may be insufficient to ensure that 
interconnection customers are able to interconnect to the transmission 
system in a reliable, efficient, transparent, and timely manner, 
thereby ensuring that rates, terms, and conditions for Commission-
jurisdictional services remain just and reasonable and not unduly 
discriminatory or preferential.\71\ We preliminarily find that the 
Commission's pro forma LGIP, pro forma LGIA, pro forma SGIP, and pro 
forma SGIA result in rates, terms, and conditions pursuant to which 
transmission providers provide generator interconnection service are 
unjust and unreasonable and unduly discriminatory or preferential. 
Further, because the interconnection queue backlogs and study delays 
afflicting generator interconnection service nationwide hinder the 
timely development of new generation and thereby stifle competition in 
the wholesale electric markets, we preliminarily find that the 
Commission's pro forma LGIP, pro forma LGIA, pro forma SGIP, and pro 
forma SGIA result in rates, terms, and conditions in the wholesale 
electric markets that are unjust and unreasonable and unduly 
discriminatory or preferential.
---------------------------------------------------------------------------

    \71\ See May Joint Task Force Tr. 23:6-11 (Riley Allen) 
(``Ultimately, this system is not working efficiently now and those 
inefficiencies translate into costs. It's not just cost on the 
developers, but I find from my decades of experience that, if there 
are inefficiencies in the system, they ultimately have to be borne 
by the loads and ratepayer interests.'').
---------------------------------------------------------------------------

    23. Our preliminary findings are based on several features of the 
Commission's existing generator interconnection procedures and 
agreements that are of concern, specifically: (1) the information (or 
lack thereof) available to prospective interconnection customers and 
the commitments required of them to enter and progress through the 
interconnection queue; (2) the reliance on a serial first-come, first-
served study process and the standard to which transmission providers 
are held for meeting interconnection study deadlines; (3) the protocols 
for affected systems studies; (4) the provisions for studying new or 
hybrid (co-located) generation technologies and considering alternative 
transmission technologies; and (5) the performance requirements for 
inverter-based technologies, including wind, solar, and electric 
storage facilities. We describe these features of the Commission's 
existing generator interconnection procedures and agreements--as set 
forth in the Commission's pro forma LGIP, pro forma LGIA, pro forma 
SGIP, and pro forma SGIA--in this section and then turn to our proposed 
reforms to address the concerns identified with those features.\72\
---------------------------------------------------------------------------

    \72\ See id. 184:6-19 (Clifford Rechtschaffen) (``I think it's 
beyond dispute that we need queue reform. I don't know if it's a 
crisis, but there's logjams, dysfunctions, inefficiencies . . . . I 
think there's a real need to keep the foot on the gas and for FERC 
to provide guidance templates, best practices, . . . minimum 
baselines, while again, providing for flexibility.'').
---------------------------------------------------------------------------

    24. First, the pro forma LGIP does not contain a process by which 
an interconnection customer can obtain information at a specific 
location or point of interconnection about potential interconnection 
costs prior to submitting an interconnection request. As a result, at 
the outset of the generator interconnection process,\73\

[[Page 39940]]

interconnection customers typically have little insight into the 
interconnection capacity available at various points on the 
transmission system. Furthermore, interconnection customers face 
limited financial commitments to enter and stay in the interconnection 
queue and few requirements to prove the commercial viability of 
proposed generating facilities.\74\ Therefore, developers often submit 
multiple interconnection requests for proposed generating facilities at 
various points of interconnection, not all of which are expected to 
reach commercial operation, as an exploratory mechanism to obtain 
information to allow them to choose the most favorable site.\75\
---------------------------------------------------------------------------

    \73\ As in the background of this NOPR, we describe the 
generator interconnection process set forth in the Commission's pro 
forma LGIP, which we recognize differs from many transmission 
providers' generator interconnection processes due to Commission-
approved variations.
    \74\ For example, the total cost of interconnection studies 
under the pro forma LGIP is often under $500,000. See pro Forma LGIP 
sections 3.1 ($10,000 deposit with interconnection request), 6.1 
($10,000 deposit with Feasibility Study Agreement), 7.2 ($50,000 
deposit with System Impact Study Agreement), 8.1 (minimum $100,000 
deposit with Facilities Study Agreement).
    \75\ See, e.g., Review of Generator Interconnection Agreements 
and Procedures, Technical Conference Transcript, Docket No. RM16-12-
000, at 211:10-21 (May 13, 2016) (Steve Naumann, Exelon Corp.) 
(filed Aug. 23, 2016) (``We would look at putting let's say new gas 
fired generation in PJM, it may have four queue positions. And we 
only intend to go through with one, that's not speculation, that's 
trying to get information on which is the most viable.'').
---------------------------------------------------------------------------

    25. Second, securing a higher interconnection queue position is 
valuable when interconnecting to a transmission provider that uses the 
serial first-come, first-served study process as laid out in the pro 
forma LGIP because the transmission provider will process 
interconnection requests (i.e., perform required interconnection 
studies) in the order in which the interconnection requests are 
received. By obtaining an early queue position, a generating facility 
may be able to use available transmission capacity and not need to 
incur costs for network upgrades that later-queued interconnection 
customers potentially incur. Under this framework, interconnection 
customers have an incentive to submit interconnection requests to 
secure a queue position as early as possible, even if they are not 
prepared to move forward with the proposed generating facility at the 
time the interconnection request is made, to identify locations with 
available headroom on the transmission system and establish priority 
over later-queued interconnection requests.
    26. Often, these more speculative interconnection requests do not 
prove to be commercially viable. For example, in many interconnection 
queues, the MW volumes of interconnection requests far exceed the 
transmission provider's peak network load.\76\ A lack of commercial 
viability often means that many proposed generating facilities in the 
interconnection queue will eventually withdraw after not finding a 
purchaser for their output. In the case where the interconnection 
customer submits multiple requests, the developer may select only the 
one or two most viable project candidates and withdraw the 
interconnection requests for the remaining projects. These withdrawals 
then impact the remaining interconnection customers in the 
interconnection queue. A withdrawal may necessitate re-studies and 
cause the shifting of network upgrade costs to lower-queued 
interconnection customers. New cost estimates, in turn, can alter a 
proposed generating facility's commercial viability and create further 
re-studies and withdrawals, often referred to as cascading re-studies 
and withdrawals.\77\ These re-studies exacerbate the cost uncertainty 
faced by interconnection customers \78\ and prevent the transmission 
provider from maintaining a model base case for how its transmission 
system is expected to reliably operate and serve load in the future.
---------------------------------------------------------------------------

    \76\ For example, Dominion, PSCo, and Tri-State each provided 
statistics to this effect as part of their argument for 
interconnection queue reforms. See Dominion, Transmittal Letter, 
Docket No. ER22-301-000, at 8 (filed Nov. 1, 2021); PSCo, 
Transmittal Letter, Docket No. ER19-2774-000, at 27 (filed Sep. 9, 
2019); Tri-State, Transmittal Letter, Docket No. ER21-410-000, at 20 
(filed Nov. 13, 2020).
    \77\ See pro forma LGIP section 7.6; see also May Joint Task 
Force Tr. 70:20-71:6 (Matthew Nelson) (analogizing reiterative 
studies to going to the supermarket to buy ingredients for a recipe 
without knowing how much the ingredients cost, finding out at the 
register that they cost too much for your budget, and having to ``go 
home, get a new recipe, and start it all over again'').
    \78\ Id 74:9-21 (Andrew French) (stating that generator 
developers complain principally about cost certainty and cost 
sharing and that ``cost certainty is the much bigger issue'' given 
that ``an essential element of being able to sell a product is to 
know what your inputs are so you can market it'').
---------------------------------------------------------------------------

    27. These delays faced by individual interconnection customers may 
hinder the timely development of new generation, and, thereby, stifle 
competition in wholesale energy markets or delay access to potential 
low cost generation, which ultimately drive up costs for consumers.
    28. Compounding these issues, the pro forma LGIP does not require 
transmission providers to meet deadlines for conducting interconnection 
studies. Rather, transmission providers are only required to use 
``reasonable efforts'' \79\ to complete interconnection studies on 
time.\80\ Despite complaints from interconnection customers, the 
Commission has not yet found that a transmission provider failed to use 
reasonable efforts to meet interconnection study deadlines, even though 
such studies are routinely completed months or years late. While 
interconnection customers can be removed from the queue for failure to 
comply with deadlines throughout the generator interconnection 
process,\81\ transmission providers face no consequences for failure to 
comply with study deadlines.
---------------------------------------------------------------------------

    \79\ Reasonable efforts are defined as ``actions that are timely 
and consistent with Good Utility Practice and are substantially 
equivalent to those a Party would use to protect its own 
interests.'' Order No. 2003, 104 FERC ] 61,103 at P 67; pro forma 
LGIP section 1.
    \80\ See pro forma LGIP sections 2.2, 6.3, 7.4, 8.3.
    \81\ Id. section 3.7 (``[I]f Interconnection Customer fails to 
adhere to all requirements of this LGIP . . . Transmission Provider 
shall deem the Interconnection Request to be withdrawn and shall 
provide written notice to Interconnection Customer . . . [.] 
Interconnection Customer shall have fifteen (15) Business Days in 
which to either respond with information or actions that cures the 
deficiency or to notify Transmission provider of its intent to 
pursue Dispute Resolution.'').
---------------------------------------------------------------------------

    29. Third, similar to the lack of requirements for timely 
completion of interconnection studies, the pro forma LGIP provides 
almost no requirements regarding how or when transmission providers or 
affected systems should complete affected system studies; in 
particular, even the reasonable efforts standard does not apply to 
these studies.\82\ In practice, these studies often lag behind those 
completed by the host transmission provider and are sometimes completed 
very late in the process, causing an additional round of delays and 
cost uncertainty for interconnection customers.\83\
---------------------------------------------------------------------------

    \82\ Affected systems studies are used to study the impact of 
proposed interconnection requests on neighboring transmission 
systems. Transmission providers are obligated to coordinate the 
conduct of affected system studies, but the Commission has not 
required transmission providers to follow any specific affected 
system coordination process. See pro forma LGIP section 3.6.
    \83\ EDF Renewable Energy, Inc. v. Midcontinent Indep. Sys. 
Operator, Inc., 168 FERC ] 61,173 (2019) (EDF v. MISO).
---------------------------------------------------------------------------

    30. In short, under the Commission's existing pro forma LGIP, pro 
forma LGIA, pro forma SGIP, and pro forma SGIA, it is difficult for 
transmission providers to disincentivize interconnection customers from 
entering multiple speculative interconnection requests into the 
interconnection queue or minimize the risk of late-stage withdrawals of 
interconnection requests. Conversely, transmission providers have 
little

[[Page 39941]]

incentive to perform interconnection studies in a timely fashion. The 
resulting timing and cost uncertainty creates a barrier to entry that 
hinders competitive wholesale electric markets. As the Commission has 
previously observed, delayed interconnection study results or 
unexpected cost increases can disrupt numerous aspects of generating 
facility development, including project financing and the ability to 
obtain a power purchase agreement.\84\ Developers in the 
interconnection queues have recently filed complaints with the 
Commission alleging that interconnection study delays have caused 
direct and indirect financial harm to them by threatening the viability 
of their projects.\85\ Cost uncertainty poses an especially significant 
obstacle because proposed generating facilities may simply not be able 
to absorb substantial unexpected interconnection costs allocated as the 
result of a re-study. As indicated earlier, our fundamental concern is 
the follow-on impacts of these issues on rates paid by consumers. 
Unnecessary interconnection costs, either on the part of project 
developers or transmission providers, are ultimately passed through to 
consumers through higher energy or transmission rates, respectively. 
Conversely, efficient interconnection queues and well-functioning 
wholesale markets deliver enormous benefits to consumers by driving 
down wholesale electricity costs.
---------------------------------------------------------------------------

    \84\ Reform of Generator Interconnection Procedures and 
Agreements, 157 FERC ] 61,212, at P 30 (2016).
    \85\ See, e.g., SOO Green HVDC Link Project Co, LLC, Complaint, 
Docket No. EL21-85-000, at 24, 38-39 (filed June 21, 2021).
---------------------------------------------------------------------------

    31. Fourth, in addition to our preliminary findings related to the 
interconnection queue backlogs described above, we preliminarily find 
that the Commission's pro forma LGIP, pro forma LGIA, pro forma SGIP, 
and pro forma SGIA are unjust and unreasonable, unduly discriminatory, 
and preferential as applied to several interconnection procedural and 
modeling issues. This set of inquiries was prompted by newer 
technologies entering interconnection queues in greater numbers. 
Interconnection queues consist now predominantly of non-synchronous 
resources such as wind, solar, and electric storage projects, all of 
which have operating characteristics that were not anticipated when the 
Commission issued Order No. 2003.\86\ In particular, interest in hybrid 
resources, which combine more than one generating facility type, often 
with electric storage, has increased dramatically.\87\ This change in 
the types of resources has brought to light several issues. For 
example, the pro forma LGIP does not specify whether interconnection 
customers of all resource types can submit a single interconnection 
request for co-located components of a generating facility, although 
research shows that this option is frequently used in regions where it 
has been made available through variations from the Commission's pro 
forma generator interconnection procedures.\88\
---------------------------------------------------------------------------

    \86\ As of the end of 2019, 90% of the generating capacity that 
was waiting in interconnection queues nationwide was wind, solar, or 
energy storage projects. See Jay Caspary et al., Ams. for a Clean 
Energy Grid, Disconnected: The Need for a New Generator 
Interconnection Policy, at 4 (Jan. 2021), <a href="https://cleanenergygrid.org/disconnected-the-need-for-new-interconnection-policy/">https://cleanenergygrid.org/disconnected-the-need-for-new-interconnection-policy/</a> (ACEG Report).
    \87\ 42% (285 GW) of solar and 8% (17 GW) of wind projects 
currently in the queue are proposed as hybrid resources including 
electric storage. Queued Up at 18.
    \88\ In researching hybrid interconnection requests, Lawrence 
Berkeley National Laboratory encountered many projects for which 
``the `Generator Type' field includes multiple types for a single 
queue entry.'' See Mark Bolinger, et al., Lawrence Berkeley Nat'l 
Lab'y, Hybrid Power Plants: Status of Installed and Proposed 
Projects, at 16 (Aug. 2021), <a href="https://emp.lbl.gov/sites/default/files/hybrid_plant_development_2021.pdf">https://emp.lbl.gov/sites/default/files/hybrid_plant_development_2021.pdf</a>.
---------------------------------------------------------------------------

    32. Further, the addition of generating facilities that do not 
affect the requested interconnection service level are often deemed a 
material modification without review, which can cause unnecessary 
network upgrades. Also, the use of the surplus interconnection process, 
as adopted in Order No. 845, has proven helpful for interconnection 
customers seeking to access interconnection capacity that has already 
been approved through an LGIA, but it is currently only available when 
a resource is fully operational. Lastly, with respect to 
interconnection requests involving electric storage resources, a 
transmission provider may use operating assumptions for interconnection 
studies that employ worst-case assumptions or other inaccuracies (e.g., 
that electric storage will charge during peak load periods) \89\ that 
do not accurately reflect the planned operation of these resources, 
thus requiring network upgrades that may not be necessary.
---------------------------------------------------------------------------

