Proposed Rule2022-03131

Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
March 3, 2022

Issuing agencies

Nuclear Regulatory Commission

Abstract

The U.S. Nuclear Regulatory Commission (NRC) is proposing to amend its regulations that relate to the decommissioning of production and utilization facilities. The NRC's goals in amending these regulations are to maintain a safe, effective, and efficient decommissioning process; reduce the need for license amendment requests and exemptions from existing regulations; address other decommissioning issues deemed relevant by the NRC; and support the NRC's Principles of Good Regulation, including openness, clarity, and reliability. The NRC will hold a public meeting to promote full understanding of this proposed rule and to facilitate public comments.

Full Text

<html>
<head>
<title>Federal Register, Volume 87 Issue 42 (Thursday, March 3, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 42 (Thursday, March 3, 2022)]
[Proposed Rules]
[Pages 12254-12336]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-03131]



[[Page 12253]]

Vol. 87

Thursday,

No. 42

March 3, 2022

Part III





 Nuclear Regulatory Commission





-----------------------------------------------------------------------





10 CFR Parts 20, 26, 50, et al.





Regulatory Improvements for Production and Utilization Facilities 
Transitioning to Decommissioning; Proposed Rule

Federal Register / Vol. 87 , No. 42 / Thursday, March 3, 2022 / 
Proposed Rules

[[Page 12254]]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

10 CFR Parts 20, 26, 50, 51, 52, 72, 73, 140

[NRC-2015-0070]
RIN 3150-AJ59


Regulatory Improvements for Production and Utilization Facilities 
Transitioning to Decommissioning

AGENCY: Nuclear Regulatory Commission.

ACTION: Proposed rule.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is proposing to 
amend its regulations that relate to the decommissioning of production 
and utilization facilities. The NRC's goals in amending these 
regulations are to maintain a safe, effective, and efficient 
decommissioning process; reduce the need for license amendment requests 
and exemptions from existing regulations; address other decommissioning 
issues deemed relevant by the NRC; and support the NRC's Principles of 
Good Regulation, including openness, clarity, and reliability. The NRC 
will hold a public meeting to promote full understanding of this 
proposed rule and to facilitate public comments.

DATES: Submit comments by May 17, 2022. Comments received after this 
date will be considered if it is practical to do so, but the Commission 
is able to ensure consideration only for comments received before this 
date.

ADDRESSES: You may submit comments by the following method (unless this 
document describes a different method for submitting comments on a 
specific subject); however, the NRC encourages electronic comment 
submission through the Federal rulemaking website:
    <bullet> Federal Rulemaking Website: Go to <a href="https://www.regulations.gov">https://www.regulations.gov</a> and search for Docket ID NRC-2015-0070. Address 
questions about NRC dockets to Dawn Forder; telephone: 301-415-3407; 
email: <a href="/cdn-cgi/l/email-protection#9edaffe9f0b0d8f1ecfafbecdef0ecfdb0f9f1e8"><span class="__cf_email__" data-cfemail="3b7f5a4c55157d54495f5e497b554958155c544d">[email&#160;protected]</span></a>. For technical questions contact the 
individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
    <bullet> Email comments to: <a href="/cdn-cgi/l/email-protection#d587a0b9b0b8b4bebcbbb2fb96bab8b8b0bba1a695bba7b6fbb2baa3"><span class="__cf_email__" data-cfemail="792b0c151c14181210171e573a1614141c170d0a39170b1a571e160f">[email&#160;protected]</span></a>. If you do 
not receive an automatic email reply confirming receipt, then contact 
us at 301-415-1677.
    <bullet> Mail comments to: Secretary, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, ATTN: Rulemakings and 
Adjudications Staff.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Daniel I. Doyle, Office of Nuclear 
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-415-3748; email: 
<a href="/cdn-cgi/l/email-protection#0246636c6b676e2c466d7b6e67426c70612c656d74"><span class="__cf_email__" data-cfemail="6d290c030408014329021401082d031f0e430a021b">[email&#160;protected]</span></a>.

SUPPLEMENTARY INFORMATION: 

Executive Summary

A. Need for the Regulatory Action

    The NRC is proposing to amend its regulations related to the 
decommissioning of production and utilization facilities. The 
Commission directed the NRC staff to proceed with an integrated 
rulemaking on nuclear power reactor decommissioning to address the 
following: A graded approach to emergency preparedness (EP), lessons 
learned from the licensees that have already gone through (or are 
currently going through) the decommissioning process, the advisability 
of requiring a licensee's post-shutdown decommissioning activities 
report (PSDAR) to be approved by the NRC, the appropriateness of 
maintaining the three existing options for decommissioning and the 
timeframes associated with those options, the appropriate role of State 
and local governments and non-governmental stakeholders in the 
decommissioning process, and any other issues deemed relevant by the 
NRC staff.
    Compared to an operating nuclear power reactor, the risk of an 
offsite radiological release is significantly lower, and the types of 
possible accidents are significantly fewer, at a nuclear power reactor 
that has permanently ceased operations and removed fuel from the 
reactor vessel. As a direct result, there is no need for the NRC to 
impose new requirements in the areas identified in this rulemaking to 
address safety or security concerns. Instead, the requirements in 
decommissioning should be aligned with the reduction in risk that 
occurs over time, while maintaining safety and security. The 
decommissioning process can be improved and made more efficient, open, 
and predictable by reducing the reliance on licensing actions (i.e., 
license amendment and exemption requests) that reflect this reduction 
in risk to achieve a sustainable regulatory framework during 
decommissioning.
    The NRC has also determined that changes to the regulations are 
appropriate with respect to drug and alcohol testing; cyber security; 
and foreign ownership, control, or domination of a production or 
utilization facility undergoing decommissioning.
    In several areas, the current regulations do not distinguish 
between provisions that apply to a nuclear power reactor that has 
permanently ceased operations and provisions that apply to an operating 
nuclear power reactor. To address this, the NRC is proposing to amend 
its regulations in several areas to provide a regulatory framework for 
the transition from operating to decommissioning. This proposed rule is 
a four-step graded approach that is commensurate with the reduction in 
radiological risk at four levels of decommissioning: (1) Permanent 
cessation of operations and permanent removal of all fuel from the 
reactor vessel, (2) sufficient decay of fuel in the spent fuel pool 
(SFP) such that it would not reach ignition temperature within 10 hours 
under adiabatic heatup conditions (i.e., a complete loss of SFP water 
inventory with no heat loss), (3) transfer of all fuel to dry storage, 
and (4) removal of all fuel from the site. The graded approach is a 
fundamental concept for this proposed rule.
    Because the current regulatory framework for decommissioning is 
adequate to protect public health and safety and the common defense and 
security, many of the new requirements in this proposed rule are 
alternatives to current requirements.

B. Major Provisions

    Major provisions of this proposed rule include changes in the 
following areas:
    <bullet> Emergency preparedness. This proposed rule offers an 
alternative, graded approach to the current requirements for onsite and 
offsite radiological emergency preparedness at a nuclear power reactor. 
This approach would provide four levels of emergency planning standards 
that coincide with significant milestones in decommissioning that 
reflect the gradual reduction of the radiological risk during 
decommissioning.
    <bullet> Physical security. This proposed rule would make certain 
changes that would apply once a nuclear power reactor enters 
decommissioning. These proposed changes would (1) permit a certified 
fuel handler (CFH) to approve the temporary suspension of security 
measures during certain emergency conditions or during severe weather, 
(2) remove the requirement that a licensee's physical protection 
program be

[[Page 12255]]

designed to prevent significant core damage, (3) remove the requirement 
that a licensee must designate the reactor control room as a ``vital 
area,'' and (4) replace the requirement for maintaining continuous 
communications between the alarm stations and the control room with a 
requirement for maintaining communications between alarm stations and 
the CFH or senior on shift licensee representative, or both. This last 
change would clarify the management role of the CFH in a manner that is 
consistent with Sec.  50.54(y) of title 10 of the Code of Federal 
Regulations (10 CFR). The NRC is also proposing to revise Sec.  
50.54(p) to add definitions for ``change'' and ``decrease in safeguards 
effectiveness,'' as those terms apply to the process for making changes 
to the security plans of licensees under 10 CFR part 50, ``Domestic 
Licensing of Production and Utilization Facilities,'' and 10 CFR part 
52, ``Licenses, Certifications, and Approvals for Nuclear Power 
Plants,'' with operating, decommissioning, or decommissioned reactor 
units. In addition, this proposed rule would provide an option for a 
licensee to protect a general license independent spent fuel storage 
installation (ISFSI) under the physical security requirements in Sec.  
73.51, ``Requirements for the physical protection of stored spent 
nuclear fuel and high-level radioactive waste,'' for a specific license 
ISFSI instead of the physical security requirements in Sec.  73.55, 
``Requirements for physical protection of licensed activities in 
nuclear power reactors against radiological sabotage,'' for a nuclear 
power reactor once all spent fuel has been moved to dry storage.
    <bullet> Cyber security. This proposed rule would provide that the 
cyber security requirements in Sec.  73.54, ``Protection of digital 
computer and communication systems and networks,'' continue to apply to 
a nuclear power reactor after the licensee's permanent cessation of 
operations, until all the fuel has been removed from the reactor vessel 
and there has been sufficient decay of the fuel in the SFP such that it 
would not reach ignition temperature within 10 hours under adiabatic 
heatup conditions, at which point no digital computer and 
communications systems would be required to meet the criteria of Sec.  
73.54. This proposed rule would also provide for the removal of the 
cyber security license condition for 10 CFR part 50 nuclear power 
reactor licensees after the spent fuel decay period.
    <bullet> Drug and alcohol testing. This proposed rule would correct 
inconsistencies in the NRC's regulations for fitness-for-duty (FFD) 
programs and clarify provisions regarding a nuclear power reactor 
licensee's insider mitigation program (IMP).
    <bullet> Certified fuel handler definition and elimination of the 
shift technical advisor. This proposed rule would retain the existing 
definition for ``certified fuel handler'' and add an alternative that 
would eliminate the need for nuclear power reactor licensees to seek 
the Commission's approval of a fuel handler training program. The 
proposed provision would require the training program to address the 
safe conduct of decommissioning activities, safe handling and storage 
of spent fuel, and appropriate response to plant emergencies. The 
proposed alternative specifies that a CFH must be qualified in 
accordance with a fuel handler training program that meets the same 
requirements as training programs for non-licensed operators required 
by Sec.  50.120, ``Training and qualification of nuclear power plant 
personnel.'' This proposed rule would also clarify that a Shift 
Technical Advisor (STA) is not required for decommissioning nuclear 
power reactors.
    <bullet> Decommissioning funding assurance. This proposed rule 
recommends several changes regarding decommissioning funding for 
nuclear power reactors. It would modify the reporting frequency in 
Sec.  50.75 to be consistent with the decommissioning funding assurance 
reporting frequency for ISFSIs in Sec.  72.30(c). For ISFSI funding 
reports, this proposed rule would allow licensees to combine the 
reports that are required by Sec.  50.82(a)(8)(v), Sec.  
50.82(a)(8)(vii), and Sec.  72.30 and remove the requirement for NRC 
approval of ISFSI reports filed under Sec.  72.30(c). It also would 
clarify that although the regulations establish a continuing obligation 
to provide reasonable assurance of decommissioning funding, when a 
licensee identifies a shortfall in the report required by Sec.  
50.75(f)(1), the licensee must obtain additional financial assurance to 
cover the shortfall and discuss that information in the next report. In 
addition, this proposed rule would make administrative changes to 
ensure consistency with Sec.  50.4, ``Written communications,'' 
regarding the submission of notifications and to eliminate Sec.  
50.75(f)(2) because Sec.  50.75(f)(1) fully encompasses paragraph 
(f)(2). Besides proposing conforming changes to 10 CFR part 52, the NRC 
is asking whether the NRC should maintain identical requirements in 
Sec.  52.110 and Sec.  50.82.
    <bullet> Offsite and onsite financial protection requirements and 
indemnity agreements. This proposed rule would allow certain nuclear 
power reactor licensees in decommissioning to reduce the insurance 
amounts that they are required to maintain without obtaining exemptions 
from the NRC's regulations.
    <bullet> Environmental considerations. This proposed rule would 
clarify that licensees must evaluate the environmental impacts of 
decommissioning and whether they are bounded by previous environmental 
reviews in the PSDAR. The proposed rule would also clarify 
environmental reporting requirements.
    <bullet> Record retention requirements. This proposed rule would 
remove certain record retention requirements for structures, systems, 
and components (SSCs) that no longer remain in service during 
decommissioning and would remove requirements to keep multiple copies 
of certain spent fuel storage records. The NRC is also asking a 
specific question concerning the recordkeeping requirements for 
facilities licensed under 10 CFR part 52.
    <bullet> Low-level waste transportation. This proposed rule would 
allow a 45-day window for notification of receipt of shipments of low-
level radioactive waste (LLW). This increase from the current 20-day 
notification window is based on operating experience that shows that 45 
days is an appropriate amount of time for notification of LLW 
shipments.
    <bullet> Spent fuel management planning. This proposed rule would 
clarify requirements that the decommissioning documents contain 
information on spent fuel management planning in accordance with the 
regulatory requirements in Sec.  72.218, ``Termination of licenses.''
    <bullet> Backfit rule. This proposed rule would clarify how the NRC 
applies Sec.  50.109, ``Backfitting,'' to nuclear power reactor 
licensees in decommissioning and would make conforming changes to Sec.  
72.62.
    <bullet> Foreign ownership, control, or domination. This proposed 
rule would specify the criteria for when a facility is no longer a 
production or utilization facility and that the foreign ownership, 
control, or domination (FOCD) prohibition found in Sec.  50.38, 
``Ineligibility of certain applicants,'' no longer applies to a person 
seeking a license for such a facility.
    <bullet> Clarification of scope of license termination plan 
requirement. This proposed rule would clarify that the requirement for 
a license termination plan in Sec. Sec.  50.82(a)(9) and 52.110(i) 
applies only to nuclear power reactor licensees that have loaded fuel 
into the reactor.
    <bullet> Removal of license conditions and withdrawal of orders 
made redundant

