Notice of Competitive Offer and Notice of Segregation for Solar Energy Development on Public Land, Clark County, Nevada
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
The Bureau of Land Management (BLM), Las Vegas Field Office is announcing that it will accept competitive bids to determine a preferred right-of-way applicant for solar energy development on a 1,635-acre parcel of public land, referred to as the Dry Lake East Designated Leasing Area, located in Clark County, Nevada. The BLM also announces the segregation of the 1,635-acre parcel of public lands from appropriation under the public land laws, including the Mining Law, but not the Mineral Leasing or Material Sales Acts, for a period of 2 years from the date of publication of this notice, subject to valid existing rights. This segregation will facilitate the orderly administration of the public lands while the BLM considers potential solar development on the described parcel.
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 65 (Tuesday, April 5, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 65 (Tuesday, April 5, 2022)]
[Notices]
[Pages 19699-19700]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-07078]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[LLNVS00000. L13400000.KH0000; MO# 4500160406]
Notice of Competitive Offer and Notice of Segregation for Solar
Energy Development on Public Land, Clark County, Nevada
AGENCY: Bureau of Land Management, Interior.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: The Bureau of Land Management (BLM), Las Vegas Field Office is
announcing that it will accept competitive bids to determine a
preferred right-of-way applicant for solar energy development on a
1,635-acre parcel of public land, referred to as the Dry Lake East
Designated Leasing Area, located in Clark County, Nevada. The BLM also
announces the segregation of the 1,635-acre parcel of public lands from
appropriation under the public land laws, including the Mining Law, but
not the Mineral Leasing or Material Sales Acts, for a period of 2 years
from the date of publication of this notice, subject to valid existing
rights. This segregation will facilitate the orderly administration of
the public lands while the BLM considers potential solar development on
the described parcel.
DATES: The competitive offer will be held at 1:00 p.m. Pacific Time
(PT) on May 20, 2022. All sealed bids must be received by the Las Vegas
Field Office at the address listed in the ADDRESSES section by 10:00
a.m. PT on May 20, 2022. The segregation for the lands identified in
this notice is effective on April 5, 2022.
ADDRESSES: Sealed bids may be mailed or hand delivered to the Bureau of
Land Management, Attention: Energy and Infrastructure Team, 4701 North
Torrey Pines Drive, Las Vegas, NV 89130. Electronic bid submissions
will not be accepted.
FOR FURTHER INFORMATION CONTACT: Beth Ransel, Supervisory Project
Manager, at (702) 515-5000 or <a href="/cdn-cgi/l/email-protection#a8eae4e5f7e6fef7fbe6ecf7edc6cddacfd1f8dac7c2cdcbdcdbe8cac4c586cfc7de"><span class="__cf_email__" data-cfemail="fcbeb0b1a3b2aaa3afb2b8a3b992998e9b85ac8e9396999f888fbc9e9091d29b938a">[email protected]</span></a>.
Individuals in the United States who are deaf, deafblind, hard of
hearing, or have a speech disability may dial 711 (TTY, TDD, or
TeleBraille) to access telecommunications relay services. Individuals
outside the United States should use the relay services offered within
their country to make international calls to the point-of-contact in
the United States.
SUPPLEMENTARY INFORMATION: Competitive Offering Information: The BLM
Las Vegas Field Office is conducting a competitive process to determine
a preferred right-of-way applicant to submit a right-of-way
application, plan of development, and application fee for a parcel of
land described as the Dry Lake East Designated Leasing Area. As
provided for in 43 CFR 2804.30(b), a sealed bid competitive bidding
procedure will be used to determine a preferred right-of-way applicant
for the Dry Lake East Designated Leasing Area.
Bidders may submit sealed bids for the parcel, consisting of
approximately 1,635 acres of public lands legally described in this
Notice. The BLM has determined the minimum bid for the parcel to be
$37,780. The minimum bid represents 10 percent of the acreage rent
($33,823); the acreage rent is calculated by multiplying the number of
acres being offered times the annual per acre zone rate from the solar
energy acreage rent schedule (43 CFR 2806.52(a)). In addition, the
minimum bid includes an administrative fee of $3,957 (approximately
$2.42 per acre) to cover the BLM's costs of preparing for and
conducting the competitive offer. In addition to the minimum bid,
bidders may also offer a bonus bid of any dollar amount.
To submit a bid, you must provide the bidder's name and personal or
business address. Each bid can only contain the name of one bidder
(i.e., citizen, association or partnership, corporation, or
municipality). For your bid to receive consideration, you must submit a
complete bid package, including a Technical and Financial Capability
Certification, Sealed Bid Statement, payment for the minimum bid and at
least 20 percent of the bonus bid. All bidding documents must be
enclosed in a sealed envelope with the bidder's name and return address
on the outside. Include the following notation on the front lower left-
hand corner of the sealed envelope: ``SEALED BID--DO NOT OPEN.'' The
Technical and Financial Capability Certification form, Sealed Bid
Statement form, and a complete description of the bid process are
contained in an Invitation for Bids package available at the following
location: <a href="https://eplanning.blm.gov/eplanning-ui/project/86813">https://eplanning.blm.gov/eplanning-ui/project/86813</a>.
The successful bidder will be determined by highest total bid. All
bidders will be notified within 10 calendar days after the bidding
closes of whether they were the successful bidder.