    \89\ Hybrid Resource Coalition, Comments, Docket No. AD20-9-000, 
at 11-12 (filed Sept. 20, 2021); City of New York, Comments, Docket 
No. AD20-9-000, at 3 (filed Sept. 20, 2021); Clean Grid Alliance, 
Comments, Docket No. AD20-9-000, at 3 (filed Sept. 20, 2021); 
Savion, Post-Technical Conference Comments, Docket No. AD20-9-000, 
at 7 (filed Sept. 24, 2020); Enel, Post-Technical Conference 
Comments, Docket No. AD20-9-000, at 2-3 (filed Sept. 24, 2020).
---------------------------------------------------------------------------

    33. We also preliminarily find that failing to consider alternative 
transmission technologies that can be deployed both more quickly and at 
lower costs than network upgrades may render Commission-jurisdictional 
rates unjust and unreasonable. Therefore, we propose to modify the 
Commission's pro forma LGIP and SGIP to require their consideration to 
achieve their benefits in generator interconnection processes.\90\ 
Alternative transmission technologies might allow for the 
interconnection of a proposed generating facility at a lower cost and 
require less time to implement than traditional network upgrades.\91\ 
Despite these potential benefits, alternative transmission technologies 
often do not receive the same consideration during generator 
interconnection processes and have only been deployed in a small number 
of instances.\92\ The result is that interconnection customers--and 
ultimately consumers--may be paying more than is reasonable to reliably 
interconnect new generating facilities, rendering Commission-
jurisdictional rates unjust and unreasonable and unduly discriminatory 
and preferential.
---------------------------------------------------------------------------

    \90\ A variety of technologies offer potential alternatives to 
standard infrastructure network upgrades (e.g., reconductoring 
transmission lines or building new ones). These technologies include 
advanced power flow control devices, transmission switching, dynamic 
line ratings, static synchronous compensators, static volt-ampere 
reactive (VAR) compensators, and electric storage in specific use 
cases.
    \91\ See, e.g., EDF Renewables, Comments, Docket No. RM21-17-
000, at 16 (filed Nov. 30, 2021); State Agencies, Comments, Docket 
No. RM21-27-000, at 30-33 (filed Nov. 30, 2021); Alliant Energy 
Corporate Services, Inc. et al., Comments, Docket No. RM20-16-000, 
at 6 (filed Mar. 22, 2021) (stating that ``utilization of [dynamic 
line ratings] can improve contingency planning and defer or 
eliminate the need for line upgrades or reconductoring'').
    \92\ See, e.g., EDF Renewables, Comments, Docket No. RM21-17-
000, at 16 (filed Nov. 30, 2021); Potomac Economics, Comments, 
Docket No. RM21-17-000, at 8-9 (filed Nov. 30, 2021); State 
Agencies, Comments, Docket No. RM21-27-000, at 31-32 (filed Nov. 30, 
2021).
---------------------------------------------------------------------------

    34. Fifth, we preliminarily find that the pro forma LGIP and SGIP's 
data submission and performance requirements for non-synchronous 
generating facilities \93\ (including wind, solar, and electric storage 
facilities) require reform to avoid undue discrimination and ensure 
just and reasonable Commission-jurisdictional rates. When an 
interconnection customer submits an interconnection

[[Page 39942]]

request for a proposed synchronous generating facility, it must provide 
a variety of system information, which allows the transmission provider 
to assess and model the facility's ability to respond appropriately to 
transmission system disturbances.\94\ By contrast, non-synchronous 
generating facilities are not required to provide a comparable level of 
information that would allow the transmission provider to model and 
assess the facility's ability to respond appropriately to transmission 
system disturbances.\95\ As the penetration of wind, solar, and 
electric storage resources increases, the behavior of these types of 
non-synchronous generating facilities during transmission system 
disturbances becomes more consequential, as does the need to assess 
their potential contribution to cascading outages or other major 
electric system issues. Furthermore, we are concerned that, without 
reform to require interconnection customers developing non-synchronous 
resources to provide sufficiently accurate and validated models, 
interconnection studies may not identify the appropriate 
interconnection facilities and network upgrades needed for that 
interconnection request. If the interconnection studies are not able to 
identify the appropriate interconnection facilities and network 
upgrades, then the interconnection costs assigned to that 
interconnection customer may be skewed, resulting in unjust and 
unreasonable rates for interconnection service.
---------------------------------------------------------------------------

    \93\ Non-synchronous generating facilities are ``connected to 
the bulk power system through power electronics, but do not produce 
power at system frequency (60 Hz).'' They ``do not operate in the 
same way as traditional generators and respond differently to 
network disturbances.'' Reactive Power Requirements for Non-
Synchronous Generation, Order No. 827, 81 FR 40793 (June 23, 2016), 
155 FERC ] 61,277, at P 10 n.24 (2016) (citing Interconnection for 
Wind Energy, Order No. 661, 70 FR 34993 (June 16, 2005), 111 FERC ] 
61,353, at P 3 n.4 (2005)).
    \94\ This information includes model block diagrams for 
excitation systems, power system stabilizers, and governor systems, 
to inform and verify the dynamic models used by the transmission 
provider to assess the proposed synchronous generating facility's 
response to transmission system disturbances. See pro forma LGIP 
app. 1, attach. A.
    \95\ See infra PP 310-312.
---------------------------------------------------------------------------

    35. In addition, we are concerned that the pro forma LGIA and SGIA 
may impose disparate performance requirements during system 
disturbances on synchronous and non-synchronous resources. 
Specifically, the physical characteristics of synchronous generating 
facilities result in such facilities continuing to inject electric 
current during transmission system disturbances, consistent with the 
need to remain ``connected to and synchronized with the Transmission 
System'' as required by the pro forma LGIA and SGIA.\96\ As a result, 
services that support transmission system reliability are not disrupted 
during such events. However, the pro forma LGIA and SGIA do not 
currently require non-synchronous generating facilities to continue 
injecting current in a comparable manner during system disturbances. 
Specifically, non-synchronous resources many cease injecting current 
through ``momentary cessation.'' \97\ As a result, transmission 
providers cannot determine whether non-synchronous generating 
facilities, in the aggregate, will continue to inject electric current 
during transmission system disturbances.
---------------------------------------------------------------------------

    \96\ Pro forma LGIA art. 9.73; pro forma SGIA art. 1.57.
    \97\ See infra note 463.
---------------------------------------------------------------------------

    36. In light of the concerns outlined above, we preliminarily find 
that it is necessary to reform the Commission's pro forma LGIP, pro 
forma LGIA, pro forma SGIP, and pro forma SGIA to ensure that 
interconnection customers are able to interconnect to the transmission 
system in a reliable, efficient, transparent, and timely manner, 
thereby ensuring that rates, terms, and conditions for Commission-
jurisdictional services remain just and reasonable and not unduly 
discriminatory or preferential.

II. Proposed Reforms

A. Reforms To Implement a First-Ready, First-Served Cluster Study 
Process

    37. In recent years, late-stage withdrawals of interconnection 
requests have caused significant delays in interconnection study 
processes. In its January 2020 interconnection queue reform filing, 
PacifiCorp noted that about 75% of all interconnection requests 
ultimately withdraw from its interconnection queue and that withdrawals 
are a significant cause of delays in the generator interconnection 
process because withdrawals trigger re-studies. PacifiCorp argued that 
the current generator interconnection process encourages speculative 
projects to enter the interconnection queue because it does not require 
any progress toward commercial viability and does not penalize 
withdrawals from the interconnection queue.\98\
---------------------------------------------------------------------------

    \98\ PacifiCorp, 171 FERC ] 61,112 at P 3.
---------------------------------------------------------------------------

    38. In support of its 2019 interconnection queue reform proposal, 
PSCo stated that it has experienced a surge in interconnection requests 
that cannot be processed under its current generator interconnection 
process. PSCo explained that, because the amount of generation 
requesting interconnection is significantly greater than the region's 
needs, only a small fraction of the generating facilities in the 
interconnection queue are likely to reach commercial operation. In 
addition, PSCo stated that, due to the configuration of PSCo's 
transmission system and the fact that most requests are for network 
resource integration service (NRIS),\99\ almost all lower-queued 
interconnection requests, regardless of study phase, are affected by 
changes to higher-queued interconnection requests.\100\
---------------------------------------------------------------------------

    \99\ NRIS allows the interconnection customer to integrate its 
generating facility with the transmission provider's transmission 
system in a manner comparable to that in which the transmission 
provider integrates its generating facilities to serve native load 
customers, or in an RTO/ISO with market-based congestion management, 
in the same manner as Network Resources. NRIS in and of itself does 
not convey transmission service. Pro forma LGIP section 1.
    \100\ PSCo, 169 FERC ] 61,182 at P 21.
---------------------------------------------------------------------------

    39. For the reasons explained above, we preliminarily find that the 
Commission's pro forma LGIP and LGIA are unjust, unreasonable, unduly 
discriminatory, and preferential and that reforms are needed to allow 
interconnection customers to interconnect in a reliable, efficient, 
timely manner, thereby ensuring that rates, terms, and conditions for 
Commission-jurisdictional services remain just and reasonable and not 
unduly discriminatory or preferential. In particular, with regard to 
interconnecting in an efficient and timely manner, we propose reforms 
to the pro forma LGIP that: (1) require transmission providers to offer 
an optional informational interconnection study to serve as additional 
information for prospective interconnection customers in deciding 
whether to submit an interconnection request and set minimum 
requirements for transmission providers to publicly post available 
information pertaining to generator interconnection; (2) require 
transmission providers to implement a first-ready, first-served cluster 
study process that allocates costs associated with cluster studies and 
identified network upgrades consistent with the discussion below; and 
(3) impose more stringent financial commitments and readiness 
requirements on interconnection customers, including increased study 
deposits, more stringent site control requirements, a commercial 
readiness framework, and higher withdrawal penalties. To implement 
these reforms, we also propose to require transmission providers to 
establish a transition process, consistent with the proposed 
requirements below.
1. Interconnection Information Access
a. Need for Reform
    40. We are concerned that the lack of transparency for prospective 
interconnection customers to obtain information about potential

[[Page 39943]]

interconnection costs prior to submitting an interconnection request is 
problematic. Without this information, it is difficult for 
interconnection customers to assess the viability of a specific 
proposed generating facility. Subsequently, interconnection customers 
submit multiple speculative interconnection requests in an attempt to 
obtain information through the system impact study process about the 
costs associated with various project configurations.
    41. Some transmission providers have attempted to solve these 
problems by making more information available to interconnection 
customers before they enter the interconnection queue through an 
optional informational interconnection study that provides estimates of 
costs and scheduling for various sites.\101\ These optional 
informational interconnection studies evaluate the feasibility of a 
proposed interconnection request and provide interconnection customers 
with non-binding information upon which to base preliminary siting 
decisions. Transmission providers that offer these types of studies 
require a $10,000 deposit for the studies, subject to a true-up based 
on actual costs of performing the studies.\102\ While some transmission 
providers offer such an option, it is not currently required by the pro 
forma LGIP.
---------------------------------------------------------------------------

    \101\ Dominion, Docket No. ER22-301-000 (Dec. 28, 2021) 
(delegated order);  Duke, 176 FERC ] 61,075 at P 19; PacifiCorp, 171 
FERC ] 61,112 at P 54; PSCo, 169 FERC ] 61,182 at PP 9-10, 30; Tri-
State Generation & Transmission Ass'n, Inc., 174 FERC ] 61,021, at P 
6 (2021) (Tri-State).
    \102\ See, e.g., Dominion, OATT and Service Agreements, attach. 
M (4.5.0), section 3.1; PSCo, Transmission and Service Agreements 
Tariff, OATT, attach. N. (0.8.0), section 6.1 (requiring a $10,000 
deposit for an informational study request).
---------------------------------------------------------------------------

b. Proposed Reforms
i. Informational Interconnection Study
    42. To address the lack of information available to interconnection 
customers prior to entering the interconnection queue, and the 
associated impacts on development of new generating facilities, 
interconnection queue backlogs, and interconnection study delays, we 
propose to revise the Commission's pro forma LGIP to require 
transmission providers to offer an informational interconnection study 
to serve as additional information for prospective interconnection 
customers in deciding whether to submit an interconnection request. The 
study would provide cost estimates for the transmission provider's 
interconnection facilities \103\ and network upgrade costs specific to 
the interconnection scenario detailed in the study agreement. 
Specifically, we propose to revise sections 6.1-6.3 and Appendix 2 to 
the pro forma LGIP to implement this reform: section 6.1 (Informational 
Interconnection Study Agreement), section 6.2 (Scope of Informational 
Interconnection Study), section 6.3 (Informational Interconnection 
Study Procedures), Appendix 2 (Informational Interconnection Study 
Request form), and Attachment A to Appendix 2 (Informational 
Interconnection Study Agreement form). We also propose to include new 
definitions for an informational interconnection study and 
informational interconnection study agreement.
---------------------------------------------------------------------------

    \103\ The pro forma LGIA defines ``Transmission Provider's 
Interconnection Facilities'' as ``all facilities and equipment 
owned, controlled or operated by the Transmission Provider from the 
Point of Change of Ownership to the Point of Interconnection as 
identified in Appendix A to the Standard Large Generator 
Interconnection Agreement, including any modifications, additions or 
upgrades to such facilities and equipment. Transmission Provider's 
Interconnection Facilities are sole use facilities and shall not 
include Distribution Upgrades, Stand Alone Network Upgrades or 
Network Upgrades.'' These are distinct from ``Interconnection 
Customer's Interconnection Facilities,'' which are those facilities 
``identified in Appendix A of the Standard Large Generator 
Interconnection Agreement, that are located between the Generating 
Facility and the Point of Change of Ownership, including any 
modification, addition, or upgrades to such facilities and equipment 
necessary to physically and electrically interconnect the Generating 
Facility to the Transmission Provider's Transmission System. 
Interconnection Customer's Interconnection Facilities are sole use 
facilities.'' Pro forma LGIA section 1.
---------------------------------------------------------------------------

    43. Proposed section 6.1 of the pro forma LGIP provides that a 
prospective interconnection customer may request an informational 
interconnection study. The proposed provision would limit prospective 
interconnection customers to no more than five separate informational 
interconnection study requests pending at a time to ensure that 
transmission providers are not overburdened with these studies and that 
one prospective interconnection customer cannot prevent others from 
taking advantage of this information-gathering process.\104\ Each 
configuration of an interconnection request would require a separate 
informational interconnection study. For example, prospective 
interconnection customers seeking to evaluate different sites or 
different voltage levels at the same site would need to submit a 
separate request for each configuration. The informational 
interconnection study would be at the interconnection customer's 
expense, and each study would require a $10,000 deposit, subject to a 
true-up based on actual study costs.
---------------------------------------------------------------------------

    \104\ See, e.g., Dominion, OATT and Service Agreements, attach. 
M (4.5.0), section 3.1 (``Any one Interconnection Customer 
(including affiliates) shall have no more than five (5) requests for 
Informational Interconnection Study reports pending at one time.'').
---------------------------------------------------------------------------