[[Page 12256]]

by regulation. This proposed rule would deem removed conditions imposed 
upon individual licensees and withdraw NRC orders that have been 
identified as having been made redundant by subsequent regulation 
resulting in their requirements being generically applicable. License 
conditions deemed removed would be actually removed by administrative 
license amendment subsequent to the effective date of the final rule. 
The NRC is interested in obtaining stakeholder input to identify 
potential redundant requirements not listed in this proposed rule.
    <bullet> Changes for consistent treatment of holders of combined 
licenses and operating licenses. The proposed rule would improve 
consistency in regulatory treatment for combined license (part 52) and 
operating license (part 50) holders by aligning regulatory 
applicabilities for combined license holders upon submittal of the 
Sec.  52.110(a) certifications with regulatory applicabilities for 
operating license holders upon submittal of the Sec.  50.82(a)(1) 
certifications.

C. Costs and Benefits

    The NRC prepared a draft regulatory analysis to determine the 
expected quantitative costs and benefits of this proposed rule, as well 
as qualitative factors to be considered in the NRC's rulemaking 
decision. The conclusion of the analysis is that this proposed rule 
would result in net savings to production and utilization facility 
licensees and the NRC. The analysis combines the costs and benefits 
from the decommissioning areas of EP, physical security, cyber 
security, drug and alcohol testing, CFH training, decommissioning 
funding assurance, offsite and onsite financial protection requirements 
and indemnity agreements, environmental considerations, records 
retention, low-level waste transportation, spent fuel management 
planning, application of the Backfit Rule, FOCD, and clarification of 
the scope of a license termination plan. The analysis discusses the 
economic impact to the nuclear industry, government, and society from 
the rulemaking and associated guidance.
    The draft regulatory analysis discusses the cost benefit analysis 
for the various alternatives of each area of decommissioning proposed 
by the NRC, and shows that the NRC's proposed rule and guidance 
development is overall cost beneficial to the nuclear industry, 
government, and society as shown in Table 1.

             Table 1--Summary of Costs and Benefits (7% NPV)
------------------------------------------------------------------------
        Benefits                  Costs                 Net benefit
------------------------------------------------------------------------
       $18,315,000               $(401,000)              $17,914,000
------------------------------------------------------------------------

    The draft regulatory analysis also considers, in a qualitative 
fashion, regulatory efficiency, public health and safety, and common 
defense and security. For the regulatory efficiency aspect, this 
proposed rule would enable the NRC to better maintain and administer 
regulatory activities over the decommissioning process and ensure that 
the requirements for decommissioning production and utilization 
facilities are clear and appropriate. This proposed rule would also 
continue to provide reasonable assurance of adequate protection of the 
public health and safety and promote the common defense and security 
and protect the environment at production and utilization facility 
sites that have started decommissioning.
    Based on these quantitative and qualitative factors, the draft 
regulatory analysis concludes that the proposed rule should be adopted. 
For more information, please see the draft regulatory analysis 
available at the NRC's Agencywide Documents Access and Management 
System (ADAMS) under Accession No. ML22019A132.

Table of Contents

I. Obtaining Information and Submitting Comments
    A. Obtaining Information
    B. Submitting Comments
II. Background
    A. 1988 Decommissioning Rule
    B. 1996 Decommissioning Rule
    C. Post-1996 Final Rule Decommissioning Activity
    D. Spent Fuel Pool Studies
    E. Changes in Nuclear Power Reactor Decommissioning at the NRC 
and Within the Nuclear Power Industry
    F. Decommissioning Lessons Learned Report
    G. Initiation of This Proposed Rule
    H. Advance Notice of Proposed Rulemaking
    I. Regulatory Basis
III. Discussion
    A. Current Regulatory Process
    B. Objectives of This Proposed Rule
    C. Applicability
    D. Applicability to NRC Licensees During Operations
    E. Applicability to ISFSI-Only and Standalone ISFSI/
Decommissioned Reactor Sites
    F. Graded Approach
    G. Technical Basis for Graded Approach
    H. Levels of Decommissioning
    1. Level 1
    2. Level 2
    3. Level 3
    4. Level 4
IV. Scope of the Proposal
    A. Emergency Preparedness
    1. Introduction
    2. Graded Approach for Emergency Preparedness
    3. Licensee Supporting Analyses
    4. Post-Shutdown Emergency Plans
    5. Permanently Defueled Emergency Plans
    6. Independent Spent Fuel Storage Installation-Only Emergency 
Plans
    7. All Spent Fuel Removed From Site
    8. Changes to Emergency Plans
    9. Program Element Review Under Sec.  50.54(t)
    10. Reasonable Assurance and Offsite Radiological Emergency 
Preparedness
    11. Clean-up of Regulations
    12. Revisions to Sec.  72.32
    B. Physical Security
    1. Security Plans
    2. Dry Cask Storage
    3. Significant Core Damage
    4. Vital Areas
    5. Communications
    6. Suspension of Security Measures
    C. Cyber Security
    D. Drug and Alcohol Testing
    1. Scope of 10 CFR Part 26
    2. Fitness-for-Duty Elements for Insider Mitigation Program
    3. Criminal Penalties
    E. Certified Fuel Handler Definition and Elimination of the 
Shift Technical Advisor
    1. Alternative Definition for Certified Fuel Handler
    2. Elimination of the Shift Technical Advisor
    F. Decommissioning Funding Assurance
    1. Clarification of Sec.  50.82(a) and Sec.  52.110(h)
    2. Changes to Reporting Requirements
    3. Shortfalls in Decommissioning Funding Assurance
    4. Conforming Changes to 10 CFR Part 52
    5. Change to 10 CFR Part 72
    G. Offsite and Onsite Financial Protection Requirements and 
Indemnity Agreements
    1. Proposed Revisions to Offsite Liability and Onsite Property 
Insurance Requirements
    2. Proposed Revision to Extraordinary Nuclear Occurrences 
Requirements
    3. Proposed New Rule Language in Sec.  50.54(w)(6)
    H. Environmental Considerations

[[Page 12257]]

    1. Clarifying Changes to 10 CFR Parts 50 and 52
    2. Consistency Changes to 10 CFR Part 51
    I. Record Retention Requirements
    J. Low-Level Waste Transportation
    K. Spent Fuel Management Planning
    1. Requirements for the IFMP in Sec.  50.54(bb) and the PSDAR in 
Sec.  50.82 and Sec.  52.110
    2. Requirements in Sec.  72.218 for Termination of the General 
License for Spent Fuel Storage
    L. Backfit Rule
    M. Foreign Ownership, Control, or Domination
    N. Clarification of Scope of License Termination Plan 
Requirement
    O. Removal of License Conditions and Withdrawal of Orders
    P. Changes for Consistent Treatment of Holders of Combined 
Licenses and Operating Licenses
V. Specific Requests for Comments
VI. Section-by-Section Analysis
VII. Regulatory Flexibility Certification
VIII. Regulatory Analysis
IX. Backfitting and Issue Finality
    A. Current and Future Applicants
    B. Existing Design Certifications
    C. Existing Licensees
    D. Backfit Analysis
    1. Introduction and Background
    2. Detailed Description of the Proposed Change Affecting Issue 
Finality
    3. Benefits: Substantial Increase in Public Health and Safety 
and Common Defense and Security
    4. Costs
    5. Determination of Substantial Benefits Justifying Costs of the 
Proposed Change Affecting Issue Finality
    6. Conclusion
    7. Evaluation of Factors in Sec.  50.109(c)(1) Through (9)
    E. Draft Regulatory Guidance
X. Cumulative Effects of Regulation
XI. Plain Writing
XII. National Environmental Policy Act
XIII. Paperwork Reduction Act
XIV. Criminal Penalties
XV. Voluntary Consensus Standards
XVI. Availability of Guidance
XVII. Public Meeting
XVIII. Availability of Documents

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2015-0070 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly available information related to this action by any of the 
following methods:
    <bullet> Federal Rulemaking Website: Go to <a href="https://www.regulations.gov">https://www.regulations.gov</a> and search for Docket ID NRC-2015-0070.
    <bullet> NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at <a href="https://www.nrc.gov/reading-rm/adams.html">https://www.nrc.gov/reading-rm/adams.html</a>. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, 
or by email to <a href="/cdn-cgi/l/email-protection#0e7e6a7c207c6b7d617b7c6d6b4e607c6d20696178"><span class="__cf_email__" data-cfemail="d7a7b3a5f9a5b2a4b8a2a5b4b297b9a5b4f9b0b8a1">[email&#160;protected]</span></a>. For the convenience of the reader, 
instructions about obtaining materials referenced in this document are 
provided in the ``Availability of Documents'' section of this document.
    <bullet> NRC's PDR: You may examine and purchase copies of public 
documents, by appointment, at the NRC's PDR, Room P1 B35, One White 
Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. To make 
an appointment to visit the PDR, please send an email to 
<a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="b5e5f1e79be7d0c6dac0c7d6d0f5dbc7d69bd2dac3">[email&#160;protected]</a> or call 1-800-397-4209 or 301-415-4737, between 
8:00 a.m. and 4:00 p.m. (ET), Monday through Friday, except Federal 
holidays.

B. Submitting Comments

    The NRC encourages electronic comment submission through the 
Federal rulemaking website (<a href="https://www.regulations.gov">https://www.regulations.gov</a>). Please 
include Docket ID NRC-2015-0070 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at 
<a href="https://www.regulations.gov">https://www.regulations.gov</a> as well as enter the comment submissions 
into ADAMS. The NRC does not routinely edit comment submissions to 
remove identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Background

    Under 10 CFR part 50 and 10 CFR part 52, the NRC requires current 
and future holders of operating licenses and current and future holders 
of combined licenses, respectively, to comply with a variety of 
regulatory requirements related to decommissioning. This section 
discusses previous rules that set out the NRC's requirements for 
production and utilization facility decommissioning and activities that 
have led to the development of this proposed rule.

