Clean Air Act Operating Permit Program; Petition for Objection to State Operating Permit for UOP Mobile Plant (Mobile County, Alabama)
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The Environmental Protection Agency (EPA) Administrator signed an Order, dated April 27, 2022, granting in part and denying in part the petition submitted by Greater-Birmingham Alliance to Stop Pollution (Petitioner) objecting to a proposed Clean Air Act (CAA) title V operating permit issued to UOP LLC for its Mobile Plant located in Mobile County, Alabama. The Order responds to an April 2, 2021, petition requesting that EPA object to the final operating permit No. 503-8010. This permitting action was issued by the Alabama Department of Environmental Management (ADEM). The Order constitutes a final action on the petition addressed therein.
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 102 (Thursday, May 26, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 102 (Thursday, May 26, 2022)]
[Notices]
[Pages 32015-32016]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-11292]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[Petition IV-2021-6; FRL-9888-01-R4]
Clean Air Act Operating Permit Program; Petition for Objection to
State Operating Permit for UOP Mobile Plant (Mobile County, Alabama)
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of final order on petition to object to state operating
permit.
-----------------------------------------------------------------------
SUMMARY: The Environmental Protection Agency (EPA) Administrator signed
an Order, dated April 27, 2022, granting in part and denying in part
the petition
[[Page 32016]]
submitted by Greater-Birmingham Alliance to Stop Pollution (Petitioner)
objecting to a proposed Clean Air Act (CAA) title V operating permit
issued to UOP LLC for its Mobile Plant located in Mobile County,
Alabama. The Order responds to an April 2, 2021, petition requesting
that EPA object to the final operating permit No. 503-8010. This
permitting action was issued by the Alabama Department of Environmental
Management (ADEM). The Order constitutes a final action on the petition
addressed therein.
ADDRESSES: Copies of the Order, the petition, and all pertinent
information relating thereto are on file at the following location: EPA
Region 4; Air and Radiation Division; 61 Forsyth Street SW, Atlanta,
Georgia 30303-8960. The Order is also available electronically at the
following address: <a href="https://www.epa.gov/system/files/documents/2022-05/UOP%20Order_4-27-22.pdf">https://www.epa.gov/system/files/documents/2022-05/UOP%20Order_4-27-22.pdf</a>.
FOR FURTHER INFORMATION CONTACT: Art Hofmeister, Air Permits Section,
Air Planning Implementation Branch, Air and Radiation Division, U.S.
Environmental Protection Agency, Region 4, 61 Forsyth Street SW,
Atlanta, Georgia 30303-8960. The telephone number is (404) 562-9115.
Mr. Hofmeister can also be reached via electronic mail at
<a href="/cdn-cgi/l/email-protection#d0b8bfb6bdb5b9a3a4b5a2feb1a2a490b5a0b1feb7bfa6"><span class="__cf_email__" data-cfemail="e981868f848c809a9d8c9bc7889b9da98c9988c78e869f">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION: The CAA affords EPA a 45-day period to
review and, as appropriate, the authority to object to operating
permits proposed by state permitting authorities under title V of the
CAA, 42 U.S.C. 7661-7661f. Section 505(b)(2) of the CAA and 40 CFR
70.8(d) authorize any person to petition the EPA Administrator to
object to a title V operating permit within 60 days after the
expiration of EPA's 45-day review period if the EPA has not objected on
its own initiative. Petitions must be based only on objections to the
permit that were raised with reasonable specificity during the public
comment period provided by the state, unless the petitioner
demonstrates that it was impracticable to raise these issues during the
comment period or the grounds for the issues arose after this period.
Pursuant to sections 307(b) and 505(b)(2) of the CAA, a petition for
judicial review of those parts of the Order that deny issues in the
petition may be filed in the United States Court of Appeals for the
appropriate circuit within 60 days from the date this notice is
published in the Federal Register.
Petitioner submitted a petition requesting that EPA object to the
proposed CAA title V operating permit no. 503-8010 issued by ADEM to
the UOP Mobile Plant. Petitioner claims: The statement of basis lacks
substantive information for adequate public review; ADEM failed to
demonstrate that monitoring requirements are consistent with respect to
applicable requirements; ADEM failed to demonstrate the source is
entitled to a permit shield; the permit fails to include underlying
citations of authority with respect to applicable permit conditions;
the permit includes synthetic minor limits that are not practically
enforceable; and ADEM failed to adequately respond to Petitioner's
comments.
On April 27, 2022, the Administrator issued an Order granting in
part and denying in part the petition. The Order explains EPA's bases
for granting in part and denying in part the petition.
Dated: May 20, 2022.
Daniel Blackman,
Regional Administrator, Region 4.
[FR Doc. 2022-11292 Filed 5-25-22; 8:45 am]
BILLING CODE 6560-50-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.