    44. Under the proposal, within seven business days of the receipt 
of a prospective interconnection customer's request for an 
informational interconnection study, the transmission provider would 
have to provide the prospective interconnection customer with an 
informational interconnection study agreement in the form of Attachment 
A to Appendix 2 of the pro forma LGIP. The informational 
interconnection study agreement would specify the technical data that 
the prospective interconnection customer must provide and an estimate 
of the expected costs of the study, including, to the extent known by 
the transmission provider, an estimate of the study costs expected to 
be incurred by any relevant affected systems. The prospective 
interconnection customer would have 10 business days to execute the 
agreement and deliver it to the transmission provider, along with the 
relevant technical data and study deposit, after which the transmission 
provider would have 45 days to complete the study.
    45. Proposed section 6.2 of the pro forma LGIP explains that the 
informational interconnection study consists of a sensitivity analysis 
based on the assumptions specified in the informational interconnection 
study agreement. The informational interconnection study would identify 
potential interconnection facilities and network upgrades that may be 
required to interconnect the prospective interconnection customer's 
proposed generating facility, including an approximation of the costs 
of such interconnection facilities and network upgrades. The 
transmission provider would also coordinate with affected systems that 
may be impacted by the prospective interconnection customer's request 
to provide information on affected systems-related issues.
    46. Proposed Attachment A to Appendix 2 of the pro forma LGIP 
contains the informational interconnection study agreement form. The 
form agreement explains that the informational interconnection study is 
performed solely for informational purposes and is not binding on 
either party. It also requires the study report to provide specific 
information, including, at a minimum: (1) preliminary identification of 
any circuit breaker short circuit capability limits exceeded; (2) 
preliminary identification of any thermal overload or voltage limit 
violations; and (3) estimated network

[[Page 39944]]

upgrade costs related to the identified overloads and violations.
    47. We recognize that the benefit of the informational 
interconnection study results would depend on the information provided, 
the assumptions made, and the timing of the proposed interconnection, 
with studies looking at interconnection requests with proposed 
commercial operation dates further into the future carrying greater 
uncertainty. Nevertheless, we seek comment on whether the informational 
interconnection study, as proposed, would provide prospective 
interconnection customers with sufficient and timely information to 
inform decision-making prior to submitting an interconnection request.
    48. We seek comment on whether transmission providers should be 
required to establish a request window of a limited number of days each 
year in which potential interconnection customers can request an 
optional informational interconnection study. Lastly, we seek comment 
on the burdens on transmission providers of conducting informational 
studies and whether other options, such as the proposal below for 
public interconnection information, might strike a better balance of 
providing interconnection customers with useful information while 
making efficient use of transmission provider resources.
ii. Public Interconnection Information
    49. In addition to the optional informational interconnection study 
described above, to address the lack of information available to 
interconnection customers prior to entering the interconnection queue, 
and the associated impacts on development of new generating facilities, 
interconnection queue backlogs, and interconnection study delays, we 
also propose to set minimum requirements for transmission providers to 
publicly post available information pertaining to generator 
interconnection. We believe that providing an interactive visual 
representation \105\ of available interconnection capacity, as 
explained below, across a transmission provider's transmission system 
could provide valuable information to prospective interconnection 
customers that are considering efficient points of interconnection and 
could ameliorate the incentive to submit multiple speculative 
interconnection requests to gather information useful to assessing the 
viability of proposed generating facilities.
---------------------------------------------------------------------------

    \105\ See, e.g., Midcontinent Indep. Sys. Operator, Points of 
Interconnection, <a href="https://giqueue.misoenergy.org/PoiAnalysis/index.html">https://giqueue.misoenergy.org/PoiAnalysis/index.html</a> (accessed March 17, 2022).
---------------------------------------------------------------------------

    50. Some transmission providers already post such generator 
interconnection information as an extra tool for prospective 
interconnection customers. For example, MISO provides an interactive 
heatmap of expected congestion to serve as a guide on potential points 
of interconnection with available interconnection capacity.\106\ The 
heatmap allows prospective interconnection customers to see estimated 
changes in variables such as the distribution factor (an approximation 
of congestion) and the percentage impact on power flow for monitored 
facilities based on a user-entered MW amount and voltage level at a 
user-selected point of interconnection. Transmission congestion is a 
key consideration for potential interconnection customers because 
elevated congestion in a particular area of the transmission system may 
signal that it is a location where network upgrades are more likely to 
be required or curtailments are more likely to occur relative to an 
area with less congestion. This heatmap is based on the assumptions in 
a given interconnection study cycle and MISO includes the caveat that 
the tool does not provide consideration for all system conditions, 
including voltage and stability constraints.
---------------------------------------------------------------------------

    \106\ Id.
---------------------------------------------------------------------------

    51. In order to make similar information available to prospective 
interconnection customers across the country--ensuring comparable 
access to information regardless of the interconnecting transmission 
provider--we propose to require transmission providers to maintain and 
make publicly available an interactive visual representation of 
available interconnection capacity as well as a table of relevant 
interconnection metrics that allow prospective interconnection 
customers to see certain estimates of a potential generating facility's 
effect on the transmission provider's transmission system. 
Specifically, we propose to revise section 6.4 of the pro forma LGIP to 
implement this reform. Section 6.4 (Publicly Posted Interconnection 
Information) would set forth minimum requirements that include a 
heatmap of estimated incremental injection capacity (in MW) available 
at each bus in the transmission provider's footprint under N-1 
conditions, as well as providing a table of results showing the 
estimated impact of the addition of a proposed project (based on the 
user-specified MW amount, voltage level, and point of interconnection) 
for each monitored facility impacted by the proposed project on: (1) 
the distribution factor; (2) the MW impact (based on the proposed 
project size and the distribution factor); (3) the percentage impact on 
the monitored facility (based on the MW values of the proposed project 
and the monitored facility rating); (4) the percentage of power flow on 
the monitored facility before the proposed project; and (5) the 
percentage power flow on the monitored facility after the injection of 
the proposed project. These metrics would be calculated based on the 
power flow model of the cluster study or re-study with the transfer 
simulated from each bus to the whole transmission providers footprint 
(to approximate NRIS), and with the incremental capacity at each bus 
decremented by the existing and queued generation in the Cluster (based 
on the existing or requested interconnection service limit of the 
generation). These metrics would be intended to facilitate a high-level 
comparison between various points of interconnection, without 
submitting an interconnection request. We propose to require 
transmission providers to make this information available on their 
public websites to facilitate transparency and the usefulness of this 
information for prospective interconnection customers. We propose to 
require transmission providers to update this information within 30 
days after the completion of each cluster study and re-study. Should 
prospective interconnection customers require more detailed analysis, 
they could submit a request for an informational interconnection study, 
as we proposed to establish above in Section A.1.b.
    52. We seek comment on whether there are any security concerns with 
this proposed requirement. We also seek comment on whether the 
assumptions specified for the analysis are the right set of 
assumptions.
2. Cluster Study
a. Need for Reform
    53. As discussed above, the inefficiency of the pro forma serial 
first-come, first-served interconnection study process in the pro forma 
LGIP is a major cause of the backlogs delaying transmission providers' 
interconnection queues. Using the pro forma serial interconnection 
study process in the face of a large interconnection queue backlog 
leads to uncertainty with regard to how long it will take to complete 
the interconnection study process, and the interconnection customer's 
cost responsibility for network upgrades.

[[Page 39945]]

    54. Even for transmission providers that have not yet experienced 
large backlogs, the serial interconnection study process may cause 
unnecessary delay and inefficiently allocate network upgrade costs. 
Under the pro forma LGIP study process, interconnection requests are 
typically studied individually where a single proposed generating 
facility may create a need for network upgrades. This current serial 
process may result in a piecemeal identification of network upgrades 
which does not account for possible efficiencies of studying multiple 
interconnection customer requests and identifying fewer network 
upgrades that are able to accommodate multiple interconnection 
requests, particularly requests that may be located in a similar 
area.\107\
---------------------------------------------------------------------------

    \107\ See May Joint Task Force Tr. 43:25-44:4 (Riley Allen) 
(``Clustering helps the regions identify what I'll call the backbone 
or trunk facilities that provide efficiencies in the system to the 
benefit ultimately of ratepayers. New England has been relying on 
clustering and I'm told that that's going very well.'').
---------------------------------------------------------------------------

    55. Moreover, advancing interconnection customers' facilities 
through the queue based solely on date of entry may result in 
inefficiencies where earlier queued customers have the potential to 
delay later-queued facilities. Specifically, the serial process 
combined with existing allocation of costs may cause unreasonable 
delays in the study process. Under existing tariffs within the RTOs/
ISOs and non-RTO/ISO regions, the transmission provider allocates the 
full cost of those network upgrades to the individual interconnection 
customer. Although the crediting policy in the pro forma LGIP requires 
that the interconnection customer is ultimately reimbursed for the cost 
of the network upgrades, the large upfront network upgrade cost 
allocation may render a proposed generating facility economically non-
viable, such that the interconnection customer is forced to withdraw 
from the interconnection queue.\108\ Unless the withdrawing 
interconnection customer's proposed generating facility is electrically 
isolated, this withdrawal will also trigger individual re-study of 
lower-queued interconnection requests. As the transmission provider 
attempts to allocate this large network upgrade cost to the next 
interconnection customer in the interconnection queue, it can cause 
several projects to withdraw and trigger further re-studies--commonly 
referred to as cascading re-studies. If the interconnection customer 
does not withdraw and pays for the network upgrade to be constructed, 
lower-queued interconnection customers that will benefit from the 
network upgrade are not required to share cost responsibility simply 
because they submitted an interconnection request at a later date.\109\ 
Therefore, the existing serial study process may now be unjust and 
unreasonable because interconnection customers are no longer able to 
consistently progress through the interconnection process in a 
timeframe consistent with Order No. 2003 and the pro forma LGIP. 
Further, the existing serial study process may now be unjust and 
unreasonable because the process frequently allocates to individual 
interconnection customers the cost network upgrades that may create 
additional interconnection capacity needed for several interconnection 
customers.
---------------------------------------------------------------------------

    \108\ See, e.g., Duke, 176 FERC ] 61,075 at P 3 (explaining 
that, in many cases, assignment of such significant network upgrade 
costs can make new generation projects infeasible, incentivizing 
those projects to delay in committing to fund the network upgrades 
or to withdraw from the interconnection queue, causing delays and 
the need for re-studies). Interconnection customers may be even more 
likely to withdraw in RTO/ISO areas where the Commission has allowed 
for participant funding of network upgrades, whereby the 
interconnection customer will not be fully reimbursed for the cost 
of the network upgrades.
    \109\ See Order No. 845-A, 166 FERC ] 61,137 at P 78 (``The 
principle of cost causation generally requires that costs `are to be 
allocated to those [that] cause the costs to be incurred and reap 
the resulting benefits.''') (citing S.C. Pub. Serv. Auth. v. FERC, 
762 F.3d 41, 87 (D.C. Cir. 2014)) (quoting NARUC v. FERC, 475 F.3d 
at 1285).
---------------------------------------------------------------------------

b. Proposed Reforms
i. Background
    56. The serial first-come, first-served study process in the pro 
forma LGIP includes three distinct studies, conducted on an individual 
basis, to identify the interconnection facilities and network upgrades 
that are needed to accommodate the interconnection request and provide 
an estimate of the cost responsibility and timing for those facilities. 
Each study incorporates the base case study model, which includes all 
generating facilities and the associated interconnection facilities and 
network upgrades needed for higher-queued interconnection requests that 
are pending, as well as an up-to-date model of the transmission 
provider's transmission system.\110\ First, the transmission provider 
conducts the feasibility study, which is a preliminary evaluation of 
the system impact and cost of interconnecting the generating facility 
to the transmission provider's transmission system, and consists of a 
power flow and short circuit analysis.\111\ The transmission provider 
must use reasonable efforts to complete the feasibility study no later 
than 45 days after it receives the executed interconnection feasibility 
study agreement.\112\
---------------------------------------------------------------------------

    \110\ Pro forma LGIP section 2.3.
    \111\ Id. section 6.2. Some transmission providers--including 
CAISO, Arizona Public Service Company, El Paso Electric Company (El 
Paso Electric), Sierra Pacific Power Company and Nevada Power 
Company (jointly, NV Energy), and Public Service Company of New 
Mexico (PNM)--have eliminated the feasibility study to reduce 
interconnection request processing time.
    \112\ Id. section 6.3.
---------------------------------------------------------------------------

    57. Second, the transmission provider conducts the system impact 
study. The system impact study identifies and details the impacts to 
the transmission provider's transmission system or an affected system 
of the interconnection of the proposed generating facility.\113\ The 
system impact study consists of a short circuit analysis, a stability 
analysis, and a power flow analysis. The transmission provider must use 
reasonable efforts to complete the system impact study within 90 days 
after it receives the executed interconnection system impact study 
agreement.\114\ The pro forma LGIP provides transmission providers with 
the option to study interconnection requests on a clustered basis for 
the system impact study.\115\
---------------------------------------------------------------------------

    \113\ Id. section 7.3.
    \114\ Id. section 7.4.
    \115\ Order No. 2003, 104 FERC ] 61,103 at PP 153-156; pro forma 
LGIP section 4.2. If the transmission provider elects to study 
interconnection requests using clustering, all interconnection 
requests received within 180 days (queue cluster window) must be 
studied together without regard to the nature of the underlying 
interconnection service, whether NRIS or ERIS. However, the pro 
forma LGIP allows the transmission provider to study an 
interconnection request separately based on the electrical 
remoteness of the proposed generating facility. Pro forma LGIP 
section 4.2.
---------------------------------------------------------------------------

    58. Third, the transmission provider conducts the facilities study, 
which specifies and estimates the cost of the equipment, engineering, 
procurement, and construction work needed to implement the conclusions 
of the system impact study.\116\ Where the system impact study focuses 
mainly on impacts to the transmission system, the facilities study aims 
to provide a more accurate estimate of the electrical switching 
configuration of the connection equipment, such as transformers, 
switchgear, meters, and other station equipment and a more accurate 
estimate of the specific costs associated with required network 
upgrades rather than a per-mile estimate. The facilities study will 
also identify any potential control equipment needed to accommodate 
requests for interconnection service that are lower than the generating 
facility capacity. Interconnection customers

[[Page 39946]]

have two options for the timeframe in which the facilities study must 
be completed: 90 days, if the interconnection customer requests a +/-
20% cost estimate contained in the report; or 180 days, if the 
interconnection customer requests a +/-10% cost estimate.\117\
---------------------------------------------------------------------------

    \116\ Id. section 8.2.
    \117\ If the interconnection customer wants its cost estimate to 
be accurate within a range of +/-20%, the study must be completed 
within 90 days since there is greater room for error on the part of 
the transmission provider's estimate, whereas if the interconnection 
customer wants its cost estimate to be accurate within a range of +/
-10%, the transmission provider has up to 180 days to develop a more 
accurate cost estimate. Id. section 8.3.
---------------------------------------------------------------------------