A. 1988 Decommissioning Rule

    On June 27, 1988, the NRC published a final rule titled, ``General 
Requirements for Decommissioning Nuclear Facilities'' (53 FR 24018) 
(referred to herein as the ``1988 Final Rule''), which established 
decommissioning requirements for various types of licensees. In this 
rule, the NRC amended its regulations to provide specific requirements 
for the decommissioning of nuclear facilities. Specifically, the final 
rule established regulations on acceptable decommissioning 
alternatives, planning for decommissioning, decommissioning timeliness, 
assurance of the availability of funds for decommissioning, and 
environmental review requirements related to decommissioning. The 1988 
Final Rule amended the regulations that applied to applicants and 
licensees under 10 CFR part 30, ``Rules of General Applicability to 
Domestic Licensing of Byproduct Material''; 10 CFR part 40, ``Domestic 
Licensing of Source Material''; 10 CFR part 50; 10 CFR part 70, 
``Domestic Licensing of Special Nuclear Material''; and 10 CFR part 72, 
``Licensing Requirements for the Independent Storage of Spent Nuclear 
Fuel, High-Level Radioactive Waste, and Reactor-Related Greater than 
Class C Waste.''
    In the 1988 Final Rule, the NRC defined decommissioning as the 
``removal of nuclear facilities safely from service and reduction of 
residual radioactivity to a level that permits release of the property 
for unrestricted use and termination of the license.'' The NRC also 
stated in the 1988 Final Rule that decommissioning activities do not 
include the removal and disposal of spent fuel, which is considered to 
be an operational activity, or the removal and disposal of 
nonradioactive structures and materials beyond that necessary to 
terminate the NRC license.
    The purpose of the 1988 Final Rule, in part, was to ensure that 
reactor decommissioning would be carried out with minimal impact on 
public and occupational health and safety and the environment. The 
NRC's objective was that decommissioned facility sites would ultimately 
be available for unrestricted use for any public or private purpose. 
The amended regulations provided a regulatory framework for efficient 
and consistent licensing actions related to decommissioning.
    The NRC noted in the 1988 Final Rule that, although decommissioning 
was not an imminent health and safety problem, the number and 
complexity of facilities that would require decommissioning

[[Page 12258]]

was expected to increase, and inadequate or untimely consideration of 
decommissioning, specifically in the areas of planning and financial 
assurance, could result in significant adverse health, safety, and 
environmental impacts. The 1988 Final Rule clearly states that the 
licensee is responsible for the funding and completion of 
decommissioning in a manner that protects public health and safety. The 
NRC stated, ``With the increased number of decommissionings expected, 
case-by-case procedures would make licensing difficult and increase NRC 
and licensee staff resources needed for these activities'' (53 FR 
24019).
    The 1988 Final Rule required that, within 2 years after a licensee 
permanently ceases operation of a licensed nuclear facility, the 
licensee must submit a detailed decommissioning plan to the NRC for 
approval along with a supplemental environmental report that addresses 
environmental issues that have not already been considered. Based on 
these submittals, the NRC reviewed the licensee's planned activities, 
prepared a safety evaluation report and an environmental assessment 
(EA), and either made a finding of no significant impact (the usual 
case) or prepared an environmental impact statement. Upon approval of 
the decommissioning plan, the NRC issued an order under Sec.  2.202, 
``Orders,'' permitting the licensee to decommission its facility in 
accordance with the approved plan. As part of the approval process for 
the decommissioning plan, the public had the opportunity to request a 
hearing under 10 CFR part 2, ``Agency Rules of Practice and 
Procedure.'' The NRC would terminate the license once the 
decommissioning process was completed and the NRC was satisfied that 
the facility had been radioactively decontaminated to an unrestricted 
release level under Sec.  20.1402, ``Radiological criteria for 
unrestricted use.'' \1\
---------------------------------------------------------------------------

    \1\ License termination based upon a facility meeting the 
unrestricted use criteria under Sec.  20.1402 is the most common 
license termination scenario. The NRC may also terminate a facility 
license under restricted conditions (Sec.  20.1403, ``Criteria for 
license termination under restricted conditions'') and under 
alternative criteria (Sec.  20.1404, ``Alternative criteria for 
license termination'').
---------------------------------------------------------------------------

    If the licensee chose to place the reactor in storage and dismantle 
it at a later time, the initial decommissioning plan submittal was not 
required to be as detailed as a plan for prompt dismantlement. However, 
before the licensee could begin dismantlement, the regulations required 
that the licensee submit a detailed plan and environmental report to 
the NRC for approval. Before the decommissioning plan was approved, the 
licensee could not perform any major decommissioning activities. If a 
licensee desired a reduction in requirements because of the permanent 
cessation of operations, it had to obtain a license amendment for 
possession-only status. This possession-only license amendment was 
usually granted after the licensee indicated that the reactor had 
permanently ceased operations and that fuel had been permanently 
removed from the reactor vessel. Three examples of licensees that were 
granted possession-only status are Yankee Atomic Electric Company for 
the Yankee Nuclear Power Station (Yankee Rowe) (August 5, 1992; ADAMS 
Accession No. ML17283A069), Portland General Electric Company for the 
Trojan Nuclear Power Plant (May 5, 1993; ADAMS Accession No. 
ML18095A126), and Sacramento Municipal Utility District for the Rancho 
Seco Nuclear Generating Station (March 17, 1992; ADAMS Accession No. 
ML17283A071).
    The 1988 Final Rule required licensees to provide assurance that, 
at any time during the life of the facility through termination of the 
license, adequate funds will be available to complete decommissioning. 
For operating reactors, the 1988 Final Rule prescribed the required 
amount of decommissioning funding in Sec.  50.75. The 1988 Final Rule 
also imposed the requirement that, 5 years before license expiration or 
cessation of operations, licensees must submit a preliminary 
decommissioning plan containing a site-specific decommissioning cost 
estimate and appropriately adjust the financial assurance mechanism. In 
addition, the 1988 Final Rule required licensees to submit a 
decommissioning plan, including a site-specific cost estimate for 
decommissioning and a correspondingly adjusted financial assurance 
mechanism, within 2 years after permanent cessation of operations. For 
delayed dismantlement of a nuclear facility, the 1988 Final Rule 
required licensees to submit an updated decommissioning plan with the 
estimated cost covering the delay of decommissioning and to 
appropriately adjust the financial assurance mechanism. Before approval 
of the decommissioning plan, the 1988 Final Rule specified that 
licensee use of the decommissioning funds would be determined on a 
case-specific basis for premature closure, when the accrual of required 
decommissioning funds may be incomplete.

B. 1996 Decommissioning Rule

    On July 29, 1996, the NRC amended its regulations for reactor 
decommissioning to clarify ambiguities, codify procedures that reduced 
regulatory burden, provide greater flexibility, and allow for greater 
public participation in the decommissioning process in a final rule 
titled, ``Decommissioning of Nuclear Power Reactors'' (61 FR 39278) 
(referred to herein as the ``1996 Final Rule''). The 1996 Final Rule 
made fundamental changes to nuclear power reactor decommissioning by 
streamlining the process and reducing both licensee and NRC resource 
expenditures while maintaining safety, protecting the environment, and 
encouraging public involvement.
    In the 1996 Final Rule, the NRC explained that the degree of 
regulatory oversight required for a nuclear power reactor in 
decommissioning is considerably less than that required for a facility 
during its operating stage. During the operating stage of the reactor, 
fuel in the reactor core undergoes a controlled nuclear fission 
reaction that generates a high neutron flux and large amounts of heat. 
Safe control of the nuclear reaction involves the use and operation of 
many complex systems. First, the nuclear reaction must be carefully 
controlled through neutron-absorbing mechanisms. Second, the heat 
generated must be removed so that the fuel and its supporting structure 
do not overheat. Third, the confining structure and ancillary systems 
must be maintained and degradation caused by radiation and mechanical 
and thermal stress ameliorated. Fourth, the radioactivity resulting 
from the nuclear reaction in the form of direct radiation (especially 
near the high neutron flux areas around the reactor vessel) and any 
radiologically contaminated materials and radiological effluents 
(gaseous and liquid) must be minimized and controlled. Moreover, proper 
operating procedures must be established and maintained, with 
appropriately trained staff to ensure that the reactor system is 
properly operated and maintained, and that operating personnel minimize 
their exposure to radiation when performing their duties. Finally, 
emergency response procedures must be established and maintained to 
protect the public in the event of an accident.
    Decommissioning of a nuclear power reactor begins when the nuclear 
fission reaction is stopped and the fuel (in the form of spent fuel 
assemblies) is permanently removed from the reactor

[[Page 12259]]

vessel and placed in the SFP until transferred to interim storage in an 
onsite ISFSI or transported offsite for storage or disposal. While the 
spent fuel is still highly radioactive and generates heat caused by 
radioactive decay, the fuel slowly cools as its energetic decay 
products diminish. The SFP, which contains circulating water, removes 
the decay heat and filters out any small radioactive contaminants 
escaping the spent fuel assemblies. The SFP system is relatively simple 
to operate and maintain compared to an operating nuclear power reactor. 
The remainder of the facility may contain radioactive contamination in 
areas that were directly impacted by reactor operation, and will be 
more highly contaminated in the area of the reactor vessel. However, no 
new radioactivity can be generated because the spent fuel is stored in 
a configuration that precludes the nuclear fission reaction. Once the 
nuclear fission process has permanently ceased and the fuel assemblies 
have been removed from the reactor vessel, safety concerns for an SFP 
are greatly reduced because there is no longer generation of large 
amounts of heat, high neutron flux and related materials degradation, 
and other related stresses that result from the functioning of an 
operating reactor system.
    Contaminated areas of the facility must still be controlled to 
minimize radiation exposure to personnel and control the spread of 
radioactive material. This situation is now similar to a contaminated 
materials facility and does not require the oversight that an operating 
reactor would require.
    The amendments issued in the 1996 Final Rule provided licensees 
with simplicity and flexibility in implementing the decommissioning 
process, especially with regard to premature closure. The amendments 
clarified ambiguities in the regulations existing at the time, codified 
procedures and terminology that had been used in a number of specific 
cases, and increased opportunities for the public to become informed 
about the licensee's decommissioning activities. The amendments 
established a level of NRC oversight commensurate with the level of 
safety concerns expected during decommissioning activities. 
Specifically, the 1996 Final Rule established or modified requirements 
with regard to initial decommissioning activities, major 
decommissioning activities, and license termination procedures.
    With regard to initial decommissioning activities, the 1996 Final 
Rule mandated that, once a licensee permanently ceases operation of the 
nuclear power reactor and removes the fuel assemblies from the reactor 
vessel, it could not undertake any major decommissioning activities 
until it provided the public and the NRC with additional information 
about the proposed decommissioning approach. The NRC required that the 
licensee submit this information in the form of a PSDAR, which consists 
of the licensee's proposed decommissioning activities and schedule 
through license termination, a discussion of the reasons for concluding 
that the environmental impacts associated with the proposed site-
specific decommissioning activities will be bounded by appropriate 
previously issued environmental impact statements, and a 
decommissioning cost estimate for the proposed activities. The NRC 
makes the PSDAR available to the public for comment and holds a public 
meeting concerning the PSDAR in the vicinity of the plant. The NRC, 
however, does not approve the PSDAR and the submission of the PSDAR and 
its review by the NRC does not require the licensee to request a 
license amendment or any other approval.
    The 1996 Final Rule also established that the licensee may not 
begin performing major decommissioning activities until 90 days after 
the NRC receives the PSDAR submittal and until the licensee submits the 
certifications under Sec.  50.82(a)(1) that operations have permanently 
ceased and that fuel has been permanently removed from the reactor 
vessel. The 1996 Final Rule also amended certain 10 CFR part 50 
technical requirements to cover the transition of the facility from 
operating to permanently shutdown status. Specifically, the 1996 Final 
Rule removed the requirement for a licensee that has permanently ceased 
operations and removed fuel from the reactor vessel to obtain a license 
amendment before proceeding with certain decommissioning activities 
within established regulatory constraints (i.e., in accordance with 
Sec.  50.59, ``Changes, tests and experiments''). These changes to the 
decommissioning requirements increased the flexibility in the type of 
actions that licensees could undertake without prior NRC approval.
    With regard to major decommissioning activities, the 1996 Final 
Rule implemented a major change from the 1988 Final Rule in that 
nuclear power reactor licensees would no longer be required to have an 
approved decommissioning plan before being permitted to perform major 
decommissioning activities. The 1996 Final Rule allowed licensees to 
perform activities that meet the criteria in Sec.  50.59, which the NRC 
amended to include additional criteria to ensure that licensees 
consider concerns specific to decommissioning. Based on NRC experience 
with licensee decommissioning activities at the time, the NRC 
recognized that the Sec.  50.59 process used by the licensee during 
reactor operations encompassed routine activities that were similar to 
those undertaken during the decommissioning process. The NRC concluded 
that the licensee could use the Sec.  50.59 process to perform major 
decommissioning activities if licensing conditions and the level of NRC 
oversight required during reactor operations continued during 
decommissioning, commensurate with the risk profile of the facility 
being decommissioned. The 1996 Final Rule also required the licensee to 
provide written notification to the NRC before performing any 
decommissioning activity that is inconsistent with, or makes 
significant schedule changes from, the actions and schedules described 
in the PSDAR.
    With regard to license termination, the 1996 Final Rule required 
that a licensee wishing to terminate its license submit a license 
termination plan for NRC approval. The approval process for the 
termination plan provides for a hearing opportunity under 10 CFR part 
2. The licensee must submit a supplemental environmental report that 
considers new and significant environmental changes associated with 
license termination activities. The 1996 Final Rule imposed an 
additional requirement for the purpose of keeping the public informed. 
A public meeting, similar to the one held after the PSDAR submittal, 
must take place after the licensee submits its license termination plan 
to the NRC.
    The 1996 Final Rule continued the same degree of decommissioning 
financial assurance that was previously required but provided more 
flexibility by allowing licensees to have limited, early use of 
decommissioning funds. The NRC presented this provision in a February 
3, 1994, draft policy statement titled, ``Use of Decommissioning Trust 
Funds before Decommissioning Plan Approval'' (59 FR 5216), which was 
published for comment and eventually incorporated into the 1996 Final 
Rule. Before issuance of the 1996 Final Rule, licensee use of these 
funds was determined on a case-specific basis for prematurely shutdown 
plants. However, the 1996 Final Rule eliminated the requirement for a 
decommissioning plan and instead required a PSDAR submittal, which 
requires a decommissioning cost estimate. The 1996 Final Rule permitted 
3 percent of the decommissioning funds generically

[[Page 12260]]

required by Sec.  50.75 to be available to the licensee for 
decommissioning planning purposes. Moreover, to allow the licensee to 
accomplish major decommissioning activities promptly, an additional 20 
percent of the generic funding amount would be made available 90 days 
after the NRC had received the PSDAR if the licensee had also submitted 
the certifications required by Sec.  50.82(a)(1). The use of any funds 
above those amounts required the licensee to submit a site-specific 
decommissioning cost estimate to the NRC prior to the use of those 
funds.

