Notice2022-05311
Appalachian Power Company; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
March 14, 2022
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 87 Issue 49 (Monday, March 14, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 49 (Monday, March 14, 2022)]
[Notices]
[Pages 14259-14260]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-05311]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2514-209]
Appalachian Power Company; Notice of Application Tendered for
Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2514-209.
c. Date Filed: February 28, 2022.
d. Applicant: Appalachian Power Company (Appalachian).
e. Name of Project: Byllesby-Buck Hydroelectric Project (Byllesby-
Buck Project).
f. Location: The two-development Byllesby-Buck Project is located
on the New River in Carroll County, Virginia. The project occupies 7.23
acres of federal land managed by the U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Elizabeth Parcell, Process Supervisor,
American Electric Power Service Corporation, 40 Franklin Road SW,
Roanoke, VA 24011; Phone at (540) 985-2441 or email at
<a href="/cdn-cgi/l/email-protection#96f3f4e6f7e4f5f3fafad6f7f3e6b8f5f9fb"><span class="__cf_email__" data-cfemail="56333426372435333a3a163733267835393b">[email protected]</span></a>.
i. FERC Contact: Jody Callihan at (202) 502-8278, or
<a href="/cdn-cgi/l/email-protection#7812171c01561b19141411101916381e1d0a1b561f170e"><span class="__cf_email__" data-cfemail="670d08031e4904060b0b0e0f0609270102150449000811">[email protected]</span></a>.
j. This application is not ready for environmental analysis at this
time.
k. The Byllesby-Buck Project consists of two developments (Byllesby
and Buck); the Byllesby Development is located 3 river miles upstream
of the Buck Development. The current license authorizes a combined
generating capacity of 30.1 megawatts (MW); however, the actual
installed capacity is 26.1 MW, which Appalachian proposes to increase
to 29.8 MW, as described below.
Between 2016 and 2020, the project had an average annual generation
of 92,820 megawatt-hours (MWh).
The Byllesby Development consists of: (1) A 64-foot-high, 528-foot-
long concrete dam, sluice gate, and main spillway section topped with
four sections of 9-foot-high flashboards, five sections of 9-foot-high
inflatable Obermeyer crest gates, and six bays of 10-foot-high Tainter
gates; (2) an auxiliary spillway including six sections of 9-foot-high
flashboards; (3) a 239-acre impoundment with a gross storage capacity
of 2,000 acre-feet; (4) a powerhouse containing four turbine-generator
units with a total installed capacity of 18.0 MW; (5) a control house
and switchyard; and (6) appurtenant facilities.
The Buck Development consists of: (1) A 42-foot-high, 353-foot-long
concrete dam and sluice gate; (2) a 1,005-foot-long, 19-foot-high
spillway section topped with twenty sections of 9-foot-high
flashboards, four sections of 9-foot-high inflatable crest gates, and
six bays of 10-foot-high Tainter gates; (3) a 66-acre impoundment with
a gross storage capacity of 661 acre-feet; (4) a powerhouse containing
three turbine-generator units with a total installed capacity of 8.1
MW; (5) two 2-mile-long overhead 13.2-kilovolt transmission lines
extending from the Buck powerhouse to the Byllesby control house; and
(6) appurtenant facilities.
The Byllesby-Buck Project is currently operated in a run-of-river
(ROR) mode, with the Byllesby impoundment maintained between elevations
of 2,078.2 feet and 2,079.2 feet National Geodetic Vertical Datum of
1929 (NGVD 29) and the Buck impoundment maintained between elevations
of
[[Page 14260]]
2,002.4 feet and 2,003.4 feet NGVD 29. A minimum flow of 360 cubic feet
per second (cfs), or project inflow if less, is provided downstream of
each powerhouse. Article 406 of the current license requires that
following periods of spill when a spillway gate has been opened 2 feet
of more, spill flows (into the Buck bypassed reach) must be released
through a 2-foot gate opening for at least 3 hours, then the gate
opening must be reduced to 1 foot for at least an additional 3 hours
prior to closing the gate.
Appalachian proposes to continue operating the project in a ROR
mode and providing a 360-cfs minimum flow at each development. However,
Appalachian proposes to modify the existing ramping rate requirement at
the Buck Development such that, following periods of spill when a
spillway gate has been opened 2 feet or more, water would be released
(into the Buck bypassed reach) through a 2-foot gate opening for at
least 2 hours, then the gate opening would be reduced to 1 foot for 2
hours, and finally to 0.5 foot for 2 hours before closing the gate. In
addition to this measure, which is intended to minimize walleye
stranding in the Buck bypassed reach, Appalachian proposes
environmental measures for the protection and enhancement of other
aquatic resources as well as terrestrial, recreation, and cultural
resources.
Appalachian also proposes to upgrade three (of the four) turbine-
generator units at the Byllesby Development and two (of the three)
turbine-generator units at the Buck Development. The proposed upgrades
are expected to increase the total installed capacity from 26.1 MW to
29.8 MW and the project's average annual generation by 25,927 MWh. In
addition, Appalachian proposes to add to the current project boundary:
(1) The Byllesby control house and switchyard and (2) two 2-mile-long
overhead 13.2-kilovolt transmission lines that extend from the Buck
powerhouse to the Byllesby control house.
l. A copy of the application can be viewed on the Commission's
website at <a href="http://www.ferc.gov">http://www.ferc.gov</a>, using the ``eLibrary'' link. Enter the
docket number, excluding the last three digits in the docket number
field, to access the document (P-2514). For assistance, contact FERC at
<a href="/cdn-cgi/l/email-protection#04424156474b6a686d6a61577174746b767044626176672a636b72"><span class="__cf_email__" data-cfemail="c3858691808cadafaaada690b6b3b3acb1b783a5a6b1a0eda4acb5">[email protected]</span></a>, or call toll-free, (866) 208-3676 or (202)
502-8659 (TTY).
m. You may also register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
----------------------------------------------------------------------------------------------------------------
Milestone Target date
----------------------------------------------------------------------------------------------------------------
Issue Deficiency Letter (if necessary)..................... March 2022.
Request Additional Information (if necessary).............. May 2022.
Notice of Acceptance/Notice of Ready for Environmental August 2022.
Analysis.
----------------------------------------------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: March 8, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-05311 Filed 3-11-22; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>