    59. Re-study is required when (1) a higher-queued interconnection 
request withdraws from the interconnection queue, (2) a higher-queued 
interconnection request modifies its proposed generating facility 
pursuant to section 4.4 of the pro forma LGIP, or (3) the 
interconnection customer redesignates its point of 
interconnection.\118\ Transmission providers are required to conduct 
re-study of the feasibility study within 45 days of the triggering 
event and re-study of the system impact and facilities studies within 
60 days of the triggering event.
---------------------------------------------------------------------------

    \118\ Id. sections 6.4, 7.6, 8.5.
---------------------------------------------------------------------------

    60. Under the pro forma LGIP, the interconnection customer can 
request to begin negotiations to the LGIA with the transmission 
provider at any time after the interconnection customer executes the 
interconnection facilities study agreement, for not more than 60 days 
after tender of the final interconnection facilities study report.\119\ 
If the interconnection customer determines that negotiations are at an 
impasse, it may request termination of the negotiations at any time 
after tender of the draft LGIA and request submission of the unexecuted 
LGIA to the Commission, or initiate dispute resolution procedures. The 
transmission provider must provide a final LGIA to the interconnection 
customer within 15 days after the completion of the negotiation 
process. Within 15 days after receipt of the final LGIA, the 
interconnection customer must provide the transmission provider either 
(1) reasonable evidence of continued site control or (2) post 
additional non-refundable security of $250,000, which will be applied 
toward future construction costs.\120\ The interconnection customer 
also must provide reasonable evidence that it has achieved one or more 
milestones in the development of the generating facility as listed in 
section 11.3 of the pro forma LGIP. As soon as practicable, but not 
later than 10 days after receiving the tendered LGIA or the request to 
file an unexecuted LGIA, the transmission provider must file the LGIA 
with the Commission.\121\
---------------------------------------------------------------------------

    \119\ Id. section 11.2.
    \120\ Id. section 11.3.
    \121\ Id.
---------------------------------------------------------------------------

    61. The Commission has stated that clustering is the preferred 
method for conducting interconnection studies, and has strongly 
encouraged clustering in interconnection queue management and 
interconnection study processes for all transmission providers.\122\ In 
the 2008 Technical Conference Order, the Commission noted that 
clustering that takes into account factors other than the 
interconnection request filing date may allow for more efficient 
prioritization of interconnection requests while still providing 
protection from undue discrimination by transmission providers.\123\ 
Subsequently, the Commission approved many variations of cluster study 
processes where the transmission provider groups interconnection 
requests received during an open window period and processes those 
requests as a cluster, with some form of shared cost responsibility for 
identified network upgrades triggered by the cluster. The Commission 
noted that performing studies in clusters helps alleviate 
interconnection queue backlogs and offers considerable benefits as the 
network upgrades required for an interconnection customer to 
interconnect to the transmission system may be large enough to 
accommodate more than one interconnection request.\124\ Generally, 
cluster study processes include the following elements: (1) an 
interconnection request window; (2) a customer engagement window; (3) 
cluster studies including (a) a power-flow and voltage study, which is 
similar to a feasibility study under the pro forma LGIP, and (b) a 
stability and short circuit study, which completes the traditional 
system impact study; (4) a facilities study; (5) re-study, if needed; 
and (6) LGIA execution or filing of an unexecuted LGIA.
---------------------------------------------------------------------------

    \122\ Order No. 2003, 104 FERC ] 61,103 at P 155, Order No. 
2006, 111 FERC ] 61,220 at P 181.
    \123\ 2008 Technical Conference Order, 122 FERC ] 61,252 at P 
18.
    \124\ Midwest Ind. Sys. Operator, Inc., 124 FERC ] 61,183 at PP 
114, 143 (accepting usage of group studies as a means to help 
alleviate interconnection queue backlog and finding that clustering 
studies offers considerable benefits); SPP, 128 FERC ] 61,114 at P 
32 (finding that performing cluster studies should enable processing 
the interconnection queue backlog more effectively); So. Cal. Edison 
Co., 135 FERC ] 61,093, at P 50 (2011) (finding that coordinating 
the cluster study processes for interconnection requests to a 
utility's transmission and distribution systems would ``achieve 
greater efficiency and effectively manage network impacts''); see 
also May Joint Task Force Tr. 42:3-9 (Gladys Brown Dutrieuille) 
(explaining that clustering has two goals: minimizing the study time 
and minimizing the first mover disadvantage by sharing costs among 
those resources that need the same upgrades).
---------------------------------------------------------------------------

    62. To join a cluster, an interconnection customer must generally 
submit a valid interconnection request before the close of the request 
window for that cluster. Some transmission providers accept 
interconnection requests during an annual \125\ window, whereas others 
have a semi-annual \126\ window. After the interconnection requests are 
received and deemed valid, and before the start of the interconnection 
study process for the cluster, a customer engagement window 
begins.\127\ During the customer engagement window, transmission 
providers work with interconnection customers to build study models, 
verify data, hold stakeholder meetings, and generally prepare for the 
interconnection study process. At the end of the customer engagement 
window, all interconnection customers with complete interconnection 
requests and a signed study agreement will be included in that cluster.
---------------------------------------------------------------------------

    \125\ PacifiCorp, Tri-State, Duke, ISO New England Inc. (ISO-
NE), MISONYISO, and SPP have annual windows.
    \126\ PNM, Arizona Public Service Company, El Paso Electric, NV 
Energy, PSCo, and CAISO have semi-annual windows.
    \127\ PSCo and Tri-State have 75-day customer engagement 
windows, while Duke has a 60-day customer engagement window.
---------------------------------------------------------------------------

    63. Many transmission providers with large transmission systems 
typically group interconnection requests on the basis of geographic 
location and electrical relevance before conducting a cluster 
study.\128\ Most transmission providers that use a cluster study 
process still conduct facilities studies on an individual basis.\129\ 
In addition, some non-RTO/ISO transmission providers offer a separate 
generator interconnection process for interconnection customers 
participating in a resource solicitation process.\130\
---------------------------------------------------------------------------

    \128\ MISO, CAISO, SPP, ISO-NE, NV Energy, Arizona Public 
Service Company, and PNM group projects in such a way, and 
PacifiCorp and Tri-State have added the term Cluster Area to their 
LGIPs. See PacifiCorp, Transmission OATT and Service Agreements, 
part. IV.36 (Definitions) (5.0.0); Tri-State Generation and 
Transmission Association, Inc., Open Access Transmission Tariff, 
attach. N, Standard LGIP (7.0.0), section 1.
    \129\ NV Energy, however, uses clusters for the facilities 
study. MISO performs both the system impact study and facilities 
study in a group study format.
    \130\ The resource solicitation process provision is discussed 
later in the NOPR.

---------------------------------------------------------------------------

[[Page 39947]]

ii. Proposal
    64. We propose to revise the pro forma LGIP and pro forma LGIA to 
make cluster studies the required interconnection study method under 
the pro forma LGIP.\131\ We therefore propose to require transmission 
providers to eliminate the serial first-come, first-served study 
process and instead use a first-ready, first-served cluster study 
process. We preliminarily find that a first-ready, first-served cluster 
study process, coupled with increased financial commitments and 
readiness requirements that we also propose in this NOPR, will address 
the interconnection queue issues described above, thereby remedying 
potentially unjust and unreasonable Commission-jurisdictional 
rates.\132\ Even in areas that have not yet experienced large backlogs, 
we believe the first-ready, first-served cluster study process 
increases efficiency of the interconnection process and would help 
prevent delays in the future. A first-ready, first-served cluster study 
process is a more efficient way of studying a large interconnection 
queue because transmission providers can perform larger interconnection 
studies encompassing numerous proposed generating facilities, rather 
than separate studies for each individual interconnection 
customer.\133\ Additionally, conducting a single cluster study and 
cluster re-study each year would minimize delays that can arise from 
proposed generating facility interdependencies and also minimize the 
risk of cascading re-studies when a higher-queued interconnection 
customer withdraws.\134\ This limited re-study process would consume 
far less time than under a serial first-come, first-served re-study 
process, which requires re-studying all proposed generating facilities 
in isolation with a new base case. In addition, the proposed reforms 
may assist interconnection queue management because, even if clusters 
have cascading re-study issues, there will be fewer re-studies needed 
and fewer cost consequences for lower-queued generators as compared to 
serial re-studies. Thus, we believe that requiring a first-ready, 
first-served cluster study process, coupled with increased financial 
commitments and readiness requirements that we also propose in this 
NOPR, should improve the efficiency in processing generator 
interconnection requests, and result in just and reasonable Commission-
jurisdictional rates.
---------------------------------------------------------------------------

    \131\ See May Joint Task Force Tr. 46:15-19 (Clifford 
Rechtschaffen) (stating that CAISO's cluster process has been 
helpful and important for improving interconnection queue processing 
and that clustering ``is a best practice and should be promoted'').
    \132\ See 2020 Tri-State Order, 173 FERC ] 61,015 at PP 29, 45 
(finding that a first-ready, first-served cluster study process 
would address interconnection queue backlog and rejecting the filing 
on other grounds); PacifiCorp, 171 FERC ] 61,112 at P 47 (finding 
that proposed interconnection queue reform was a just and reasonable 
solution to an interconnection queue backlog); PSCo, 169 FERC ] 
61,182 at P 30 (same); Pub. Serv. Co. of N.M., 136 FERC ] 61,231, at 
P 77 (2011) (PNM) (finding that first-ready, first-served cluster 
study process would address interconnection queue backlog and allow 
projects that are further along in development to proceed on a more 
accelerated basis while allowing less developed projects to receive 
early information); Duke, 176 FERC ] 61,075 at P 51 (finding that 
proposed revisions to Duke LGIP and LGIA were consistent with or 
superior to the pro forma LGIP and LGIA); see also Tri-State, 174 
FERC ] 61,021 at P 27 (noting previous findings from the 2020 Tri-
State Order).
    \133\ See Duke, 176 FERC ] 61,075 at P 52 (finding that Duke's 
transition to a first-ready, first-served cluster study process 
could relieve ``(1) delays in completing generator interconnection 
studies; (2) inability of interconnection customers to share costs 
of network upgrades; and (3) existence of non-viable projects in the 
queues''); see also Tri-State, 174 FERC ] 61,021 at P 31 (noting 
PSCo's Comments that PSCo's preliminary experience of operating 
under the cluster study process has demonstrated that ``studying 
requests in clusters is shown to be more efficient than studying 
each request individually,'' and that ``this approach to generator 
interconnection is superior to the pro forma LGIP and LGIA'').
    \134\ PNM, 136 FERC ] 61,231 at P 79 (noting that ``PNM's 
proposal adopting the cluster approach to study related projects 
together will likely improve efficiency by limiting the need for re-
studies'') (citing Order No. 2006, 111 FERC ] 61,220, at P 181).
---------------------------------------------------------------------------

    65. In particular, we propose several revisions to the pro forma 
LGIP and pro forma LGIA to implement a first-ready, first-served 
cluster study process. We describe these revisions briefly in this 
section and include the full proposed language in appendices to this 
NOPR. We propose to add several new defined terms and revise several 
defined terms in section 1 of the pro forma LGIP and article 1 of the 
pro forma LGIA. For example, we propose to modify the definition of 
stand alone network upgrade to clarify that, for a network upgrade to 
be eligible for treatment as a stand alone network upgrade,\135\ the 
network upgrade must only be required for one interconnection customer. 
This clarification should prevent lengthy conflict and negotiations in 
instances where multiple interconnection requests trigger the need for 
a network upgrade that could be considered a stand alone network 
upgrade under the current definition mainly because it can be 
constructed without affecting day-to-day operations of the transmission 
system, and several interconnection customers have an interest in 
exercising the option to build. We also propose modifying the 
definition of material modification to account for the equal queue 
position of generating facilities in the same cluster.\136\ The new 
definition would clarify that material modifications are those with a 
material impact on the cost or timing of interconnection requests with 
a later or equal queue position.
---------------------------------------------------------------------------

    \135\ Under the current pro forma, Stand Alone Network Upgrades 
are defined as ``Network Upgrades that are not part of an Affected 
System that an Interconnection Customer may construct without 
affecting day-to-day operations of the Transmission System during 
their construction. Both the Transmission Provider and the 
Interconnection Customer must agree as to what constitutes Stand 
Alone Network Upgrades and identify them in Appendix A to the 
Standard Large Generator Interconnection Agreement. If the 
Transmission Provider and Interconnection Customer disagree about 
whether a particular Network Upgrade is a Stand Alone Network 
Upgrade, the Transmission Provider must provide the Interconnection 
Customer a written technical explanation outlining why the 
Transmission Provider does not consider the Network Upgrade to be a 
Stand Alone Network Upgrade within 15 days of its determination.'' 
Pro forma LGIP section 1.
    \136\ Under the current pro forma, Material Modification is 
defined as ``those modifications that have a material impact on the 
cost or timing of any Interconnection Request with a later queue 
priority date.'' Pro forma LGIP section 1.
---------------------------------------------------------------------------

    66. We propose revisions to add new subsection 3.1.1.1 (Initial 
Study Deposit) to the pro forma LGIP, which provides that an 
interconnection customer must submit its interconnection request and 
applicable study deposit during a cluster request window (described 
below). We also propose to add new subsection 3.1.2 (Submission) to the 
pro forma LGIP, which provides that interconnection customers 
evaluating different options (such as different sizes, sites, or 
voltages) are encouraged but not required to use the new informational 
interconnection study proposed in this NOPR before entering the cluster 
study. New subsection 3.1.2 of the pro forma LGIP also provides that 
the interconnection customers must select a definitive point of 
interconnection to be studied when executing the cluster study 
agreement. Upon mutual agreement, the transmission provider may make 
reasonable changes to the requested point of interconnection to 
facilitate efficient interconnection of clustered interconnection 
requests at common points of interconnection.
    67. We also propose to add new subsection 3.4.1 (Cluster Request 
Window) to the pro forma LGIP, which provides that interconnection 
customers must submit an interconnection request during a specified 
period, the cluster request window, which is a 45-day period with the 
start date to be determined by each transmission provider (with the 
annual start date for the transmission provider's cluster