C. Post-1996 Final Rule Decommissioning Activity

    In a series of Commission papers issued between 1997 and 2001, the 
NRC staff provided options and recommendations to the Commission to 
address regulatory improvements related to nuclear power reactor 
decommissioning. To consolidate these recommendations, in the Staff 
Requirements Memorandum (SRM) for SECY-99-168, ``Staff Requirements--
SECY-99-168--Improving Decommissioning Regulations for Nuclear Power 
Plants,'' dated December 21, 1999 (ADAMS Accession No. ML003752190), 
the Commission directed the NRC staff to proceed with a single, 
integrated, and risk-informed decommissioning rule addressing the areas 
of EP, insurance, safeguards, staffing and training, and backfitting 
for decommissioning nuclear power reactors. The objective of the 
rulemaking was to clarify and remove certain regulations for 
decommissioning nuclear power reactors based in large part on the 
reduction in radiological risk compared to operating reactors.
    On June 28, 2000, the NRC staff submitted SECY-00-0145, 
``Integrated Rulemaking Plan for Nuclear Power Plant Decommissioning,'' 
to the Commission (ADAMS Accession No. ML003721626). In this paper, the 
NRC staff proposed an integrated decommissioning rulemaking plan and 
requested Commission approval to proceed with developing an integrated 
rulemaking for nuclear power plant decommissioning in accordance with 
the recommendations detailed in the rulemaking plan. The paper 
addressed the regulatory areas of EP, insurance, safeguards, staffing 
and training, and backfitting for decommissioning nuclear power 
reactors. The rulemaking plan was contingent on the completion of a SFP 
zirconium fire risk study. The Commission responded to SECY-00-0145 in 
an SRM dated September 27, 2000 (ADAMS Accession No. ML003754381). The 
Commission returned that SECY to the staff without a vote on the 
rulemaking plan pending further developments in the area and requested 
that the staff submit a revised paper to the Commission.

D. Spent Fuel Pool Studies

    In the late 1990s and early 2000s, the NRC was assessing the risk 
of an SFP accident at a nuclear power reactor site in decommissioning. 
Following the removal of spent fuel from the reactor, the principal 
radiological risks are associated with the storage of spent fuel on 
site. Generally, a few months after the reactor has been permanently 
shut down and defueled, there are no possible design-basis accidents 
that could result in a radiological release exceeding the limits 
established by the U.S. Environmental Protection Agency (EPA) early-
phase Protective Action Guides (PAGs) at the exclusion area boundary 
(EPA-400-R-92-001, ``Manual of Protective Action Guides And Protective 
Actions For Nuclear Incidents,'' issued May 1992, and final revision 
EPA-400/R-17/001, ``PAG Manual: Protective Action Guides and Planning 
Guidance for Radiological Incidents,'' issued January 2017). The only 
SFP accident scenario that might lead to a release with offsite 
consequences exceeding the PAGs at a decommissioning reactor is a 
zirconium fire. The zirconium fire scenario is a postulated, but highly 
unlikely, beyond-design-basis accident scenario that involves a major 
loss of water inventory from the SFP, resulting in a significant heatup 
of the spent fuel, and culminating in substantial zirconium cladding 
oxidation, fire, and fuel damage. The significance of spent fuel heatup 
scenarios that might result in a zirconium fire depends on the decay 
heat of the irradiated fuel stored in the SFP. Therefore, the 
probability of a zirconium fire scenario continues to decrease as a 
function of the time that the decommissioning reactor has been 
permanently shut down and defueled.
    In the 1980s, the NRC examined the risk of an SFP accident as 
Generic Safety Issue 82, ``Beyond Design Basis Accidents in Spent Fuel 
Pools,'' because of the increased use of high-density storage racks and 
laboratory studies that indicated the possibility of a zirconium fire 
spreading between assemblies in an air-cooled environment (see Section 
3 of NUREG-0933, ``Resolution of Generic Safety Issues,'' issued 
December 2011 (available at <a href="https://www.nrc.gov/sr0933/Section%203.%20New%20Generic%20Issues/082r3.html">https://www.nrc.gov/sr0933/Section%203.%20New%20Generic%20Issues/082r3.html</a>)). The risk assessment 
and cost benefit analyses developed through this effort (Section 6.2 of 
NUREG-1353, ``Regulatory Analysis for the Resolution of Generic Issue 
82, `Beyond Design Basis Accidents in Spent Fuel Pools,' '' issued 
April 1989 (ADAMS Accession No. ML082330232)) concluded that the risk 
of a severe accident in the SFP was low and appeared to meet the public 
health objectives of the Commission's Safety Goal Policy Statement (51 
FR 30028; August 21, 1986) and that no new regulatory requirements were 
warranted.
    To support the rulemaking for decommissioning nuclear power plants 
in the late 1990s, the NRC reevaluated the risk of an SFP accident. The 
NRC's assessment in NUREG-1738, ``Technical Study of Spent Fuel Pool 
Accident Risk at Decommissioning Nuclear Power Plants,'' issued 
February 2001 (ADAMS Accession No. ML010430066), conservatively assumed 
that if the water level in the SFP dropped below the top of the spent 
fuel, an SFP zirconium fire involving all of the spent fuel would occur 
and thereby bounded those conditions associated with air cooling of the 
fuel (including partial draindown scenarios) and fire propagation. Even 
with this conservative assumption, the study found the risk of an SFP 
fire to be low and well within the Commission's safety goals.
    Although NUREG-1738 did not completely rule out the possibility of 
a zirconium fire, it did demonstrate that storage of spent fuel in a 
high-density configuration in SFPs is safe and that the risk of 
accidental release of a significant amount of radioactive material to 
the environment is low. The study used simplified and sometimes 
bounding assumptions and models to characterize the likelihood and 
consequences of beyond-design-basis SFP accidents. Subsequent NRC 
regulatory activities and studies (described in more detail in this 
section) have reaffirmed the safety and security of spent fuel stored 
in pools and have demonstrated that SFPs are effectively designed to 
prevent accidents and minimize damage from malevolent attacks.
    In the wake of the terrorist attacks of September 11, 2001, the NRC 
took several actions to further reduce the possibility of an SFP fire. 
The NRC issued immediately effective nonpublic orders (see the cover 
letter at ADAMS Accession No. ML020510637) that required licensees to 
implement additional security measures, including increased patrols, 
augmented security forces and capabilities, and more restrictive site-
access controls to reduce the likelihood of an SFP accident resulting 
from a terrorist-initiated event. A memorandum to the Commission

[[Page 12261]]

titled, ``Documentation of Evolution of Security Requirements at 
Commercial Nuclear Power Plants with Respect to Mitigation Measures for 
Large Fires and Explosions,'' dated February 4, 2010 (ADAMS Accession 
No. ML092990438), provides a comprehensive discussion of these actions, 
some of which specifically address SFP safety and security.
    New requirements to mitigate a postulated loss of SFP water 
inventory were also implemented following the terrorist attacks of 
September 11, 2001; these requirements resulted in enhanced spent fuel 
coolability and the potential to recover SFP water level and cooling 
prior to a postulated SFP zirconium fire. Based on the implementation 
of these additional strategies, the probability and, accordingly, the 
risk to the public health and safety of an SFP zirconium fire scenario 
has decreased and is expected to be less than previously analyzed in 
NUREG-1738 and previous studies.
    After the events of September 11, 2001, the NRC also addressed by 
order the issue of potential aircraft impacts to the SFP by requiring 
licensees to have in place mitigating strategies for large fires or 
explosions at nuclear power plants. The Nuclear Energy Institute (NEI) 
provided detailed guidance in NEI 06-12, Revision 2, ``B.5.b Phase 2 & 
3 Submittal Guideline,'' dated December 2006 (ADAMS Accession No. 
ML070090060). The NRC found this guidance acceptable for use as 
documented in NUREG-0800, ``Standard Review Plan for the Review of 
Safety Analysis Reports for Nuclear Power Plants: LWR Edition,'' 
Section 19.4, ``Strategies and Guidance to Address Loss of Large Areas 
of the Plant Due to Explosions and Fires,'' Revision 0, dated June 2015 
(ADAMS Accession No. ML13316B202). The NRC's issuance of the final rule 
titled, ``Power Reactor Security Requirements,'' on March 27, 2009 (74 
FR 13926), made the requirements of the order generically applicable. 
In that final rule, the NRC added Sec.  50.54(hh)(2) to require 
licensees to develop and implement guidance and strategies to, among 
other things, maintain or restore SFP cooling capability in the event 
of loss of large areas of the plant resulting from fires or explosions, 
which further decreases the probability of an SFP fire.
    Under Sec.  50.54(hh)(2), nuclear power reactor licensees are 
required to implement strategies such as those provided in NEI 06-12. 
The NEI guidance specifies that portable, power independent pumping 
capabilities must be able to provide at least 500 gallons per minute of 
bulk water makeup to the SFP and at least 200 gallons per minute of 
water spray to the SFP. Recognizing that the SFP is more susceptible to 
a release when the spent fuel is in a nondispersed configuration (i.e., 
fuel assemblies with more decay heat are not dispersed among fuel 
assemblies with less decay heat), the guidance also specifies that the 
portable equipment should be capable of being deployed within 2 hours 
for a nondispersed configuration.
    Further, other organizations, such as Sandia National Laboratories 
(SNL), have confirmed the effectiveness of the additional mitigation 
strategies to maintain spent fuel cooling in the event that the pool is 
damaged and its initial water inventory is reduced or lost entirely. 
The analyses conducted by SNL (collectively referred to as the ``Sandia 
studies'') are sensitive security-related information and are not 
available to the public. The Sandia studies considered spent fuel 
loading patterns and other aspects of a pressurized water reactor SFP 
and a boiling water reactor SFP, including the role that the 
circulation of air plays in the cooling of spent fuel when there is a 
partial or complete loss of water. The Sandia studies indicated that 
there is a significant amount of time between the initiating event 
(i.e., the event that causes the SFP water level to drop) and the point 
at which the spent fuel assemblies become partially or completely 
uncovered. In addition, the Sandia studies indicated that for those 
hypothetical conditions in which air cooling may not be effective in 
preventing a zirconium fire, there is a significant amount of time 
between the spent fuel becoming uncovered and the possible onset of 
such a zirconium fire, thereby providing a substantial opportunity for 
event mitigation. The Sandia studies, which account for relevant heat 
transfer and fluid flow mechanisms, also indicated that air cooling 
spent fuel could be sufficient to prevent SFP zirconium fires at a 
point much earlier following fuel offload from the reactor than 
previously considered in NUREG-1738.
    In NUREG-2161, ``Consequence Study of a Beyond-Design-Basis 
Earthquake Affecting the Spent Fuel Pool for a U.S. Mark I Boiling 
Water Reactor,'' issued September 2014 (ADAMS Accession No. 
ML14255A365), the NRC evaluated the potential benefits of strategies 
required in Sec.  50.54(hh)(2). The report explains that successful 
implementation of mitigation strategies significantly reduces the 
likelihood of a release from the SFP in the event of a loss of cooling 
water. Additionally, the NRC found that the placement of spent fuel in 
a dispersed configuration in the SFP would have a positive effect in 
promoting natural circulation, which enhances air coolability and 
thereby reduces the likelihood of a release from a completely drained 
SFP. The NRC issued Information Notice 2014-14, ``Potential Safety 
Enhancements to Spent Fuel Pool Storage,'' dated November 14, 2014 
(ADAMS Accession No. ML14218A493), to all nuclear power reactor and 
ISFSI licensees to inform them of the insights from NUREG-2161. This 
information notice describes the benefits of storing spent fuel in more 
favorable configurations, placing spent fuel in dispersed patterns 
immediately after core offload, and taking action to improve mitigation 
strategies.
    In 2013, the NRC documented a regulatory analysis in COMSECY-13-
0030, ``Staff Evaluation and Recommendation for Japan Lessons Learned 
Tier 3 Issue on Expedited Transfer of Spent Fuel'' (ADAMS Accession No. 
ML13329A918), which considered a broad history of the NRC's oversight 
of spent fuel storage and SFP operating experience (domestic and 
international) and relied on information compiled in NUREG-2161. In 
COMSECY-13-0030, the NRC staff concluded that SFPs are robust 
structures with large safety margins and recommended to the Commission 
that further regulatory actions to require the expedited transfer of 
spent fuel from SFPs to dry cask storage were not warranted. The 
Commission subsequently approved the staff's recommendation in SRM-
COMSECY-13-0030, dated May 23, 2014 (ADAMS Accession No. ML14143A360).
    In addition, in response to the Fukushima Dai-ichi accident, the 
NRC implemented additional regulatory actions to further enhance 
reactor and SFP safety. On March 12, 2012, the NRC issued two orders: 
Order EA-12-051, ``Order Modifying Licenses with Regard to Reliable 
Spent Fuel Pool Instrumentation'' (ADAMS Accession No. ML12054A679), 
and Order EA-12-049, ``Order Modifying Licenses with Regard to 
Requirements for Mitigation Strategies for Beyond-Design-Basis External 
Events'' (ADAMS Accession No. ML12054A735). Order EA-12-051 required 
licensees to install reliable means of remotely monitoring wide-range 
SFP levels to support effective prioritization of event mitigation and 
recovery actions in the event of a beyond-design--basis external event. 
Although the primary purpose of the order was to ensure that operators 
were not distracted by uncertainties related to SFP conditions during 
the accident