If you are the successful bidder, within 15 calendar days after
notification you must submit the balance of the bonus bid to the BLM
Las
[[Page 19700]]
Vegas Field Office. If you are the successful bidder, the BLM will
select you as the preferred right-of-way applicant only if you: (1)
Satisfy the qualifications in 43 CFR 2803.10; (2) make the required
payments listed above; and (3) do not have any trespass action pending
against you for any activity on BLM-administered lands or have any
unpaid debts owed to the Federal Government. If the listed requirements
are not satisfied within the 15-day time period, the BLM will not
select the identified successful bidder as the preferred right-of-way
applicant and will keep all money that has been submitted. In that
event, the BLM may identify the next highest bidder as the successful
bidder (then follow requirements as noted above for successful bidder)
or re-offer the lands through another competitive process.
The administrative fee portion of the minimum bid will be retained
by the agency to recover administrative costs for conducting the
competitive bid and related processes. The remainder of the minimum bid
and bonus bid will be deposited with the U.S. Treasury. Neither amount
will be returned or refunded to the successful bidder(s) under any
circumstance. If you are not the successful bidder, the BLM will return
or refund the bid amount submitted with your bid.
Any required payments submitted must be made by a certified check,
postal money order, bank draft, or cashier's check made payable in U.S.
dollars to ``Department of the Interior--Bureau of Land Management''.
If there is no bid received for the parcel, then no preferred
right-of-way applicant will be identified and no application will be
processed for solar energy development under the procedures listed in
this notice. In the case of tied bids, the BLM may re-offer the lands
competitively to the tied bidders or to all prospective bidders.
Within 30 days of notification of the auction result, the
successful bidder must submit a right-of-way application that conforms
with all application requirements found at 43 CFR 2804.12. Within 60
days of notification of the auction result, the successful bidder must
submit a plan of development that conforms with the BLM's Solar Energy
Development Plan of Development template. The preferred right-of-way
applicant will be required to reimburse the United States for the cost
of processing an application consistent with the requirements of the
regulations at 43 CFR 2804.14. The cost recovery fees are based on the
amount of time the BLM estimates it will take to process the right-of-
way application and issue a decision. The BLM will begin processing the
right-of-way application once the cost recovery fees are received as
required by the regulations. Processing of the right-of-way application
will be done in accordance with applicable law, regulation, and policy.
Additional fees may be required as part of approval of a right-of-way
grant, including mitigation-related fees.
Only interests in issued right-of-way grants are assignable under
the existing regulations at 43 CFR 2807.21. The interest acquired by
the successful high bidder or preferred right-of-way applicant from
this auction may not be assigned or sold to another party prior to the
issuance of a right-of-way grant. The successful bidder may, however,
continue to pursue their application if the successful bidder becomes a
wholly-owned subsidiary of a new third party.
Segregation: Regulations found at 43 CFR 2091.3-1(e) and 2804.25(f)
allow the BLM to segregate public lands for potential rights-of-way
when initiating a competitive process for solar energy development from
the operation of the public land laws, including the Mining Law, by
publication of a Federal Register notice. The BLM uses this authority
to preserve its ability to approve, approve with modifications, or deny
proposed rights-of-way, and to facilitate the orderly administration of
the public lands. This segregation is subject to valid existing rights,
including existing mining claims located before this segregation
notice. Licenses, permits, cooperative agreements, or discretionary
land use authorizations of a temporary nature which would not impact
lands identified in this notice may be allowed with the approval of a
BLM authorized officer during the segregation period. As provided in
the regulations, the segregation of lands in this notice will not
exceed 2 years from the date of publication unless extended for an
additional 2 years through publication of a new notice in the Federal
Register. The segregation period will terminate and the land will
automatically reopen to appropriation under the public land laws,
including the mining law at the earliest of the following dates: Upon
issuance of a decision by the authorized officer granting, granting
with modifications, or denying the application for a right-of-way;
without further administrative action at the end of the segregation
provided for in the Federal Register notice initiating the segregation;
or upon publication of a Federal Register notice terminating the
segregation. Upon termination of the segregation of these lands, all
lands subject to this segregation would automatically reopen to
appropriation under the public land laws, including the mining law.
Legal Description for Parcel: The subject parcel is legally
described as follows--
Mount Diablo Meridian, Nevada
T. 17 S., R. 64 E.,
Sec. 32, those portions of the S\1/2\NE\1/4\ lying westerly of
the westerly right-of-way of CC-0360, those portions of the SE\1/
4\NW\1/4\ lying southeasterly of the southeasterly right-of-way
boundary of NEV-045565, and those portions of the S\1/2\ lying
southeasterly of the southeasterly right-of-way boundary of NEV-
045565 and westerly of the westerly right-of-way boundary of CC-
0360.
T. 18 S., R. 64 E.,
Sec. 5, those portions lying westerly of the westerly right-of-
way boundary of CC-0360;
Sec. 6, that portion of lot 8 lying southeasterly of the
southeasterly right-of-way boundary of NEV-045565, that portion of
the SE\1/4\NE\1/4\ lying southeasterly of the southeasterly right-
of-way boundary of NEV-045565, and S\1/2\SE\1/4\SE\1/4\;
Sec. 7, lots 12, 18, 19, 20, and 29, NE\1/4\NE\1/4\, S\1/2\NE\1/
4\, N\1/2\SE\1/4\SW\1/4\, N\1/2\SE\1/4\, N\1/2\SW\1/4\SE\1/4\, and
N\1/2\SE\1/4\SE\1/4\;
Sec. 8, those portions of the N\1/2\ and NW\1/4\SW\1/4\ lying
northerly and northwesterly of the northerly and northwesterly
right-of-way boundary of CC-0360.
The area described contains 1,635 acres, more or less, according
to the BLM National Public Land Survey System CadNSDI and the
official plats of the surveys of the said land, on file with the
BLM.
Shonna Dooman,
Field Manager--Las Vegas Field Office.
[FR Doc. 2022-07078 Filed 4-4-22; 8:45 am]