[[Page 39948]]

request window included in its LGIP). The transmission provider would 
consider all interconnection requests accepted within this period to 
have equal queue priority for purposes of the cluster study. Following 
the close of the cluster request window, the transmission provider 
would begin a 30-day customer engagement window as provided in new 
subsection 3.4.5 (Customer Engagement Window) of the pro forma LGIP.
    68. We propose to renumber and revise subsection 3.4.4 (Scoping 
Meeting) as subsection 3.4.6 of the pro forma LGIP to provide that, 
during the customer engagement window, transmission providers must hold 
a scoping meeting with all interconnection customers whose 
interconnection requests were received in that cluster request window. 
Revised subsection 3.4.6 of the pro forma LGIP would also require 
transmission providers to hold individual customer-specific scoping 
meetings, at the interconnection customer's request, which must be 
requested by no later than 15 business days after the close of the 
cluster request window. By the end of the customer engagement window, 
the transmission provider would post on OASIS the final cluster study 
plan, which lists all valid interconnection requests with an executed 
cluster study agreement that will be part of the cluster study.
    69. We propose to replace the sections of the pro forma LGIP, 
including subsection 3.5.2 (Requirement to Post Interconnection Study 
Metrics) of the pro forma LGIP, that require the posting of metrics for 
interconnection feasibility studies processing time and system impact 
study processing time with sections that require the posting of metrics 
for cluster study processing time and cluster re-study processing time. 
We also propose to add a new subsection to require the posting of the 
time from when the transmission provider received a valid 
interconnection request to the completion of the cluster study, cluster 
re-study, and facilities study.
    70. We also propose several revisions to section 4 (Queue Position) 
of the pro forma LGIP to make clear that cluster studies are the 
required interconnection study method under the pro forma LGIP and that 
transmission providers may not have a first-come, first-served 
interconnection study method under their respective LGIPs. We propose 
to rename and revise section 4.1 of the pro forma LGIP as ``Queue 
Position'' and add two new subsections: (1) subsection 4.1.1 
(Assignment of Queue Position), which makes clear that queue position 
will be based on the time and date that the transmission provider 
receives all items required under section 3.4 (Valid Interconnection 
Request) and that there is no queue priority for interconnection 
customers that opted for informational interconnection studies; \137\ 
and (2) subsection 4.1.2 (Higher Queue Position), which provides that 
all interconnection requests studied in a single cluster shall be 
considered to have equal queue priority, but clusters initiated earlier 
in time shall be considered to have a higher queue position than 
clusters initiated later. To be clear, the date of submission of an 
individual interconnection request within the same cluster would have 
no bearing on the allocation of the cost of the network upgrades 
identified in the applicable cluster study, because such costs would be 
allocated among interconnection requests using a proportional impact 
method (discussed below in section II.A.4.).
---------------------------------------------------------------------------

    \137\ See supra PP 42-45 (explaining that the informational 
interconnection study is intended to provide prospective 
interconnection customers with information prior to entering the 
queue).
---------------------------------------------------------------------------

    71. New subsection 4.1.2 of the pro forma LGIP also provides that 
moving a point of interconnection shall result in a loss of queue 
position if the transmission provider deems the change a material 
modification. To align with this, we propose corresponding changes to 
the material modification provisions in section 4.4 (Modification) of 
the pro forma LGIP to provide that moving a point of interconnection 
shall result in a loss of interconnection queue position if it is 
deemed a material modification by the transmission provider. We note 
that the interconnection customer may decide to forego the requested 
change that constitutes a material modification and retain its existing 
queue position.\138\ We also propose to revise pro forma LGIP section 
4.4.5, which currently states that an extension of less than three 
cumulative years of the generating facility's commercial operation date 
are not material and should be handled through construction sequencing. 
We propose to provide that the commercial operation date reflected in 
the initial interconnection request shall be used in calculating the 
permissible three-year extension.
---------------------------------------------------------------------------

    \138\ Pro forma LGIP section 4.4.3.
---------------------------------------------------------------------------

    72. We propose to remove from section 4.2 (Clustering) of the pro 
forma LGIP the provisions allowing interconnection requests to be 
studied serially. We also propose to remove the requirement for the 
transmission provider to provide 180 days' advance notice before 
opening a cluster window. In addition to removing these provisions, we 
propose to rename section 4.2 of the pro forma LGIP ``General Study 
Process'' and revise it to provide that interconnection studies shall 
be performed within the cluster study process.
    73. We propose to revise subsection 4.4.1 of the pro forma LGIP to 
make clear that: (1) the modifications previously permitted prior to 
return of the executed system impact study agreement are now permitted 
to be made prior to return of the executed cluster study agreement; and 
(2) for plant increases, the incremental increase will be studied with 
the next cluster study for purposes of cost allocation and study 
analysis.
    74. We propose to delete section 6 (Interconnection Feasibility 
Study) of the pro forma LGIP (and all subsections). As explained above, 
we propose to adopt the new section 6 (Interconnection Information 
Access) of the pro forma LGIP to establish a mechanism for the 
interconnection customer to evaluate the feasibility of a prospective 
generating facility. We propose to revise section 7 (Interconnection 
System Impact Study) of the pro forma LGIP to make clear that the 
system impact study will now be conducted on a clustered basis, and 
that the transmission provider must complete the cluster study within 
150 days of the closing of the customer engagement window. We further 
propose revisions to sections 3.4.2 and 8.1 of the pro forma LGIP to 
include the financial commitments and readiness requirements that must 
be met for the interconnection customer to remain in the 
interconnection queue following the completion of the cluster study. 
Those requirements are discussed in greater detail below. We propose 
additional revisions to delete section 7.5 (Meeting with Transmission 
Provider) of the pro forma LGIP and adopt the new section 7.5 (Cluster 
Study Re-Studies) of the pro forma LGIP to include provisions governing 
clustered re-studies where an interconnection customer in the cluster 
or a higher-queued cluster withdraws its interconnection request. 
Specifically, we propose to require transmission providers to conduct a 
re-study of the cluster within 150 days of informing the cluster of the 
need for re-study.
    75. We propose revisions to the facilities study provisions in 
section 8 (Interconnection Facilities Study) of the pro forma LGIP to 
make clear that re-studies can be triggered by a higher or equally 
queued interconnection project withdrawing from the interconnection 
queue or modification of a higher or equally queued interconnection 
project

[[Page 39949]]

pursuant to section 4.4 (Modifications) of the pro forma LGIP.
    76. We also propose revisions to section 11.1 (Tender) of the pro 
forma LGIP to clarify the procedures for executing the LGIA. We propose 
revisions to section 11.3 (Execution and Filing) of the pro forma LGIP 
to provide that the interconnection customer must submit to the 
transmission provider at the same time it submits the executed LGIA 
demonstration of continued site control, the requisite deposit, and 
reasonable evidence of achieving milestones in the development of the 
generating facility. An interconnection customer that requests that the 
transmission provider file an unexecuted LGIA with the Commission must 
submit the aforementioned information within 15 days of the Commission 
issuing an order on the unexecuted LGIA filing, or its interconnection 
request will be deemed withdrawn. We propose revisions to the system 
impact study agreement and facilities study agreement to be consistent 
with the new cluster study process. We propose to add several new 
definitions to section 1 of the pro forma LGIP and article 1 of the pro 
forma LGIA that relate to the new first-ready, first-served cluster 
study process and to modify a number of other definitions.
    77. We seek comment on whether the Commission should require 
transmission providers to conduct cluster studies on subgroups of 
interconnection customers based on areas of geographic and electric 
relevance, and, if so, whether the Commission should adopt provisions 
governing how cluster areas should be formed to ensure that cluster 
areas are formed in a transparent and not unduly discriminatory 
manner.\139\
---------------------------------------------------------------------------

    \139\ Commenters that believe that the Commission should adopt 
provisions governing how cluster areas should be formed should also 
explain how to define such a cluster area (e.g., based on geographic 
proximity, geographic constraints such as bodies of water or 
mountain ranges, system topology, and/or major transmission system 
constraints).
---------------------------------------------------------------------------

    78. We seek comment on whether the pro forma LGIP should specify 
how cluster studies must be rerun after re-study is triggered or 
whether there are provisions the Commission could adopt to improve the 
efficacy of the re-study process, such as preventing excessive re-study 
by limiting the transmission provider to two re-studies per month 
within the 150-day cluster re-study period.
    79. We seek comment on whether the Commission should maintain an 
option in the pro forma LGIP for some interconnection requests to be 
processed outside of the annual cluster study process, and if so, in 
what circumstances and on what timeframe (for completion of the study), 
and on what priority compared to any active clusters.
3. Allocation of Cluster Study Costs
a. Background
    80. Under the pro forma LGIP, interconnection studies are conducted 
for each individual interconnection request and study costs are paid by 
the interconnection customer. Transitioning to a first-ready, first-
served cluster study process would require transmission providers to 
establish a method to allocate the shared cost of clustered 
interconnection studies among the interconnection customers in the 
cluster.
    81. The Commission has accepted a variety of approaches to 
allocating the costs of cluster studies, most of which allocate costs 
using two factors: (1) the total MW size requested in a cluster; and 
(2) the number of interconnection requests in the cluster. Approaches 
among transmission providers vary with regard to the weight assigned to 
each of these factors. For example, Duke and Dominion allocate 90% of 
the applicable study costs to interconnection customers on a pro rata 
basis based on requested MWs included in the applicable cluster, and 
10% on a per capita basis based on the number of interconnection 
requests included in the applicable cluster.\140\ SPP, PNM, PSCo, 
PacifiCorp, and Tri-State allocate 50% of the study costs based on 
requested MWs, and 50% based on the number of interconnection 
requests.\141\ CAISO, NYISO, and MISO only use one of the two factors 
in their allocation method. CAISO and NYISO allocate all study costs 
equally based on the number of interconnection requests within the 
cluster,\142\ while MISO allocates all study costs pro rata based on 
the number of MWs requested.\143\
---------------------------------------------------------------------------

    \140\ See Duke, 176 FERC ] 61,075 at P 18; Dominion, Docket No. 
ER22-301-000 (Dec. 28, 2021) (delegated order).
    \141\ See SPP, OATT, attach. V (4.0.0), section 4.2.5; PNM, 136 
FERC ] 61,231 at P 24; PSCo, 169 FERC ] 61,182 at P 32; PacifiCorp, 
171 FERC ] 61,112 at P 13; Tri-State, 174 FERC ] 61,021 at P 33.
    \142\ CAISO, CAISO eTariff, OATT, app. DD, section 3 (14.0.0), 
section 3.5.1.2; NYISO, NYISO Tariffs, attach. X, section 30.13 
(5.0.0), section 30.13.3.
    \143\ MISO, FERC Electric Tariff, OATT, attach. X, (155.0.0) 
section 3.3.1.
---------------------------------------------------------------------------

b. Proposal
    82. We propose to revise section 13.3 (Obligation for Study Costs) 
of the pro forma LGIP to allocate the shared costs of cluster studies 
as follows: 90% of the applicable study costs to interconnection 
customers on a pro rata basis based on requested MWs included in the 
applicable cluster, and 10% of the applicable study costs to 
interconnection customers on a per capita basis based on the number of 
interconnection requests included in the applicable cluster.\144\ We 
preliminarily find that this allocation of the costs of cluster studies 
would result in just and reasonable Commission-jurisdictional rates 
because it appropriately recognizes that the MW size of a cluster has a 
dramatic impact on the cost of studying the cluster, while also 
recognizing that the number of interconnection requests included in the 
cluster also impacts the cost of studying the cluster, but to a lesser 
degree.
---------------------------------------------------------------------------

    \144\ If an interconnection customer withdraws its 
interconnection request prior to the start of the cluster study, 
that customer would be required to pay the actual costs of 
processing its interconnection request but would not be assessed a 
withdrawal penalty.
---------------------------------------------------------------------------

    83. We seek comment on whether a different cost allocation approach 
may be appropriate or whether each transmission provider should be 
provided additional flexibility to propose a cost allocation approach 
on compliance with any final rule.
4. Allocation of Cluster Network Upgrade Costs
a. Background
    84. As discussed above, under the serial first-come, first-served 
study process in the pro forma LGIP, transmission providers study 
interconnection requests individually and in the order in which they 
are received. If a study identifies a need for network upgrades in 
response to an individual interconnection customer request, the 
transmission provider allocates the initial cost of those network 
upgrades to the individual interconnection customer. The pro forma LGIP 
allows transmission providers to perform clustered system impact 
studies but does not explain how transmission providers should allocate 
network upgrade costs among interconnection customers within a cluster.
    85. Several of the transmission providers that have adopted a 
cluster first-ready, first-served study process have also adopted 
methods for allocating network upgrade costs that differ from their 
previously existing cost allocation mechanisms in one of two ways: (1) 
proportional capacity (based on the proposed generating facility's MW 
capacity in proportion to the cluster's total MW capacity); or (2) 
proportional impact (determined based

[[Page 39950]]

on a distribution factor analysis). Several transmission providers also 
separate network upgrades into two categories prior to allocating costs 
based on the proportional capacity or proportional impact method: (1) 
station equipment, including all equipment located in the substation 
immediately beyond the point of interconnection to which the generating 
facility is connected (called station equipment network upgrades); and 
(2) all other network upgrades, including equipment located beyond the 
substation, such as transmission lines, transformers, voltage support, 
and distantly located breakers (called system network upgrades).\145\ 
These methods allocate station equipment network upgrade costs based on 
the number of generating facilities interconnecting at an individual 
station (i.e., allocated equally to each interconnection customer 
interconnecting to the substation).
---------------------------------------------------------------------------

    \145\ E.g., PNM, 136 FERC ] 61,231 at P 25.
---------------------------------------------------------------------------

    86. For network upgrades beyond the transmission provider's 
substation, PNM and PacifiCorp use the proportional capacity 
method.\146\ PacifiCorp explained in its interconnection queue reform 
proposal that the proportional capacity method is better for PacifiCorp 
given the size of its service territory, and that PacifiCorp uses a 
cluster area approach in which it clusters projects by electrical 
relevance, which prevents interconnection customers from bearing the 
costs of network upgrades in distant areas of PacifiCorp's transmission 
system.\147\
---------------------------------------------------------------------------

    \146\ Id.; PacifiCorp, 171 FERC ] 61,112 at P 18.
    \147\ PacifiCorp, Transmittal, Docket No. ER20-924-000, at n.107 
(filed Jan. 31, 2020).
---------------------------------------------------------------------------

    87. CAISO, MISO, SPP, NYISO, PSCo, Tri-State, Duke, and Dominion 
use the proportional impact method by performing a distribution factor 
analysis.\148\ Relative to other transmission providers, Tri-State 
includes a more comprehensive explanation of its distribution factor 
analysis method in its tariff. Specifically, Tri-State's tariff 
provides that: (1) thermal network upgrade costs are allocated based on 
the impact (in MWs) from each generating facility within the cluster or 
cluster area; (2) voltage network upgrade costs are allocated based on 
the voltage impact from each generating facility within the cluster or 
cluster area on the most constrained bus under the most constraining 
contingency in the definitive interconnection study case(s); (3) 
transient stability network upgrade costs within a cluster or cluster 
area are allocated based on the pro rata share of the total MW requests 
of all generating facilities causing instability; (4) short circuit 
network upgrade costs are allocated based on the impact (in 
kiloamperes) from each generating facility within the cluster or 
cluster area, on the constrained facilities under the most constraining 
fault in the definitive interconnection study case(s); and (5) in 
instances when a network upgrade resolves multiple types of constraints 
(such as thermal and voltage or thermal and voltage and transient 
stability), the costs are allocated within a cluster or cluster area 
based on a ratio share of the total cost of the independent mitigation 
types to equitably allocate the cost to all generating facilities 
contributing to constraints.\149\
---------------------------------------------------------------------------