[[Page 12262]]

response, the improved monitoring capabilities would help in the 
diagnosis and response to potential losses of SFP integrity. Order EA-
12-049 required licensees to, among other actions, develop, implement, 
and maintain guidance and strategies to maintain or restore SFP cooling 
capabilities independent of normal alternating current power systems 
following a beyond-design-basis external event. Further, the NRC issued 
the Mitigation of Beyond-Design-Basis Events final rule on August 9, 
2019 (84 FR 39684), which made these two orders generically applicable 
and moved the requirements of Sec.  50.54(hh)(2) to paragraph (b)(2) of 
the new Sec.  50.155, ``Mitigation of beyond-design-basis events.'' 
These requirements ensure that a more reliable and robust mitigation 
capability is in place to address degrading conditions in SFPs 
resulting from certain significant, but unlikely, events.
    The additional mitigation strategies implemented after the 
terrorist attacks of September 11, 2001, such as the issuance of Sec.  
50.54(hh)(2) (now Sec.  50.155(b)(2)) and the NRC's review and approval 
of NEI 06-12, and the issuance of Orders EA-12-049 and EA-12-051, made 
generically applicable as Sec.  50.155(b)(1) and Sec.  50.155(e), 
following the Fukushima Dai-ichi accident enhance spent fuel 
coolability and the potential to recover SFP water level and cooling 
before the initiation of a potential SFP zirconium fire. The Sandia 
studies also confirmed the effectiveness of additional mitigation 
strategies to maintain spent fuel cooling in the event that the pool is 
drained. Based on this information and the implementation of additional 
strategies, the probability of an SFP zirconium fire initiation in a 
draindown event is expected to be less than that reported in NUREG-1738 
and previous studies and therefore well within the Commission's 
expressed safety goals, as described previously.

E. Changes in Nuclear Power Reactor Decommissioning at the NRC and 
Within the Nuclear Power Industry

    On June 4, 2001, the NRC staff submitted SECY-01-0100, ``Policy 
Issues Related to Safeguards, Insurance, and Emergency Preparedness 
Regulations at Decommissioning Nuclear Power Plants Storing Fuel in 
Spent Fuel Pools'' (ADAMS Accession No. ML011450420), to the 
Commission. Before the Commission responded to SECY-01-0100, the 
terrorist attacks of September 11, 2001, occurred. Given the security 
implications of those events and the results of the NUREG-1738 
zirconium fire risk study that showed the risk of an SFP fire to be low 
and well within the Commission's safety goals, the NRC later redirected 
its rulemaking priorities and resources to focus on programmatic 
regulatory changes related to safeguards and security. In a memorandum 
to the Commission titled, ``Status of Regulatory Exemptions for 
Decommissioning Plants,'' dated August 16, 2002 (ADAMS Accession No. 
ML030550706), the NRC staff justified this redirection in part by 
observing that no additional permanent nuclear power reactor shutdowns 
were anticipated in the foreseeable future and that no immediate need 
existed to proceed with the decommissioning regulatory improvement work 
that was planned. The NRC staff concluded that, if any additional 
nuclear power reactors permanently shut down after the rulemaking 
effort was suspended, establishment of the decommissioning regulatory 
framework would continue to be addressed for each facility through the 
license amendment and exemption processes.
    Between 1998 and 2013, no nuclear power reactors permanently ceased 
operation. Between 2013 and 2021, however, 12 nuclear power reactors 
permanently shut down, defueled, and entered decommissioning. Notably, 
in 2013, four nuclear power reactor units permanently shut down without 
significant advance notice or preplanning: Crystal River Unit 3 Nuclear 
Generating Plant (Duke Energy Florida); Kewaunee Power Station 
(Dominion Energy); and San Onofre Nuclear Generating Station (SONGS), 
Units 2 and 3 (Southern California Edison). In addition, on December 
29, 2014, Entergy Nuclear Operations, Inc. (Entergy) permanently ceased 
operations at the Vermont Yankee Nuclear Power Station (VY); on October 
24, 2016, the Omaha Public Power District permanently ceased operations 
at Fort Calhoun Station, Unit 1; on September 17, 2018, Exelon 
Generation Company, LLC (Exelon) permanently ceased operations at 
Oyster Creek Nuclear Generating Station; on May 31, 2019, Entergy 
permanently ceased operations at Pilgrim Nuclear Power Station; on 
September 20, 2019, Exelon permanently ceased operations at Three Mile 
Island, Unit 1; on April 30, 2020, and April 30, 2021, respectively, 
Entergy permanently ceased operations at Indian Point Nuclear 
Generating, Unit Nos. 2 and 3; and on August 10, 2020, NextEra Energy 
Duane Arnold, LLC (NextEra) permanently ceased operations of Duane 
Arnold Energy Center. Licensees have also announced plans for 
additional near-term permanent shutdowns, including Palisades Nuclear 
Plant (Entergy) and Diablo Canyon Power Plant, Units 1 and 2 (Pacific 
Gas & Electric Co.).
    Decommissioning reactor licensees and the NRC have expended 
substantial resources processing licensing actions for nuclear power 
reactors during their transition period to decommissioning status. 
Consistent with the nuclear power reactors that permanently shut down 
in the 1990s, the licensees that are currently transitioning to 
decommissioning have been requesting NRC review and approval of 
licensing actions, informed by the low risk of an offsite radiological 
release posed by a decommissioning reactor. Specifically, the licensees 
are seeking NRC approvals of exemptions from requirements and license 
amendments to reflect the reduced operations and radiological risks 
posed by a permanently shutdown and defueled nuclear power reactor.

F. Decommissioning Lessons Learned Report

    In October 2016, the NRC published the ``Power Reactor Transition 
from Operations to Decommissioning: Lessons Learned Report'' (ADAMS 
Accession No. ML16085A029). The report documents the lessons learned by 
the NRC and stakeholders associated with permanent nuclear power 
reactor shutdowns during the period from 2013 to 2016. In particular, 
the report focuses on the transition from reactor operations to 
decommissioning for Kewaunee, Crystal River Unit 3, SONGS Units 2 and 
3, and VY. The transition process includes the NRC's review and 
approval of certain requests for exemptions from the NRC's regulations 
and for license amendments to modify the operating reactors' licensing 
bases to reflect those of decommissioning reactors. After these actions 
are complete, the NRC then transfers the project management and 
oversight responsibility from its Office of Nuclear Reactor Regulation 
to its Office of Nuclear Material Safety and Safeguards (NMSS). Project 
management support is provided by NMSS for these decommissioning 
reactors until license termination. The report also provides a number 
of best practices identified from recent experience with reactor 
shutdowns and the transition to decommissioning.
    The report highlights some of the challenges experienced by the NRC 
during the decommissioning transition licensing reviews from 2013 to 
2016 and the NRC's actions to address those challenges. The report also 
discusses external stakeholders' interest in the NRC's review of the 
decommissioning transition licensing activities, especially

[[Page 12263]]

those associated with SONGS Units 2 and 3 and VY, as represented by 
requests for hearings, public meetings, and questions to the NRC staff.
    In addition to the lessons learned and best practices, the report 
provides detailed project management guidance, recommendations, and 
documentation of precedent related to the reviews and evaluations 
specific to the types of licensing actions that the NRC expects to be 
processed during the decommissioning transition period, including 
oversight activities and communications. The NRC considered many of the 
lessons learned and recommendations described in this report during the 
development of this proposed rule.

G. Initiation of This Proposed Rule

    In light of the number of licensees deciding to permanently shut 
down their nuclear power reactors, the Commission directed the NRC 
staff to proceed with an integrated rulemaking on nuclear power reactor 
decommissioning in an SRM dated December 30, 2014 (ADAMS Accession No. 
ML14364A111), associated with SECY-14-0118, ``Request by Duke Energy 
Florida, Inc., for Exemptions from Certain Emergency Planning 
Requirements,'' dated October 29, 2014 (ADAMS Accession No. 
ML14219A444). The Commission further stated that this rulemaking should 
address:
    <bullet> Issues discussed in SECY-00-0145 such as the graded 
approach to EP;
    <bullet> Lessons learned from the plants that have already gone 
through (or are currently going through) the decommissioning process;
    <bullet> The advisability of requiring a licensee's PSDAR to be 
approved by the NRC;
    <bullet> The appropriateness of maintaining the three existing 
options for decommissioning (DECON, SAFSTOR, and ENTOMB) \2\ and the 
timeframes associated with those options;
---------------------------------------------------------------------------

    \2\ Additional information about the existing options for 
decommissioning is available in NUREG/BR-0521, Rev. 1, 
``Decommissioning Nuclear Power Plants,'' dated June 2017 (ADAMS 
Accession No. ML17177A253).
---------------------------------------------------------------------------

    <bullet> The appropriate role of State and local governments and 
non-governmental stakeholders in the decommissioning process; and
    <bullet> Any other issues deemed relevant by the NRC staff.
    In SECY-15-0014, ``Anticipated Schedule and Estimated Resources for 
a Power Reactor Decommissioning Rulemaking,'' dated January 30, 2015 
(ADAMS Accession No. ML15082A089, redacted), the NRC staff committed to 
proceed with a rulemaking on nuclear power reactor decommissioning and 
provided an anticipated schedule and estimate of the resources required 
for the completion of a decommissioning rulemaking.

H. Advance Notice of Proposed Rulemaking

    To begin the nuclear power reactor decommissioning rulemaking 
process, the NRC published an advance notice of proposed rulemaking 
(ANPR) in the Federal Register on November 19, 2015 (80 FR 72358). In 
the ANPR, the NRC sought public comment on specific questions and 
issues with respect to possible revisions of the NRC's decommissioning 
requirements. The NRC staff considered the comments received on the 
ANPR in its formulation of a draft regulatory basis for further 
regulatory action. Section 5 of the draft regulatory basis (ADAMS 
Accession No. ML17047A413) summarizes the public comments received on 
the ANPR.

I. Regulatory Basis

    The NRC published the draft regulatory basis in the Federal 
Register on March 15, 2017 (82 FR 13778). In the draft regulatory 
basis, the NRC staff presented draft recommendations for amendments to 
the NRC's regulations and guidance development to provide regulatory 
improvements for nuclear power reactors transitioning to 
decommissioning. The NRC requested public comment on these 
recommendations and asked specific questions regarding other possible 
revisions of the NRC's requirements. In addition, the NRC published a 
preliminary draft regulatory analysis on May 9, 2017 (82 FR 21481). The 
NRC held a public meeting from May 8-10, 2017, to discuss the draft 
regulatory basis and the associated preliminary draft regulatory 
analysis and issued a summary of the meeting on November 15, 2017 
(ADAMS Accession No. ML17157B211).
    The NRC received 40 public comment submissions on the draft 
regulatory basis and preliminary draft regulatory analysis, which it 
considered in its formulation of the revised regulatory basis. The NRC 
published a Federal Register notice announcing the public availability 
of the regulatory basis on November 27, 2017 (82 FR 55954).\3\
---------------------------------------------------------------------------

    \3\ At the time of publication of the regulatory basis, the 
rulemaking title was ``Regulatory Improvements for Power Reactors 
Transitioning to Decommissioning.'' During the development of the 
proposed rule, the scope of the rulemaking expanded to include all 
production and utilization facilities licensed under 10 CFR parts 50 
and 52. In order to reflect this change, the NRC has changed the 
title of the rulemaking to ``Regulatory Improvements for Production 
and Utilization Facilities Transitioning to Decommissioning.''
---------------------------------------------------------------------------

III. Discussion

A. Current Regulatory Process

    Decommissioning requirements for production and utilization 
facilities are codified in Sec. Sec.  50.82 and 52.110. Associated 
decommissioning funding requirements are codified in Sec. Sec.  50.75, 
50.82, and 52.110. A nuclear power reactor licensee formally begins the 
decommissioning process when it certifies its permanent cessation of 
operations and permanent removal of fuel from the reactor vessel under 
Sec. Sec.  50.82(a)(1) or 52.110(a). Once the NRC dockets these 
certifications, under Sec.  50.82(a)(2) or Sec.  52.110(b), the 10 CFR 
part 50 or 10 CFR part 52 license no longer authorizes operation of the 
reactor or emplacement or retention of fuel in the reactor vessel. 
Despite this withdrawal of authority to operate the reactor, a 
decommissioning nuclear power plant continues to retain a license under 
10 CFR part 50 or 10 CFR part 52. For this reason, the decommissioning 
plant continues to be subject to many of the requirements that apply to 
plants authorized to operate under 10 CFR part 50 or 10 CFR part 52.
    Regulations that are designed to protect the public against reactor 
operation related design-basis events that include conditions of normal 
operation, anticipated operational occurrences, and design-basis 
accidents (DBAs) are no longer applicable at a permanently shutdown and 
defueled reactor. For example, certain accident sequences for a nuclear 
power reactor that is operating, such as loss of coolant accidents and 
anticipated transients without scram, are no longer relevant to a 
permanently shutdown and defueled reactor. In addition, some 
regulations may not be relevant to certain SSCs because the SSCs are no 
longer required to be maintained, to operate, or to mitigate certain 
accidents, events, or transients, regardless of whether they are 
safety-related or security-related SSCs. Other regulations, although 
based on power operation of the plant, may continue to be applicable to 
the permanently defueled facility for a limited time, such as the 
standards for offsite radiological emergency preparedness (REP) plans 
under 10 CFR part 50 or 10 CFR part 52. Typically, the scope of NRC 
requirements can be reduced to those regulations and requirements that 
primarily pertain to the safe storage of the spent fuel in the SFP, as 
described in the site's final safety analysis report (FSAR).

[[Page 12264]]

    Upon permanent cessation of reactor operations and removal of fuel 
from the reactor vessel, the licensee is likely to submit a significant 
number of licensing actions (license amendment and exemption requests) 
to the NRC for review and approval based primarily on the reduced 
radiological risk to public health and safety. As discussed previously 
in this document, the types of potential accidents at decommissioning 
reactors are fewer, and the risks of radiological releases are reduced, 
when compared to those at an operating reactor. Therefore, to reflect 
this reduction in risk, licensees of decommissioning reactors typically 
request certain amendments to their licenses and certain exemptions 
from the NRC's regulations. These licensing actions, which are 
processed by the NRC during licensees' transition from operating to 
decommissioning status, establish the regulatory framework for reactors 
that have permanently shut down and defueled.
    For non-power reactor facilities, Sec.  50.82(b) requires that the 
licensee apply for license termination within two years following 
permanent cessation of operation. Each application for termination of a 
license must be accompanied, or preceded, by a proposed decommissioning 
plan (DP). In addition to the DP required by Sec.  50.82, Sec.  
50.75(f)(4) requires each licensee to submit a preliminary DP. The 
preliminary DP must be submitted at or about 2 years before the 
projected end of operation. In addition to the DP, Sec.  51.53(d) 
requires each applicant for a license amendment approving a DP to 
submit a supplement to its environmental report (ER).
    The decommissioning process for non-power reactor licensees begins 
with the removal of fuel as soon as possible after reactor operations 
permanently cease and the shipment of the fuel offsite in accordance 
with the U.S. Department of Energy, NRC, and U.S. Department of 
Transportation regulations. Under some circumstances, the licensee can 
apply for a possession-only license amendment under Sec.  50.90, 
``Application for amendment of license, construction permit, or early 
site permit,'' after operations have ended and before decommissioning 
starts. The possession-only license amendment limits the licensee's 
authority to possessing specific nuclear material but does not 
authorize its use or the operation of a nuclear facility. If granted, a 
possession-only license amendment provides regulatory relief from the 
license and technical specification (TS) requirements for a non-power 
reactor in decommissioning. Further, the possession-only amendment 
permits the licensee to retain the facility, related radioactive 
byproduct material, and, in some cases, special nuclear material, 
pending approval of the DP.
    In addition to requesting license amendments and exemptions, 
nuclear power reactor licensees can make certain changes without prior 
NRC approval if the changes are permitted by an NRC regulation. 
Licensees primarily use an evaluation process with criteria in Sec.  
50.59 to make changes in a facility (or procedures) as described in the 
FSAR (as updated), including changes to the PSDAR, without prior NRC 
approval. The licensee's updated FSAR should reflect changes to the 
decommissioning design-basis analyses, SSCs, and the licensee's 
organizations, processes, and procedures. Licensees can also make 
changes without prior NRC approval as described in Sec.  50.54(p) and 
Sec.  50.54(q). In the case of non-power reactor facilities, the DP, 
which is put into effect with an order, provides for accommodation of 
any necessary changes in the DP and procedures through a process 
similar to the one in Sec.  50.59.
    The timing and implementation for some decommissioning licensing 
actions rely on an approach that recognizes the reduction in 
radiological risk after permanent cessation of power operation and 
removal of fuel from the reactor vessel. These risk reductions can be 
tied to several factors, including, but not limited to: (1) Reduction 
of the radiological source term after cessation of power operation and 
removal of fuel from the reactor vessel, (2) elapsed time after 
permanent shutdown, and (3) type of long-term onsite fuel storage. The 
two areas where these additional risk reductions are considered in the 
early decommissioning process are EP and facility insurance and 
indemnity. The NRC will not approve exemptions from EP and insurance 
coverage requirements until analyses confirm that there are no DBAs 
that would require protective actions for the public resulting from a 
release of radioactive material with a dose exceeding the EPA's PAGs at 
the exclusion area boundary. The analyses also must assess a postulated 
beyond-design-basis zirconium fire scenario.

B. Objectives of This Proposed Rule

    This proposed rule would amend the current requirements for 
production and utilization facility licensees during decommissioning. 
Experience has demonstrated that licensees for decommissioning nuclear 
power reactors seek several exemptions and license amendments per site 
to establish a long-term licensing basis for decommissioning. Non-power 
production or utilization facility licensees typically seek license 
amendments in decommissioning to change their 10 CFR part 50 operating 
licenses to possession-only licenses. By issuing this rule, the NRC 
would establish regulations that would maintain safety and security at 
sites transitioning to decommissioning without the need to grant 
specific exemptions or license amendments in certain regulatory areas. 
Specifically, the decommissioning rulemaking would: (1) Propose a 
regulatory regime that continues to provide reasonable assurance of 
adequate protection of public health and safety and the common defense 
and security at decommissioning sites; (2) ensure that the requirements 
for decommissioning are clear and appropriate; (3) adopt regulations to 
address generic issues applicable to all decommissioning nuclear power 
reactors that have historically been addressed through similarly worded 
exemptions or license amendments; and (4) identify, define, and resolve 
additional areas of concern related to the regulation of 
decommissioning licensees under 10 CFR parts 50 and 52.
    Given that the current regulatory framework regarding 
decommissioning is adequate to protect public health and safety and the 
common defense and security, many of the new requirements proposed by 
this rulemaking are alternatives to the current requirements.

C. Applicability

    This proposed rule would apply to the following categories of 
license holders:

<bullet> Nuclear power reactors currently licensed under 10 CFR part 50
<bullet> Future nuclear power reactors licensed under 10 CFR part 50
<bullet> Nuclear power reactors currently licensed under 10 CFR part 52
<bullet> Future nuclear power reactors licensed under 10 CFR part 52
<bullet> Non-power production or utilization facilities and fuel 
reprocessing plants currently licensed under 10 CFR part 50
    <bullet> Future non-power production or utilization facilities and 
fuel reprocessing plants licensed under 10 CFR part 50

D. Applicability to NRC Licensees During Operations

    The proposed rule includes changes in three areas that would apply 
to NRC licensees during operations: (1) The process to change a 
licensee's security plan, (2) the timing of decommissioning

[[Page 12265]]

funding assurance reporting requirements, and (3) identification of 10 
CFR 26.3, ``Scope,'' as a regulation with substantive requirements that 
could result in criminal penalties if violated.
    The NRC's regulations in Sec.  50.54(p) establish processes that 
allow licensees to make changes to their security plans. The NRC is 
proposing that all nuclear power reactor licensees making a change 
under Sec.  50.54(p)(2) submit in their report of the change a summary 
of any analysis that was completed to make the determination that the 
change does not decrease the safeguards effectiveness of the security 
plan. Additionally, the NRC is proposing to revise Sec.  50.54(p) to 
include definitions of the terms ``change'' and ``decrease in 
safeguards effectiveness.'' The application of these definitions is 
limited to use with the revised Sec.  50.54(p) and will apply to all 
holders of 10 CFR part 50 operating licenses and 10 CFR part 52 
combined licenses.
    The proposed rule would change the timing of the decommissioning 
funding assurance reporting requirements in Sec.  50.75(f)(1) to 
coordinate them with the ISFSI decommissioning reporting requirements 
in Sec.  72.30, ``Financial assurance and recordkeeping for 
decommissioning.'' This change would convert the biennial 
decommissioning funding status report required for 10 CFR part 50 and 
10 CFR part 52 nuclear power reactor licensees to a triennial 
decommissioning funding status report as currently required for 10 CFR 
part 72 ISFSI licensees.
    Current Sec.  26.3 includes a substantive requirement and 
violations of this regulation should be subject to criminal penalties. 
Therefore, this proposed rule would remove Sec.  26.3 from the list of 
provisions that are not subject to criminal penalties if violated in 
Sec.  26.825(b).