    \148\ PSCo, 169 FERC ] 61,182 at P 34; Tri-State, 174 FERC ] 
61,021 at P 38; Duke, 176 FERC ] 61,075 at P 11; Dominion, Docket 
No. ER22-301-000 (Dec. 28, 2021) (delegated order).
    \149\ Tri-State LGIP section 4.2.4.b.
---------------------------------------------------------------------------

b. Proposal
    88. We propose to revise the pro forma LGIP to include new 
subsection 4.2.3 to require transmission providers to allocate network 
upgrade costs to interconnection customers within a cluster using a 
proportional impact method. Therefore, we propose to establish the 
definition ``Proportional Impact Method'' in the pro forma LGIP,\150\ 
and require transmission providers to revise their LGIPs to include the 
specific technical parameters and thresholds of the method for cost 
allocation. We preliminarily find that this approach will ensure just 
and reasonable Commission-jurisdictional rates because it will allow 
the transmission provider to allocate network upgrade costs among 
several interconnection customers that may benefit from (and cause the 
need for) certain network upgrades.\151\ By allocating shared network 
upgrade costs among a cluster of interconnection customers, we expect 
that this reform will reduce the frequency of an individual customer 
being allocated a large network upgrade that benefits subsequent 
interconnection customers, reduce the incentive to submit multiple 
speculative requests, and reduce the amount of cascading withdrawals 
and re-studies. We believe that a proportional impact method will 
accurately reflect the level of contribution of an interconnection 
request to the need for the network upgrade.
---------------------------------------------------------------------------

    \150\ We propose to revise section 1 of the pro forma LGIP to 
provide that Proportional Impact Method shall mean a technical 
analysis conducted by the transmission provider to determine the 
degree to which each generating facility in the cluster contributes 
to the need for a specific network upgrade.
    \151\ Tri-State, 174 FERC ] 61,021 at P 38.
---------------------------------------------------------------------------

    89. We seek comment on whether there are specific types of analyses 
that the Commission should require transmission providers to use to 
determine the proportional impact attributed to an interconnection 
request, including the benefits and drawbacks of any proposed approach. 
Conversely, we seek comment on whether there are specific types of 
analyses that the Commission should prohibit because they are known to 
be inaccurate, provide undue discretion to the transmission provider, 
or could otherwise be problematic. Additionally, we seek comment on 
alternative methods to allocate the cost of network upgrades within a 
cluster such as the proportional capacity method as discussed above. 
While such a method does not assign cost based on level of contribution 
of an interconnection request to the need for a network upgrade, we 
seek comment on whether this method can be sufficiently accurate, in 
certain instances, in a manner consistent with or superior to the 
proposed method. For instance, we seek comment on whether the 
proportional capacity method may be appropriate when a transmission 
provider with a relatively small service territory clusters projects by 
electrical relevance. Conversely, we seek comment on whether there are 
some circumstances where the proportional capacity method would not be 
appropriate, such as circumstances where there may be potential for 
discriminatory treatment.
5. Shared Network Upgrades
a. Background
    90. There are no existing provisions in the pro forma LGIP that 
require transmission providers to share network upgrade costs between 
earlier-in-time and later-in-time interconnection customers (e.g., 
customers studied in separate clusters). However, in MISO and NYISO, 
the Commission has approved tariff provisions that require 
interconnection customers in later cluster studies that benefit from 
network upgrades completed prior to that later-in-time interconnection 
customer commencing commercial operation to partially reimburse the 
interconnection customers in an earlier cluster study that were 
initially responsible for the facilities' construction.\152\
---------------------------------------------------------------------------

    \152\ See NYISO, NYISO Tariffs, attach. S, section 25 (16.0.0), 
section 25.7.2; MISO, FERC Electric Tariff, MISO OATT, attach. FF 
section III (81.0.0), section III.A.2.d.2.
---------------------------------------------------------------------------

    91. MISO tests all network upgrades in service for less than five 
years to

[[Page 39951]]

determine whether they qualify for cost sharing. MISO requires 
interconnection customers in a later cluster study to share costs if 
they (1) connect to that network upgrade or (2) pass a two-part power 
flow screening.\153\ If the test reveals that more than five MW of the 
later-in-time interconnection customer's generating facility uses the 
network upgrade with a network upgrade rating exceeding one percent, 
MISO performs an additional analysis. If the results of the second 
analysis conclude that the interconnection customer generating 
facility's impact exceeds more than five percent of the network 
upgrade's facility rating, or that the transmission distribution factor 
(TDF) \154\ is greater than 20%, the interconnection customer in the 
later cluster study will reimburse interconnection customers from the 
earlier cluster study based on the share of the cost of the network 
upgrade allocated to each interconnection customer. MISO allocates the 
costs of the shared network upgrades using the pro rata share of the MW 
contribution on all constraints from each project.
---------------------------------------------------------------------------

    \153\ MISO Business Practice Manual No. 15, section 6.1.1.1.11, 
version 23 (May 2021), <a href="https://cdn.misoenergy.org/BPM%20015%20-%20Generation%20Interconnection49574.zip">https://cdn.misoenergy.org/BPM%20015%20-%20Generation%20Interconnection49574.zip</a>
    \154\ TDF measures the energy the interconnection customer has 
requested to inject onto the transmission system, expressed as the 
percent of the flows across a given transmission facility.
---------------------------------------------------------------------------

    92. NYISO accounts for excess capacity created by network upgrades 
and requires that interconnection customers in a later cluster study 
reimburse the interconnection customers from an earlier cluster study 
for the use of these facilities. NYISO tracks any excess capacity, or 
headroom,\155\ created by network upgrades and determines eligibility 
for cost sharing using two methods. When technically feasible, a later-
in-time interconnection customer's use of headroom is measured in terms 
of the interconnection customer's electrical impact. Otherwise, 
headroom usage is based on the total number of interconnection 
customers using a given network upgrade. The headroom is available for 
10 years or until it is depleted.\156\
---------------------------------------------------------------------------

    \155\ NYISO defines headroom as ``the functional or electrical 
capacity of the System Upgrade Facility or the electrical capacity 
of the System Deliverability Upgrade that is in excess of the 
functional or electrical capacity actually used by the Developer's 
Project.'' NYISO, NYISO Tariffs, attach. S, section 25.1 (12.0.0).
    \156\ See id. section 25.8.7.
---------------------------------------------------------------------------

b. Relevant ANOPR Comments
    93. Multiple commenters support the concept of cost sharing 
approaches. The National Association of Regulatory Utility 
Commissioners (NARUC), for example, contends that the Commission should 
encourage improvements to the participant funding model through sharing 
the costs of clusters of similarly situated interconnection 
customers.\157\
---------------------------------------------------------------------------

    \157\ NARUC, Comments, Docket No. RM21-17-000, at 23 (filed Oct. 
12, 2021).
---------------------------------------------------------------------------

    94. MISO and NYISO each highlight the advantages of their existing 
network upgrade cost sharing approaches. MISO claims that its cost 
sharing method appropriately balances the interconnection customers' 
interests.\158\ NYISO asserts that its group-based facilities study 
minimizes later-in-time interconnection customers benefiting without 
paying for the use of a network upgrade at the outset.\159\ NYISO also 
states that its headroom accounting process partly addresses the issue 
caused by later-in-time interconnection customers benefiting from 
preexisting network upgrades.
---------------------------------------------------------------------------

    \158\ MISO, Comments, Docket No. RM21-17-000, at 87-88 (filed 
Oct. 12, 2021).
    \159\ NYISO, Comments, Docket No. RM21-17-000, at 45 (filed Oct. 
12, 2021).
---------------------------------------------------------------------------

    95. The Michigan Commission asserts that MISO has not made frequent 
use of its shared network upgrade process and suggests that the 
Commission explore whether analyzing network upgrades up to 20 years 
post-construction would encourage the development of higher-cost 
network upgrades in transmission constrained areas.\160\
---------------------------------------------------------------------------

    \160\ Michigan Comm'n, Comments, Docket No. RM21-17-000, at 21-
22 (filed Oct. 12, 2021).
---------------------------------------------------------------------------

    96. Some commenters argue that a network upgrade sharing 
arrangement would be too complicated to execute and lead to stakeholder 
disagreements. EDF asserts that, while a study-based cost allocation 
might offer a more precise representation of benefits, such approaches 
are time-consuming and can be prone to stakeholder disagreement over 
the study's assumptions and results; EDF believes that any cost sharing 
percentage for generators should be commensurate with the value of the 
reimbursement generators receive.\161\ TAPS states that, while cost 
sharing arrangements make sense conceptually, developing a cost sharing 
process can be resource-intensive and highly contentious.\162\
---------------------------------------------------------------------------

    \161\ EDF Renewables, Inc., Comments, Docket No. RM21-17-000, at 
13 (filed Oct. 12, 2021).
    \162\ Transmission Access Policy Study Group (TAPS), Comments, 
Docket No. RM21-17-000, at 47-48 (filed Oct. 12, 2021).
---------------------------------------------------------------------------

c. Need for Reform
    97. We preliminarily find that the absence of network upgrade cost 
sharing provisions in the pro forma LGIP poses a barrier to entry to 
generation development. Absent cost sharing provisions among clusters, 
interconnection customers may significantly benefit from earlier-in-
time network upgrades but not share in the cost of those network 
upgrades in a manner that is roughly commensurate with benefits.\163\ 
As a result, individual interconnection customers may be responsible 
for the entire cost of network upgrades and may be reluctant to move 
forward with the development of an interconnection request if there is 
no opportunity to recover some of the costs associated with the 
construction of significant network upgrades that are likely to benefit 
interconnection customers in subsequent cluster studies.
---------------------------------------------------------------------------

    \163\ See May Joint Task Force Tr. 135:6-7 (Andrew French) (``I 
do think costs should be shared between clusters.'')
---------------------------------------------------------------------------

d. Proposal
    98. We propose to revise the pro forma LGIP and pro forma LGIA to 
require transmission providers to allocate the costs for network 
upgrade costs between interconnection customers in an earlier cluster 
study and interconnection customers in a subsequent cluster study that 
benefit from the same network upgrade in a manner that is roughly 
commensurate with the benefits received. First, we propose to require 
that, as part of the first-ready, first-served cluster study process 
that we also propose in this NOPR, the transmission provider analyze 
all network upgrades identified through the transmission provider's 
study process, and, if a generating facility of an interconnection 
customer in a later cluster study directly connects either to (1) a 
network upgrade in-service for less than five years or (2) a substation 
where the network upgrade in-service for less than five years 
terminates, then the transmission provider would be required to 
designate the network upgrade a shared network upgrade, and the 
interconnection customer in the later cluster study would be required 
to contribute a pro rata portion of the shared network upgrade's 
remaining undepreciated capital cost based on the impact the 
interconnection customer in the later cluster study has on the network 
upgrade as measured using the same method the transmission provider 
used to determine the impact of the interconnection customer(s) in the 
earlier cluster study. Second, if the new generating facility does not 
directly connect to the network upgrade, then the transmission provider 
would perform a power flow analysis with a two-step test to measure the 
later-in-time interconnection customer's use of and benefit from the 
network upgrade

[[Page 39952]]

funded by interconnection customers from an earlier cluster study. 
Under the first step, the transmission provider would determine if the 
impact of the interconnection customer in the later cluster study 
exceeds 5 MW and exceeds one percent of the network upgrade's rating, 
which we believe would reasonably identify interconnection customers 
that benefit from the network upgrade. Then, if those criteria are met, 
the transmission provider would determine if the later-in-time 
interconnection customer's impact either exceeds more than five percent 
of the network upgrade's facility rating or if the TDF is greater than 
20%.\164\ Finally, if either of these criteria were met, the 
transmission provider would be required to designate that network 
upgrade a shared network upgrade, and the interconnection customer in 
the later cluster study would be responsible for a pro rata share of 
the network upgrade's remaining undepreciated capital cost based on the 
impact the interconnection customer in the later cluster study has on 
the network upgrade as measured using the same method the transmission 
provider used to determine the impact of the interconnection 
customer(s) from the earlier cluster study.
---------------------------------------------------------------------------

    \164\ Midwest Indep. Transmission Sys. Operator, Inc., 133 FERC 
] 61,221, at P 336 (2010) (finding that the 20% TDF screen is an 
appropriate measure of benefits for shared network upgrades that 
strikes an appropriate balance between cost sharing and guarding 
against overcharging late-coming generating facilities).
---------------------------------------------------------------------------

    99. We propose to require the interconnection customer in the later 
cluster study to pay the transmission provider for the interconnection 
customer's share of the shared network upgrade costs through a one-time 
lump sum, which the transmission provider would disburse to the 
appropriate interconnection customer(s) from the earlier cluster study. 
Where applicable, the interconnection customer from the earlier cluster 
study or the relevant transmission provider would be required to assign 
transmission credits for the portion of the shared network upgrade that 
the interconnection customer in the later cluster study funded to the 
interconnection customer in the later cluster study. Additionally, we 
propose to require that the interconnection customer in the later study 
cluster not be required to pay for its share of the cost of the shared 
network upgrade until that shared network upgrade is in service. We 
propose to require transmission providers to provide the list of shared 
network upgrades to interconnection customers in subsequent cluster 
studies at the conclusion of the cluster study and to list those 
network upgrades in the LGIA.
    100. As noted above, an interconnection customer in a later cluster 
study that otherwise meets the criteria described above would only bear 
some of the network upgrade costs for a network upgrade that was in 
service before the commercial operation date of the generating facility 
of the interconnection customer in the later cluster study. Thus, there 
could be scenarios where the network upgrade may be identified as both 
a shared network upgrade and a contingent facility pursuant to section 
3.8 of the pro forma LGIP; and, therefore a designation of a network 
upgrade as a contingent facility does not preclude it from also being a 
shared network upgrade if the network upgrade meets the aforementioned 
criteria and passes the screens.\165\
---------------------------------------------------------------------------

    \165\ Contingent facilities include ``those unbuilt . . . 
Network Upgrades upon which the Interconnection Request's costs, 
timing, and study findings are dependent, and if delayed or not 
built, could cause a need for Re-Studies of the Interconnection 
Request or a reassessment of the Interconnection Facilities and/or 
Network Upgrades and/or costs and timing.'' Pro forma LGIP section 
1. Pursuant to section 3.8 of the pro forma LGIP, transmission 
providers must have a method for identifying contingent facilities 
to be provided to the interconnection customer at the conclusion of 
the system impact study and including in the LGIA. Id. section 3.8.
---------------------------------------------------------------------------

    101. We preliminarily find that requiring transmission providers to 
develop a method to share network upgrade costs among interconnection 
customers in earlier and later cluster studies will result in just and 
reasonable Commission-jurisdictional rates by allowing for allocation 
of costs of network upgrades in a manner more closely aligned to the 
distribution of benefits than the status quo.\166\ Specifically, to the 
extent that interconnection customers in later cluster studies benefit 
from pre-existing network upgrades, we preliminarily find that it is 
just and reasonable for those interconnection customers to share a 
portion of those network upgrade costs.\167\
---------------------------------------------------------------------------

    \166\ See, e.g., Midwest Indep. Transmission Sys. Operator, 
Inc., 133 FERC ] 61,221 at PP 55, 336 (accepting shared network 
upgrades as just and reasonable and agreeing that the proper test 
for cost sharing with regard to an already-constructed upgrade is 
not what effect a late-coming generating facility would have had on 
the system as it existed prior to the network upgrade, but rather 
whether that late-coming generating facility will actually benefit 
from the network upgrade).
    \167\ Id. P 336.
---------------------------------------------------------------------------