E. Applicability to ISFSI-Only and Standalone ISFSI/Decommissioned 
Reactor Sites

    During the public comment period for the draft regulatory basis, 
the NRC received many comments on the applicability of the 
decommissioning rulemaking to ``standalone ISFSI'' \4\ sites where the 
associated reactor has already been decommissioned in comparison with 
``ISFSI-only'' sites. As part of this rulemaking effort, the NRC 
recommends standardizing the terms ``ISFSI-only'' and ``standalone 
ISFSI/Decommissioned Reactor'' as follows:
---------------------------------------------------------------------------

    \4\ Given that the public comments referred to ``standalone 
ISFSIs,'' this proposed rule uses that same terminology. However, in 
accordance with Inspection Manual Chapter 2690, ``Inspection Program 
for Dry Storage of Spent Reactor Fuel at Independent Spent Fuel 
Storage Installations and for 10 CFR part 71 Transportation 
Packagings,'' dated March 9, 2012, the NRC uses the term ``away-
from-reactor (AFR) ISFSI'' to refer to ``any general licensed ISFSI 
where decommissioning and final survey activities related to reactor 
operations are completed and the only remaining operation conducted 
under the 10 CFR part 50 license is the operation of the general 
licensed ISFSI.''
---------------------------------------------------------------------------

    <bullet> ``ISFSI-only'' sites contain nuclear power reactor 
facilities that are still involved in decommissioning activities, but 
the spent fuel has been completely transferred from the SFPs to dry 
storage in an onsite ISFSI. For these facilities, the remaining 
decommissioning activities are primarily related to remediation of any 
remaining residual radioactivity at the site to meet the license 
termination and decommissioning criteria in 10 CFR part 20, subpart E. 
The ``ISFSI-only'' term refers to the location of the spent fuel; the 
term reflects that no spent fuel is stored in the SFP, and all of the 
spent fuel is in dry storage in an onsite ISFSI.
    <bullet> ``Standalone ISFSI/Decommissioned Reactor'' sites are 
those former nuclear power reactor facilities where the license 
termination and decommissioning criteria in 10 CFR part 20, subpart E, 
have already been met, with the exception of the ISFSI area. The 
licensee's 10 CFR part 50 license for the site has been reduced to an 
area that only encompasses the ISFSI facility (unless the facility 
ISFSI is licensed under a 10 CFR part 72 specific license, in which 
case the 10 CFR part 50 license is wholly terminated). The remaining 
activities at these facilities that are regulated by the NRC are spent 
fuel storage and the eventual decommissioning of the ISFSI itself, once 
the spent fuel has been permanently removed from the site. A 10 CFR 
part 72 specific license ISFSI is decommissioned in accordance with 10 
CFR 72.54, ``Expiration and termination of licenses and decommissioning 
of sites and separate buildings or outdoor areas.''
    Accordingly, the proposed requirements would not apply to 
standalone ISFSI/Decommissioned Reactor sites because those licensees 
have already decommissioned their 10 CFR part 50 facilities and met the 
decommissioning and license termination criteria in 10 CFR part 20, 
subpart E, with the exception of the area encompassed by the remaining 
ISFSI. The proposed requirements are consistent with the licensing 
actions that the NRC has already approved for these licensees. In 
addition, the proposed requirements of this rulemaking provide an 
alternative to the existing decommissioning regulations and would not 
impose new requirements on ISFSI-only licensees.

F. Graded Approach

    As the NRC reviewed the exemption and license amendment requests 
related to the recent nuclear power reactor decommissionings and noted 
the growing list of future planned permanent shutdowns, as discussed in 
the ``Background'' section of this document, the NRC realized that the 
existing regulatory framework could and should be revised to provide 
for a more efficient decommissioning process. As early as the late 
1990's, the NRC contemplated an integrated rulemaking to provide an 
appropriate graded approach to the decommissioning process. A graded 
approach is a process by which the safety requirements and criteria 
adjust during the decommissioning process commensurate with several 
factors. These factors include the magnitude of any credible hazard 
involved, the particular characteristics of a facility, and the balance 
between radiological hazards and non-radiological hazards (e.g., fire, 
flood, chemical spill) as applicable to specific points in time within 
the decommissioning process. This approach would be a risk-informed 
process.
    Currently, no explicit regulatory provisions distinguish 
requirements in several technical areas for a nuclear power reactor 
that has permanently ceased operations from those for an operating 
nuclear power reactor. To address this, the NRC is proposing to amend 
its regulations to provide an efficient regulatory framework for the 
transition to decommissioning. Under this proposed rule, the NRC would 
adopt an optional graded approach for several technical areas that 
provides a set of requirements commensurate with the reductions in 
radiological risk at each of the following four levels of 
decommissioning: (1) Permanent cessation of operations and permanent 
removal of all fuel from the reactor vessel, (2) sufficient decay of 
fuel in the SFP such that it would not reach ignition temperature for 
the zirconium alloy cladding of the fuel within 10 hours under 
adiabatic heatup conditions (i.e., a complete loss of SFP water 
inventory with no heat loss), (3) transfer of all fuel to dry storage, 
and (4) removal of all fuel from the site. Four technical areas of this 
proposed rule (Emergency Preparedness, Physical Security, Cyber 
Security, and Offsite and Onsite Insurance) use all or some of this 
graded approach.

[[Page 12266]]

G. Technical Basis for Graded Approach

    The NRC has approved exemptions from the emergency planning 
regulations in Sec.  50.47, ``Emergency plans,'' and appendix E, 
``Emergency Planning and Preparedness for Production and Utilization 
Facilities,'' to 10 CFR part 50 at several permanently shutdown and 
defueled nuclear power reactor sites. Licensees that have been granted 
EP exemptions must maintain an onsite emergency plan addressing the 
classification of an emergency, notification of emergencies to licensee 
personnel and offsite authorities, and coordination with designated 
offsite government officials following an event declaration so that, if 
needed, offsite authorities may initiate appropriate response actions. 
At the appropriate points in decommissioning, the EP exemptions may 
also relieve the licensee from certain requirements of Sec.  50.47 and 
appendix E to 10 CFR part 50 as they pertain to offsite radiological 
EP, including the requirement to maintain the 10-mile plume exposure 
pathway and the 50-mile ingestion pathway emergency planning zones 
(EPZs). The NRC granted these exemptions based, in part, on its 
determination that there are no applicable design-basis accidents at a 
decommissioning licensee's facility that could result in an offsite 
radiological release exceeding the limits established by the EPA's 
early-phase PAGs at the exclusion area boundary.
    The NRC also relied on analyses from NUREG-1738 that showed that 
emergency planning would be of marginal benefit in reducing the risk of 
a beyond-design-basis zirconium fire in the SFP if the accident evolved 
slowly enough to allow mitigative measures and, if necessary, to allow 
offsite protective actions to be implemented without preplanning. This 
conclusion was based, in part, on the assumption that it would take at 
least 10 hours for spent fuel to heat up to the temperature at which 
the onset of fission product release is expected during an SFP rapid 
draindown event. This 10-hour period would provide a substantial amount 
of time for the licensee to take onsite mitigation measures and, if 
necessary, for offsite authorities to take appropriate response actions 
to protect the public. To support the approval of exemptions from 
portions of the EP regulations, licensees had to demonstrate through 
site-specific analyses that in a draindown event at their SFP the fuel 
would not reach the zirconium fuel cladding ignition temperature for at 
least 10 hours under adiabatic heatup conditions.
    A 10-hour timeframe has been justified in the past for similar 
purposes. In the Low Power Rule (47 FR 30232; July 13, 1982), the NRC 
amended its regulations to clarify that no NRC or Federal Emergency 
Management Agency (FEMA) review, findings, and determinations 
concerning the state or adequacy of offsite emergency preparedness were 
necessary for issuance of operating licenses authorizing fuel loading 
and low power operation (i.e., up to 5 percent of rated power). The NRC 
determined that several factors contributed to a substantial reduction 
in risk and potential accident consequences for low power testing as 
compared to the higher risks in continuous full power operation. These 
factors included consideration of the reduced source term, the 
capability of mitigation systems, and the time scale for taking actions 
to identify and mitigate an accident. Even for a postulated low-
likelihood, design-basis accident during low power operations, which 
eventually results in release of fission products into the containment, 
at least 10 hours would be available to allow adequate precautionary 
actions to be taken to protect the public near the site.
    To support a graded approach during decommissioning, the NRC 
further examined the certainty and margin provided by a 10-hour 
timeframe for the fuel to heat up in relation to the time for taking 
mitigating actions and appropriate EP response actions. The NRC 
conducted an applied research study (``Transmittal of Reports to Inform 
Decommissioning Plant Rulemaking for User Need Request NSIR-2015-001,'' 
dated May 31, 2016 (ADAMS Accession No. ML16110A416)) with three tasks: 
(1) To perform a task analysis that includes a timeline of responder 
actions at representative SFP configurations to mitigate a draindown 
event and determine its likelihood of success, (2) to analyze 
representative spent fuel to determine the decay time necessary for the 
fuel to remain below zirconium clad ignition temperature for at least 
10 hours assuming adiabatic heatup conditions, and (3) to analyze the 
offsite dose rate from the radionuclides released during a hypothetical 
spent fuel zirconium clad ignition accident. As demonstrated in these 
analyses, for many initiating events at decommissioning reactors, 
mitigative actions would have a high likelihood of preventing 
uncontrolled spent fuel heatup. In cases where an uncontrolled heatup 
is not prevented, the heatup would be relatively slow, providing 
significant time before a radiological release. In the case of a 
radiological release, dose rates would be low enough such that 
significant additional time is available to take offsite actions to 
protect the public.
    The NRC's analysis of spent fuel decay times provided information 
on the time required for fuel to heat up to 900 degrees Celsius (C) 
(i.e., the temperature at which the onset of fission product release is 
expected for a zirconium fuel cladding fire) as a function of decay 
time for both pressurized water reactor (PWR) and boiling water reactor 
(BWR) assemblies. The analysis also included sensitivities to the mass 
of the racks and the fuel configuration in the SFP. The NRC notes that 
the decay periods provided for PWRs and BWRs are based on studies that 
consider current operating parameters in the nuclear power industry 
(e.g., fuel types, enrichment, and fuel burnup levels). Based on this 
analysis, the NRC concluded that after a decay period of 10 months for 
BWRs or 16 months for PWRs, beginning when the reactor permanently 
shuts down, the spent fuel cannot reasonably heat up to clad ignition 
temperature within 10 hours after a draindown event. These decay 
periods are based on an adiabatic heatup to 900 degrees C assuming the 
decay heat value for the hottest assembly (as opposed to an average 
assembly), a burnup of 60 gigawatt days per metric ton of heavy metal 
(GWd/MTHM), and accounting for the mass of the racks. The analysis 
assumption of 60 GWd/MTHM conservatively bounds current industry 
burnups and enrichments for zirconium clad fuel and provides margin for 
potentially higher burnup rates, up to 72 GWd/MTHM. This analysis does 
not account for the additional time margin that would be provided if 
additional cooling mechanisms were available or would be provided by a 
more favorable SFP configuration such that the heat load is more 
uniformly distributed.
    The NRC's analysis of dose rates shows that even in the event of a 
beyond-design-basis accident leading to a rapid draindown of the SFP 
and subsequent zirconium fire, there would be additional time margin on 
the order of several hours beyond the 10-hour heatup time during which 
protective actions could be taken to protect the public before the dose 
levels associated with EPA PAGs would be exceeded offsite.
    In addition to the analyses performed by the NRC to support this 
rulemaking, as discussed in the ``Background'' section of this 
document, the conclusions of NUREG-2161 and NUREG-1738 support the 
technical

[[Page 12267]]

basis for a graded approach during decommissioning as they provide 
insight into the risk of an offsite release and the effectiveness of 
mitigation measures.
    <bullet> In NUREG-2161, the NRC considered various spent fuel 
cooling mechanisms and additional heat from oxidation. Because previous 
studies found that earthquakes present the dominant risk for SFPs, this 
analysis considered a severe earthquake with ground motion stronger 
than the maximum earthquake reasonably expected to occur for the 
reference plant, which would challenge the SFP integrity. The study 
considered two spent fuel configurations: High-density and low-density 
loading. The study also analyzed two cases for each scenario: One that 
credited the mitigation measures of Sec.  50.54(hh)(2) (i.e., the 
strategies to maintain or restore SFP cooling in the event of a loss of 
large areas of the plant as a result of fire or explosion), and one in 
which those measures were not used or were unsuccessful. The study 
results showed that successful mitigation reduces the likelihood of a 
release and that the likelihood of a release was equally low for both 
high- and low-density loading in the SFP. The study found that a 
release is not expected to occur at the nuclear power reactor site 
studied for at least 72 hours following a beyond-design-basis seismic 
event that occurs more than 60 days after shutdown.
    <bullet> In NUREG-1738, the NRC presented the results of its 
evaluation of the potential accident risk for an SFP at a 
decommissioning nuclear power reactor in the United States. NUREG-1738 
identified a zirconium cladding fire resulting from a substantial loss 
of water from the SFP as the only postulated scenario at a 
decommissioning nuclear power reactor that could result in a 
significant radiological release. While highly unlikely, the 
consequences of such an accident could lead to an offsite dose in 
excess of the EPA PAGs. Based on spent fuel storage design 
characteristics and operating practices considered in the analysis, the 
scenarios that lead to this condition have very low probabilities of 
occurrence. Accordingly, these scenarios are considered to be beyond 
the facility's design basis. Furthermore, as the spent fuel ages, the 
generation of decay heat decreases. After a certain amount of time, the 
overall risk of a zirconium fire becomes extremely low because of: (1) 
The large amount of time available for preventive and mitigating 
actions and (2) the increased probability that the decay heat will be 
low enough that the fuel will be air-coolable in the post-event 
configuration.