6. Increased Financial Commitments and Readiness Requirements
a. Need for Reform
    102. The pro forma LGIP allows an interconnection customer to 
proceed through the generator interconnection process without having 
shown evidence to the transmission provider of meaningful progress 
toward achieving commercial viability (e.g., a power purchase agreement 
or site control). We are concerned that without requiring this type of 
evidence, interconnection customers will continue to submit multiple 
speculative interconnection requests and later withdraw those requests, 
triggering rounds of re-studies. While we believe that our proposal to 
require transmission providers to implement a first-ready, first-served 
cluster study process will substantially improve transmission 
providers' ability to manage their interconnection queues, we recognize 
that the sheer volume of interconnection requests in interconnection 
queues nationwide are overwhelming many transmission providers' 
resources.\168\ Although the optional informational interconnection 
study that we also propose in this NOPR would provide a mechanism for 
prospective interconnection customers to obtain key information on 
potential points of interconnection for proposed generating facilities, 
prospective interconnection customers may still prefer to submit an 
interconnection request to establish a queue position rather than 
investing in and waiting for the results of an optional informational 
interconnection study.
---------------------------------------------------------------------------

    \168\ See, e.g., Tri-State Generation and Transmission 
Association, Inc., Transmittal Letter, Docket No. ER20-2593-000, at 
3, 14, and 17 (filed Jul. 31, 2020); Transmittal Letter, Docket No. 
ER11-3522-000, at 3 (filed May 5, 2011); PacifiCorp, Transmittal 
Letter, Docket No. ER20-924-000, at 5 (filed Jan. 31, 2020).
---------------------------------------------------------------------------

    103. Therefore, in addition to the reforms that we propose to 
implement a first-ready, first-served cluster study process, we also 
propose a set of reforms to adopt more stringent financial commitments 
and readiness requirements for interconnection customers to remain in 
the interconnection queue to discourage speculative interconnection 
requests and allow transmission providers to focus on processing viable 
interconnection requests and to better approximate the cost of the 
interconnection study process.\169\ These

[[Page 39953]]

proposed reforms pertain to (1) increased study deposits, (2) 
demonstration of site control, (3) commercial readiness, and (4) 
withdrawal penalties.
---------------------------------------------------------------------------

    \169\ See May Joint Task Force Tr. 38:7-8 (Matthew Nelson) 
(``[W]hat we hope to do is try to make sure that being in the queue 
means something[.]''); id 47:1-4 (Clifford Rechtschaffen) 
(cautioning that clustering is important but must be accompanied by 
other reforms to interconnection queue processing to address 
existing problems).
---------------------------------------------------------------------------

b. Proposed Reforms
i. Increased Study Deposits and LGIA Deposit
(a) Background
    104. Under the serial first-come, first-served interconnection 
study process in the pro forma LGIP, an interconnection customer must 
submit the following study deposits: \170\
---------------------------------------------------------------------------

    \170\ Pro forma LGIP sections 6.1, 7.2, 8.1.
---------------------------------------------------------------------------

    <bullet> $10,000 deposit with its interconnection request, which is 
used for the feasibility study,
    <bullet> $50,000 deposit when executing the system impact study 
agreement, and
    <bullet> $100,000 deposit when executing the facilities study 
agreement.
    105. Several transmission providers have increased the study 
deposit requirements in a tiered fashion to recognize that 
interconnection requests with higher generating facility capacities 
cost more to study. In accepting PNM's tiered approach, the Commission 
stated that increasing the study deposit in a tiered fashion is 
reasonable because it recognizes that larger proposed generating 
facilities within a cluster likely carry a greater risk (such as risk 
triggering the need for substantial network upgrades and triggering re-
studies when withdrawing from the queue).\171\ The Commission has 
accepted maximum study deposits as high as $250,000 for interconnection 
requests of 200 MW and greater and accepted proposals requiring study 
deposits at multiple points throughout the interconnection study 
process. For example, PSCo, Tri-State, Dominion, and Duke require four 
study deposits throughout their cluster study processes, and an 
additional deposit upon LGIA execution. In accepting PSCo's study 
deposit framework, the Commission reasoned that the study deposits 
represented the total approximate cost of PSCo's reformed cluster study 
process and that this framework was consistent with Order No. 2003's 
requirement that interconnection customers pay the actual costs of 
their studies.\172\
---------------------------------------------------------------------------

    \171\ PNM, 136 FERC ] 61,231 at P 80.
    \172\ PSCo, 169 FERC ] 61,182 at P 36 (citing Order No. 2003, 
104 FERC ] 61,103 at P 37).
---------------------------------------------------------------------------

 (b) Proposal
    106. We propose to adopt the following study deposit framework in 
the pro forma LGIP:

----------------------------------------------------------------------------------------------------------------
Size of proposed  generating facility  associated with
                interconnection request                                     Amount of deposit
----------------------------------------------------------------------------------------------------------------
>20 MW <80 MW.........................................                                      $35,000 + $1,000/MW.
>80 MW <200 MW........................................                                                 $150,000.
>200 MW...............................................                                                 $250,000.
----------------------------------------------------------------------------------------------------------------

    107. We propose to require transmission providers to collect this 
study deposit before each phase of the new first-ready, first-served 
cluster study process (i.e., cluster study, cluster re-study, and 
facilities study).\173\ We propose to require the interconnection 
customer to provide an initial study deposit along with its 
interconnection request which will be used to pay for the cluster 
study.\174\ We propose to require the interconnection customer to 
provide the second study deposit of the same amount within 20 days of 
receiving the cluster study report from the transmission provider.\175\ 
This second study deposit will cover the cost of any clustered re-
studies. We propose to require the interconnection customer to provide 
the third study deposit of the same amount along with its executed 
facilities study agreement.\176\ Study deposits would be refundable, 
and the transmission provider would refund any portion of the study 
deposits above the applicable study costs and withdrawal penalties once 
the interconnection customer executes the LGIA, requests the filing of 
an unexecuted LGIA and submits the corresponding payment discussed 
below, or withdraws from the queue.\177\
---------------------------------------------------------------------------

    \173\ Proposed pro forma LGIP section 3.1.1.
    \174\ Id. section 3.1.1.1.
    \175\ Id. section 3.1.1.2.
    \176\ Id. section 3.1.1.2.
    \177\ Consistent with Order No. 2003, interconnection customers 
would be responsible for actual study costs, and the study deposits 
would be subject to true-up. Order No. 2003, 104 FERC ] 61,103 at P 
37; pro forma LGIP section 8.1.
---------------------------------------------------------------------------

    108. We also propose to require interconnection customers to submit 
a deposit equal to nine times the amount of its study deposit when 
executing the LGIA or requesting the filing of an unexecuted LGIA.\178\ 
This deposit would be fully refunded once the generating facility 
achieves commercial operation, but if the interconnection customer 
withdraws after executing the LGIA or after requesting the filing of an 
unexecuted LGIA, this deposit would be refunded subject to the 
withdrawal penalty discussed below.
---------------------------------------------------------------------------

    \178\ Proposed pro forma LGIP section 3.1.1.3.
---------------------------------------------------------------------------

    109. We believe that increasing the total study deposit amounts 
submitted in the interconnection study process would better approximate 
the cost of the interconnection study process and disincentivize 
interconnection customers from submitting interconnection requests for 
speculative, non-commercially viable generating facilities. As the 
Commission recognized in the 2008 Technical Conference Order, 
``relatively small deposit amounts, coupled with the incentives 
produced by a first-come, first-served approach to allocating capacity, 
provides an incentive for developers to secure a place in the queue 
even for projects that may not be commercially viable.'' \179\ 
Conversely, the Commission has specifically found that increased study 
deposits ``better identif[y] viable projects that are more ready to 
proceed with construction and commercial operation while discouraging 
speculative projects that could delay the cluster study process.'' 
\180\ The Commission has similarly explained ``that increasing the 
deposit in a tiered fashion . . . is reasonable because it recognizes 
that larger projects likely carry a greater risk.'' \181\ Accordingly, 
we propose to revise section 3 of the pro forma LGIP to implement these 
proposed increased study deposit reforms.
---------------------------------------------------------------------------

    \179\ 2008 Technical Conference Order, 122 FERC ] 61,252 at P 
15.
    \180\ PNM, 136 FERC ] 61,231 at P 80; see also PSCo, 169 FERC ] 
61,182 at PP 36, 49.
    \181\ PNM, 136 FERC ] 61,231 at P 80.
---------------------------------------------------------------------------

    110. We seek comment on whether the proposed study deposit amounts 
accurately estimate the cost of conducting cluster studies, such that 
interconnection customers are not required to submit deposits that are 
likely to far exceed actual study costs. We also seek comment on 
whether the Commission should adopt additional provisions or a 
different framework that would require larger proposed

[[Page 39954]]

generating facilities to provide a higher deposit amount--such as a per 
MW framework.
ii. Demonstration of Site Control
(a) Background
    111. The pro forma LGIP defines site control as documentation 
demonstrating: (1) ownership of, a leasehold interest in, or a right to 
develop a site for the purpose of constructing the generating facility; 
(2) an option to purchase or acquire a leasehold site for such purpose; 
or (3) an exclusivity or other business relationship between the 
interconnection customer and the entity having the right to sell, 
lease, or grant the interconnection customer the right to possess or 
occupy a site for such purpose.\182\ Interconnection customers are 
required to submit a demonstration of site control along with the 
interconnection request or submit a $10,000 deposit in lieu of such a 
demonstration.\183\ The in-lieu-of deposit allows the interconnection 
customer to proceed through the generator interconnection process 
without providing evidence of site control. At the end of the study 
process, within 15 days after receipt of the draft LGIA, the 
interconnection customer must provide evidence of continued site 
control or post $250,000 of non-refundable security that will be 
applied toward future construction costs. The pro forma LGIA allows the 
interconnection customer to suspend its LGIA for up to three years 
before providing the additional security or demonstration of site 
control.\184\
---------------------------------------------------------------------------

    \182\ Pro forma LGIP section 1.
    \183\ Id. section 3.4.1.
    \184\ Pro forma LGIA art. 5.16.
---------------------------------------------------------------------------

    112. The Commission has accepted several interconnection queue 
reform proposals that have increased the initial $10,000 deposit in 
lieu of site control. For example, Nevada Power increased the initial 
deposit amount to $50,000 \185\ and Arizona Public Service Company and 
El Paso Electric increased the amount of the initial deposit in lieu of 
site control to match their increased study deposits--$160,000 for 
interconnection requests less than 75 MW, and $250,000 for 
interconnection requests for 75 MW and greater.\186\ All of these 
transmission providers maintain the pro forma LGIP provision allowing 
the interconnection customer to post $250,000 of non-refundable 
security in lieu of site control at LGIA execution.
---------------------------------------------------------------------------

    \185\ NV Energy, Inc., 142 FERC ] 61,165, at P 25 (2013).
    \186\ Ariz. Pub. Serv. Co., 137 FERC ] 61,099, at P 11 (2011); 
El Paso Elec. Serv. Co., 137 FERC ] 61,101, at P 11 (2011).
---------------------------------------------------------------------------

    113. PacifiCorp allows interconnection customers to submit a 
$10,000 deposit in lieu of site control to begin the cluster study 
process but requires that the interconnection customer demonstrate 
exclusive site control before proceeding to the facilities study.\187\ 
Duke and Dominion adopted a similar approach of requiring that the 
interconnection customer demonstrate exclusive site control before 
proceeding to the facilities study but increased the deposit amount to 
$20,000 plus $500 per MW.\188\ These transmission providers have 
removed the option to post $250,000 of non-refundable security in lieu 
of site control at LGIA execution and instead require proof of site 
control without exception.
---------------------------------------------------------------------------

    \187\ PacifiCorp, Transmission OATT and Service Agreements, 
attach. W, section 5 (3.0.0), section 5.2.
    \188\ Duke, Tariffs, Rate Schedules and Service Agreements, 
OATT, attach. J (18.0.0), section 4.4.2; Dominion, OATT and Service 
Agreements, attach. M (4.5.0), section 4.4.2.
---------------------------------------------------------------------------

    114. PNM,\189\ PSCo,\190\ and MISO have eliminated the deposit in 
lieu of site control. However, MISO allows a deposit in lieu of site 
control of $10,000 per MW where regulatory limitations prohibit the 
procurement of site control.\191\ This deposit is subject to a floor of 
$500,000 and a ceiling of $2,000,000. The cash in lieu deposit is only 
available to customers at the start of the study process: 
interconnection customers must demonstrate 100% site control prior to 
MISO conducting the facilities study.\192\ To cut down on multiple 
speculative projects leasing the same site in order to remain in the 
queue, MISO also requires that interconnection customers demonstrate an 
``exclusive right to develop the site'' of a generating facility or, 
where facilities are to be co-located, a right that is ``sufficient to 
accommodate the final design of the facility and account for any other 
projects that will utilize all or part of the same site.'' \193\
---------------------------------------------------------------------------

    \189\ PNM, 136 FERC ] 61,231 at P 81.
    \190\ PSCo, 169 FERC ] 61,182 at P 58. Site control requirements 
for PSCo are as follows: (1) before entering Phase 1, demonstration 
of 50% site control and 0% site control of interconnection 
customer's interconnection facilities is required; (2) before 
entering Phase 2, demonstration of 50% site control and 0% site 
control of interconnection customer's interconnection facilities is 
required; (3) before entering Phase 1, demonstration of 60% site 
control and 0% site control of interconnection customer's 
interconnection facilities is required; (4) before entering Phase 4, 
demonstration of 75% site control and 0% site control of 
interconnection customer's interconnection facilities is required; 
(5) before executing an LGIA, demonstration of 90% site control and 
50% site control of interconnection customer's interconnection 
facilities is required. PSCo, Transmission and Service Agreements 
Tariff, Xcel Energy Operating Cos. Joint OATT, attach. N (0.8.0), 
section 7.7.6.
    \191\ In order to demonstrate regulatory limitations to securing 
site control, MISO requires the interconnection customer to submit: 
(1) a signed affidavit from an officer of the company indicating 
that site control is unobtainable due to regulatory requirements; 
and (2) documentation sufficiently describing and explaining the 
source and effects of such regulatory restrictions, including a 
description of any conditions that must be met in order to satisfy 
the regulatory restrictions and the anticipated time by which the 
interconnection customer expects to satisfy the regulatory 
restrictions. MISO, FERC Electric Tariff, MISO OATT, attach. X 
(155.0.0), section 7.2.1.2.
    \192\ Midcontinent Indep. Sys. Operator, Inc., 169 FERC ] 
61,173, at P 27 (2019).
    \193\ Id. P 48; see also Midcontinent Indep. Sys. Operator, 
Inc., 166 FERC ] 61,187 (2019).
---------------------------------------------------------------------------

(b) Proposal
    115. We believe that more stringent site control requirements will 
help prevent interconnection customers from submitting interconnection 
requests for speculative, non-commercially viable proposed generating 
facilities.\194\ We preliminarily find that an interconnection customer 
securing the exclusive land right necessary to construct its proposed 
generating facility (or for co-located resources, demonstration of 
shared land use) is sufficient evidence of the interconnection 
customer's commitment to construct the generating facility.
---------------------------------------------------------------------------

    \194\ See, e.g., PNM, 136 FERC ] 61,231 at P 81 (accepting PNM's 
increased deposit requirement and revised site control); PSCo, 169 
FERC ] 61,182 at P 58 (stating that removing the $10,000 deposit 
option ``provides interconnection customers with the flexibility to 
demonstrate their viability while also balancing the goal of 
ensuring viable projects continue through the queue'').
---------------------------------------------------------------------------

    116. We propose to revise the pro forma LGIP to require 
interconnection customers to demonstrate 100% site control for their 
proposed generating facilities when they submit their interconnection 
request. We propose to have transmission providers include in their 
tariff specific acreage requirements for each generating facility 
technology type.
    117. To cut down on multiple interconnection customers leasing the 
same site in order to remain in the queue, we propose to revise the pro 
forma LGIP to require interconnection customers to demonstrate the 
exclusive land right (where the land rights are exclusive to the 
interconnection customer, not necessarily the individual project) to 
develop, construct, operate, and maintain its generating facility or, 
where facilities are co-located, to demonstrate a shared land use right 
to develop, construct, operate, and maintain co-located facilities.
    118. We propose to include a limited option for interconnection 
customers to submit a deposit in lieu of site control

[[Page 39955]]

when they submit their interconnection request only when regulatory 
limitations prohibit the interconnection customer from obtaining site 
control.\195\ In such instances, the interconnection customer would 
submit an initial deposit in lieu of site control of $10,000 per MW, 
subject to a floor of $500,000 and a ceiling of $2,000,000, which would 
be applied toward any interconnection studies or withdrawal penalty, if 
applicable. Such an interconnection customer must demonstrate 100% site 
control prior to the facilities study.
---------------------------------------------------------------------------

    \195\ For example, in MISO, the Commission found that 100% site 
control for the interconnection customer's interconnection 
facilities, the transmission owner's interconnection facilities, and 
network upgrades at the point of interconnection is impractical 
because those facilities often are subject to additional state 
siting and permitting requirements that do not apply to generating 
facilities. Midcontinent Indep. Sys. Operator, Inc., 169 FERC ] 
61,173 at P 40.
---------------------------------------------------------------------------

    119. In compliance with any final rule in this proceeding, we also 
propose that, after notifying the transmission provider of a change to 
the interconnection customer's site control demonstration, the 
transmission provider give the interconnection customer 10 business 
days to demonstrate satisfaction with the applicable requirement after 
notification. We propose to implement these requirements through 
revisions to sections 3.4.1 and 11.3 of the pro forma LGIP, as set 
forth in Appendix B to this NOPR.
    120. We believe that strengthening the site control requirements of 
the pro forma LGIP to include a demonstration of 100% site control 
would help prevent speculative interconnection requests. We recognize 
that requiring site control effectively bars entry into the queue until 
land is acquired, and that this may prevent early-stage projects from 
entering the queue. We nevertheless believe this proposed reform to be 
just and reasonable because it will address the concerns with 
interconnection queue backlogs and study delays explained in the Need 
for Reform by reducing the number of interconnection requests being 
submitted and ensure that interconnection customers in the queue are 
ready to proceed.
    121. We seek comment on whether there are other specific situations 
in which the Commission should accept a deposit in lieu of site 
control.
    122. We seek comment on whether the definition of ``site control,'' 
including the requirement to obtain an exclusive land right (or, for 
co-located resources, a shared land right), should be broadened or 
refined to account for circumstances that may arise in, for example, 
the siting and permitting of offshore resources in bodies of water and/
or submerged land. Further, for circumstances where interconnection 
customers are proposing to develop generating facilities on sites owned 
or physically controlled by a state governmental entity and/or federal 
governmental entity, there may be a need to craft a different site 
control requirement that acknowledges that the interconnection 
customer, that has to comply with regulatory requirements, may not be 
able to demonstrate site control as proposed in this NOPR until later. 
For this reason, we seek comment on whether and how the definition of 
``site control'' should be adjusted for interconnection customers 
(including both onshore and offshore) to account for any regulatory 
requirements they may have associated with proposed generating 
facilities developed on sites owned or physically controlled by a state 
governmental entity and/or a federal governmental entity. We also seek 
comment on the appropriate stage in developing such sites when the 
Commission should view completion of such stage as indicative of an 
interconnection customer's request being non-speculative and whether 
there are substantive differences among interconnection customers 
(including both onshore and offshore) developing sites owned or 
physically controlled by a state governmental entity and/or a federal 
governmental entity.
    123. We also seek comment on whether the Commission should allow 
transmission providers to accept demonstrations of less than 100% site 
control in the initial phases of the interconnection study process, 
outside of when regulatory limitations prohibit the interconnection 
customer from obtaining site control. Additionally, we seek comment on 
whether the Commission should instead adopt site control provisions 
that allow a deposit in lieu of site control to enter the generator 
interconnection process and be evaluated under the first-ready, first-
served cluster study process described above but require 
interconnection customers to demonstrate site control to enter the 
facilities study.
iii. Commercial Readiness
(a) Background
    124. Generally, at least in bilateral markets, an interconnection 
customer does not proceed to construct a generating facility unless it 
has executed some form of off-take agreement, such as a contract for 
the sale of electric energy or capacity from the generating facility. 
Transmission providers often use the terms ``ready'' or ``commercially 
viable'' to describe projects that have demonstrated commercial 
progress by executing such an agreement.\196\ Aside from a 
demonstration of site control or the $10,000 deposit in lieu of site 
control, the pro forma LGIP does not require interconnection customers 
to demonstrate progress towards achieving commercial readiness 
throughout the interconnection study process. Rather, section 11.3 of 
the pro forma LGIP only requires demonstrations of commercial progress 
within 15 days after receipt of the final LGIA, after the transmission 
provider has completed its studies of the interconnection request. If 
interconnection customers cannot meet this deadline, the pro forma LGIA 
allows them to suspend their LGIAs for up to three years: that 
suspension may include a decision by the interconnection customer to 
pause work on their proposed generating facilities and network 
upgrades.\197\ Under this approach, interconnection customers are able 
to submit interconnection requests and progress through the 
interconnection queue for only $160,000 in study deposits, subject to 
true-up based on actual study costs and then suspend their LGIAs for an 
additional three year time period for no cost.\198\ In Order 2003, the 
Commission allowed suspension for a three year time period to allow 
generation projects the flexibility necessary to accommodate permitting 
and other delays that are particularly likely to affect large 
projects.\199\
---------------------------------------------------------------------------

    \196\ See, e.g., PSCo, Transmission and Service Agreements 
Tariff, Xcel Energy Operating Cos. Joint OATT, attach. N, (0.8.0) 
Sec.  7.7.6; PacifiCorp, Transmission OATT and Service Agreements, 
OATT, pt. IV.38 (6.0.0), section 38.4.1.
    \197\ Pro forma LGIA art. 5.16.
    \198\ See pro forma LGIP sections 3.4.1, 6.1, 7.2, 8.1 
(providing for: $10,000 for the Interconnection Feasibility Study, 
$50,000 for the Interconnection System Impact Study, and $100,000 
for the Interconnection Facilities Study).
    \199\ Order No. 2003, 104 FERC ] 61,103 at P 410.
---------------------------------------------------------------------------

    125. PSCo, PacifiCorp, Tri-State, Dominion, and Duke have 
implemented frameworks that require interconnection customers to 
demonstrate commercial readiness early in the generator interconnection 
process to incentivize developers to submit ready or near-ready 
proposed generating facilities into the interconnection queue and to 
discourage the inclusion of speculative interconnection requests in the 
interconnection queue. These transmission providers offer several 
options to demonstrate commercial readiness. Notably, the commercial 
readiness requirements become more stringent as the interconnection 
customer proceeds to the later phases of the interconnection study 
process:

[[Page 39956]]

    <bullet> Executed term sheet in early phases, or executed contract 
or power purchase agreement in later phases;
    <bullet> Reasonable evidence of being selected in a resource plan 
or offered into a resource solicitation plan in early phases, or proof 
of applying for certificate of public convenience and necessity, if 
required, in later phases; or
    <bullet> Provisional LGIA filed executed or unexecuted at the 
Commission in early phases or accepted at the Commission in later 
phases.\200\
---------------------------------------------------------------------------

    \200\ PSCo, Transmission and Service Agreements Tariff, Xcel 
Energy Operating Cos. Joint OATT, attach. N (0.8.0), section 7.7; 
PacifiCorp, Transmission OATT and Service Agreementts, OATT, pt. 
IV.38 (6.0.0), section 38.4.1; Tri-State, Tri-State OATT, attach. N 
(7.0.0), section 7.7; Dominion, OATT and Service Agreements, attach. 
M (4.5.0), section 10.1; Duke, Tariffs, Rate Schedules and Service 
Agreements, OATT, attach. J (18.0.0), section 10.11 .
---------------------------------------------------------------------------

    126. As an alternative, PSCo, PacifiCorp, Tri-State, Dominion, and 
Duke allow interconnection customers that cannot provide these non-
financial forms of readiness to instead provide additional deposit 
funds to proceed through the interconnection study process. Because 
PacifiCorp's cluster study process has fewer phases than PSCo, Tri-
State, Dominion, and Duke, PacifiCorp offers the option to submit a 
deposit in lieu of readiness of $3,000/MW at the interconnection 
request phase, and for the later phase, a deposit equal to the network 
upgrade costs allocated to the interconnection customer in the most 
recent cluster study.\201\ To contrast, in PSCo, Tri-State, Dominion, 
and Duke, an interconnection customer that cannot provide a readiness 
demonstration must provide additional deposits equal to:
---------------------------------------------------------------------------

    \201\ PacifiCorp, Transmission OATT and Service Agreements, 
OATT, pt. IV.38 (6.0.0), section 38.4.1(v).
---------------------------------------------------------------------------

    <bullet> Two times the study deposit amount to enter the phase 1 
cluster study;
    <bullet> Three times the study deposit amount after the phase 1 
report meeting to enter the phase 2 cluster study;
    <bullet> Five times the study deposit amount after the phase 2 
report meeting; and
    <bullet> Seven times the study deposit amount after receipt of the 
facilities study agreement.\202\
---------------------------------------------------------------------------

    \202\ PSCo, Transmission and Service Agreements Tariff, Xcel 
Energy Operating Cos. Joint OATT, attach. N (0.8.0), section 7.7.5; 
Tri-State, Tri-State OATT, attach. N (7.0.0), section 7.7.5; 
Dominion, OATT and Service Agreements, attach. M (4.5.0), section 
10.1.6; Duke, Tariffs, Rate Schedules and Service Agreements, OATT, 
attach. J (18.0.0), section 10.11.6.
---------------------------------------------------------------------------

    127. As explained earlier, we are concerned with the significant 
interconnection queue backlogs and study delays, which we believe are 
caused in part by the minimal requirements for submitting 
interconnection requests and the tendency for non-viable projects to 
linger in interconnection queues. We have learned through 
interconnection queue reform filings that interconnection customers 
typically do not actually construct generating facilities unless they 
have entered into an off-take agreement for the output of such 
facilities, at least in bilateral market areas.\203\ On the other hand, 
interconnection customers that do not enter into such agreements 
frequently withdraw from the interconnection queue, sometimes late in 
the study process or even after the conclusion of the study process, 
triggering the types of delays and re-studies for commercially viable 
projects that raise concerns for us. Thus, we believe that the existing 
pro forma LGIP requirements may be insufficient because they do not 
require customers to demonstrate commercial readiness early enough in 
the study process to deter interconnection customers from submitting 
interconnection requests for, and continuing in the interconnection 
queue, speculative proposed generating facilities.
---------------------------------------------------------------------------

    \203\ PNM, Transmittal Letter, Docket No. ER11-3522-000, at 10-
12 (filed May 5, 2011); PacifiCorp, Transmittal Letter, Docket No. 
ER20-924-000, at 51 (filed Jan. 31, 2020).
---------------------------------------------------------------------------

(b) Proposal
    128. We propose to revise the pro forma LGIP to include a 
commercial readiness framework. One major benefit of the frameworks 
adopted by PSCo, PacifiCorp, Tri-State, Dominion, and Duke is that the 
financial requirement in lieu of readiness increases throughout the 
study process, which encourages interconnection customers that are not 
ready to proceed to withdraw from the interconnection queue earlier in 
the study process while also providing them the flexibility to enter 
and remain in the interconnection queue without an off-take agreement. 
We believe that such a mechanism would reduce the number of times an 
interconnection customer executes and suspends an LGIA for a 
speculative interconnection request, only to later withdraw the 
request, which impacts the remaining interconnection customers in the 
interconnection queue by causing re-studies and shifting network 
upgrade costs to lower-queued interconnection customers. This proposed 
reform should also reduce the strain on transmission providers and 
enable viable interconnection requests to progress more quickly through 
a less congested interconnection queue, thereby remedying the unjust 
and unreasonable Commission-jurisdictional rates discussed in our need 
for reform.
    129. Therefore, we propose to establish the defined terms 
``Commercial Readiness Demonstration'' \204\ and ``Commercial Readiness 
Deposit'' \205\ in the pro forma LGIP. We also propose to add to 
sections 3.4.2, 7.5 and 8.1 of the pro forma LGIP the following options 
as acceptable commercial readiness demonstration options to enter into 
the cluster study and cluster re-study:
---------------------------------------------------------------------------

    \204\ We propose to revise section 1 of the pro forma LGIP to 
provide that Commercial Readiness Demonstration shall have the 
meaning set forth in Sections 3.4.2, 7.5, and 8.1 of this LGIP.
    \205\ We propose to revise section 1 of the pro forma LGIP to 
provide that Commercial Readiness Deposit shall mean a deposit paid 
in lieu of submitting a Commercial Readiness Demonstration, as set 
forth in Sections 3.4.2, 7.5, and 8.1 of this LGIP.
---------------------------------------------------------------------------

    <bullet> Executed term sheet (or comparable evidence) related to a 
contract, binding upon the parties to the contract, for sale of (1) the 
constructed generating facility, (2) the generating facility's energy 
or capacity, or (3) the generating facility's ancillary services; where 
the term of sale is not less than five years.
    <bullet> Reasonable evidence that the project has been selected in 
a resource plan or resource solicitation process by or for a load 
serving entity, is being developed by a load-serving entity (LSE), or 
is being developed for purposes of a sale to a commercial, industrial, 
or other large end-use customer.
    <bullet> Provisional LGIA which has been filed at the Commission 
(executed or unexecuted), which is not suspended and includes a 
commitment to construct the generating facility.
    130. We propose to add to section 8.1 of the pro forma LGIP that 
the following may serve as commercial readiness demonstration options 
to enter the facilities study, and must be provided with the executed 
facilit

[…truncated; see source link]
Indexed from Federal Register on July 5, 2022.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.