H. Levels of Decommissioning

    Using the aforementioned analyses as its technical basis, the NRC 
is proposing to amend its regulations to provide an efficient 
regulatory framework during decommissioning using a graded approach in 
several technical areas. This graded approach is commensurate with the 
reductions in radiological risk at four levels of decommissioning: 
(Level 1) permanent cessation of operations and permanent removal of 
all fuel from the reactor vessel, (Level 2) sufficient decay of fuel in 
the SFP such that it would not reach ignition temperature within 10 
hours under adiabatic heatup conditions, (Level 3) transfer of all 
spent fuel to dry storage, and (Level 4) removal of all fuel from the 
site. These levels are discussed further as follows:
1. Level 1
    Licensees in Level 1 include nuclear power reactor licensees that 
have docketed certifications of permanent cessation of operations and 
permanent removal of fuel from the reactor vessel pursuant to Sec.  
50.82, ``Termination of license,'' or Sec.  52.110, ``Termination of 
license.'' In this level, a decommissioning nuclear power reactor is 
defueled and permanently shut down, but the spent fuel in the SFP is 
still susceptible to a zirconium fuel cladding fire within 10 hours 
under adiabatic heatup conditions.
2. Level 2
    In Level 2, the reactor is defueled and permanently shut down, and 
spent fuel in the SFP has decayed and cooled sufficiently such that it 
cannot heat up to the zirconium cladding ignition temperature within 10 
hours under adiabatic conditions. The NRC has determined that this 
condition is reached after spent fuel has decayed for a minimum of 
either 10 months for a BWR or 16 months for a PWR or an alternative 
site-specific timeframe to be approved by the NRC. The decay period 
could begin when the fuel is still in the reactor vessel but the 
reactor has permanently ceased operations. In order to verify that a 
licensee has met the condition, the NRC would rely upon the date of 
permanent cessation of operation provided by a licensee under Sec.  
50.4(b)(8) or Sec.  52.3(b)(8), updated as necessary under Sec.  50.9 
or Sec.  52.6, both entitled ``Completeness and accuracy of 
information.'' Because the identified date of permanent cessation of 
operations would determine transition from Level 1 to Level 2, the NRC 
would consider a change in the planned date initially certified to the 
NRC for permanent cessation of operations to the actual date as 
information ``having a significant implication for public health and 
safety or common defense and security'' under Sec.  50.9 or Sec.  52.6. 
At this point, the site may also possess a radioactive inventory of 
liquid radiological waste, radioactive reactor components, and 
contaminated structural materials. The radioactive inventory may 
change, depending on the licensee's proposed shutdown activities and 
schedule.
3. Level 3
    In Level 3, all spent nuclear fuel (SNF) is in dry cask storage 
pursuant to the terms and conditions of a license granted under 10 CFR 
part 72, including the general license issued in Sec.  72.210. However, 
the licensee may still hold a 10 CFR part 50 or 10 CFR part 52 license, 
and the site may contain a radioactive inventory of liquid radiological 
waste, radioactive reactor components, and contaminated structural 
materials.
4. Level 4
    At this point in the facility's life cycle, all SNF has been 
removed from the site. The site may possess a radioactive inventory of 
liquid radiological waste, radioactive reactor components, and 
contaminated structural materials. The radioactive inventory during 
this configuration may change, depending on the licensee's proposed 
decommissioning activities and schedule.
    As a facility transitions from being operational to having all SNF 
in dry cask storage, the proposed rule's regulatory requirements are 
graded to provide for reasonable assurance of the health and safety of 
the public commensurate with the risk profile of the facility. Table 2 
summarizes the proposed changes to decommissioning requirements in the 
technical areas that use aspects of this graded approach.

[[Page 12268]]

[GRAPHIC] [TIFF OMITTED] TP03MR22.000

IV. Scope of the Proposal

    This rulemaking proposes revising requirements in 16 technical 
areas.

A. Emergency Preparedness

1. Introduction
    In 1978, an NRC and EPA task force established the planning basis 
for EP for nuclear power reactor accidents in NUREG-0396, ``Planning 
Basis for the Development of State and Local Government Radiological 
Emergency Response Plans in Support of Light Water Nuclear Power 
Plants'' (ADAMS Accession No. ML051390356). This guidance provides a 
basis for offsite radiological EP efforts for large light-water nuclear 
power reactor facilities. In NUREG-0396, the task force determined that 
no single accident sequence should be identified as a planning basis 
and chose to provide recommendations in terms of the consequences and 
characteristics of accidents that would be important in determining the 
extent of the planning effort. The task force concluded that the EP 
planning basis requires consideration of a spectrum of accidents, 
informed by probability considerations. The scope of the planning 
effort was based on three key planning elements: (1) The distance to 
which planning for the initiation of predetermined protective actions 
is warranted, (2) the time-dependent characteristics of potential 
releases and exposures, and (3) the kinds of radioactive materials that 
can potentially be released to the environment. The risk-informed 
planning basis for EP, established in NUREG-0396, was endorsed for use 
in the NRC's policy statement, ``Planning Basis for Emergency Responses 
to Nuclear Power Reactor Accidents,'' dated October 23, 1979 (44 FR 
61123). This planning basis results in emergency plans that are 
effective, regardless of the accident probability.
    The rationale in NUREG-0396 and the planning basis elements can 
also be applied to light water nuclear power reactors in 
decommissioning to scope the planning effort. The NRC applied the 
NUREG-0396 methodology (i.e., consideration of a spectrum of accident 
consequences and the three key planning elements) to establish a graded 
approach to EP for decommissioning nuclear power reactors that 
maintains public health and safety. As discussed in NUREG-0396, no 
single specific accident sequence should be isolated as the one for 
which to plan because each accident could have different consequences, 
both in nature and degree. Further, the range of possible selections 
for a planning basis is very large, starting with a zero point of 
requiring no planning at all, because significant offsite radiological 
accident consequences are unlikely to occur to planning for the worst 
possible accident regardless of its extremely low likelihood. 
Fundamentally, the spectrum of possible accidents is significantly 
smaller and the risk of an offsite radiological release is 
significantly lower at a nuclear power facility that has permanently 
shut down

[[Page 12269]]

and removed fuel from the reactor vessel than at an operating nuclear 
power reactor. All such accidents would be associated with hazards 
based on the storage of spent fuel, either in the SFP or in dry cask 
storage, until its permanent removal from the site. In NUREG-1738, the 
NRC found that the event sequences important to risk at decommissioning 
sites are limited to large earthquakes and cask drop events. For EP 
assessments, this is an important difference relative to operating 
nuclear power reactors, where typically a large number of different 
sequences make significant contributions to risk.
    Although the NRC considered the full spectrum of accidents 
applicable to a decommissioning nuclear power reactor, the number of 
events that can have significant offsite consequences is greatly 
reduced, and the events are dominated by the zirconium fire scenario--a 
postulated, but highly unlikely, beyond-design-basis accident that 
involves a major loss of water inventory from the SFP, resulting in a 
significant heatup of the spent fuel and culminating in substantial 
zirconium cladding oxidation, fire, and fuel damage. The guidance in 
NUREG-0396 states that while it is not appropriate to develop specific 
plans for the most severe and most improbable events, the 
characteristics of these events should be considered ``in judging 
whether emergency plans based primarily on smaller accidents can be 
expanded to cope with larger events.'' This approach provides 
reasonable assurance that capabilities exist to minimize the impacts of 
even the most severe events. Consistent with this guidance, the NRC 
considered the potential impacts of a zirconium fire, even with the 
assurance that mitigating strategies are in place to prevent an offsite 
release from occurring for this highly unlikely beyond-design-basis 
event.
    In addition to the three analyses performed by the NRC to support 
this rulemaking (ADAMS Accession No. ML16110A416), the NRC has 
previously conducted SFP studies, including NUREG-2161 and NUREG-1738, 
the conclusions of which support the technical basis for a graded 
approach to EP. Overall, these analyses: (1) Demonstrate that a period 
of 10 hours provides sufficient time to implement mitigation measures 
for design-basis events at decommissioning sites, (2) provide a 
conservative basis for a spent fuel decay time beyond which the fuel in 
the SFP can reasonably be expected to take longer than 10 hours to heat 
up to ignition temperature, and (3) provide additional understanding of 
the amount of time available for taking action in response to beyond-
design-basis events, including the margin of time that offsite agencies 
have to decide upon and initiate actions to protect public health and 
safety. The NRC applied these analyses and the considerations from 
previous studies of SFP risk to the planning basis elements from NUREG-
0396 to develop the proposed regulations for EP at various levels 
during decommissioning.
2. Graded Approach for Emergency Preparedness
    A graded approach to EP has a longstanding regulatory history. The 
16 planning standards for operating reactors, outlined in Sec.  
50.47(b), and the associated evaluation criteria in NUREG-0654/FEMA-
REP-1, Revision 1, ``Criteria for Preparation and Evaluation of 
Radiological Emergency Response Plans and Preparedness in Support of 
Nuclear Power Plants,'' issued November 1980 (ADAMS Accession No. 
ML040420012) or Revision 2 issued December 2019 (ADAMS Accession No. 
ML19347D139), are one part of a continuum of planning standards for 
radiological EP. The regulations in Sec.  50.47(c)(2) for case-by-case 
EPZ size determinations; the EP regulations for research and test 
reactors and other non-power production or utilization facilities, fuel 
cycle facilities, and ISFSIs; and the EP considerations for small 
modular reactors and other new technologies (see the Proposed Rule for 
``Emergency Preparedness for Small Modular Reactors and Other New 
Technologies'' (85 FR 28436 and 85 FR 32308)), are also part of a 
graded approach to EP that is commensurate with the relative 
radiological risk, source term, and potential hazards, among other 
considerations.
    Consistent with the concept of a graded approach, the NRC is 
proposing four levels of emergency planning standards that coincide 
with the same milestones as the graded approach:

<bullet> Post-Shutdown Emergency Plan (PSEP) (Level 1)
    <bullet> Permanently Defueled Emergency Plan (PDEP) (Level 2)
<bullet> ISFSI-Only Emergency Plan (IOEP) (Level 3)
<bullet> No emergency planning (Level 4)

    In developing this proposed rule, the NRC considered the 
appropriateness of the EP requirements in 10 CFR part 50 and 10 CFR 
part 72 for decommissioning sites, including those requirements that 
have historically been addressed in approved exemptions and those that 
have not. The proposed planning standards within the levels are based 
on the current set of operating reactor EP standards informed by the 
analyses and considerations supporting a graded approach to EP as 
previously described, as well as public comments on the ANPR and on the 
draft regulatory basis for this rulemaking. The NRC also considered the 
criteria of safety, implementation costs, efficiency, transparency, 
flexibility, and responsiveness. The following discussion describes the 
proposed graded approach to EP.
Post-Shutdown Emergency Plan
    For a decommissioning site, once all the fuel is in the SFP, the 
spectrum of accidents that can have significant offsite consequences is 
greatly reduced and is dominated by the highly unlikely occurrence of a 
zirconium fire. The primary consideration for the planning basis for a 
PSEP is the potential consequences and timing of this narrow spectrum 
of accidents in relation to the time needed to initiate protective 
actions.
    From a regulatory perspective, the purpose of a PSEP is to provide 
a transition period to ensure that an appropriate level of EP is 
maintained onsite and offsite to respond to applicable DBAs and to 
ensure a prompt response to the highly unlikely rapid draindown of the 
SFP and subsequent zirconium fire and release occurring in less than 10 
hours. A nuclear power reactor licensee would be permitted to 
transition to a PSEP after the NRC's docketing of the licensee's 
certifications of permanent cessation of operations and permanent 
removal of fuel from the reactor vessel pursuant to Sec. Sec.  50.82 or 
52.110. The NRC anticipates that licensees will maintain a PSEP from 
the date that the NRC dockets the licensee's certifications of 
permanent cessation of operations and permanent removal of fuel from 
the reactor vessel, until the spent fuel has decayed for a period of at 
least 10 months (for BWRs) or 16 months (for PWRs) from the date of 
permanent cessation of operations, unless a different period is 
justified. During this time, the licensee would be relieved of the 
regulatory burden of requirements that are not needed to support an 
appropriate level of EP as preparations are made to implement a PDEP. 
The PSEP is a transition period for both onsite and offsite emergency 
planning in which the regulatory requirements for periodic updates, 
reviews, and audits that were necessary to support operating reactor EP 
programs should not interfere with efforts to establish an appropriate 
level of EP for a PDEP. The NRC does not intend for many significant 
changes to

[[Page 12270]]

occur to the emergency plan while the PSEP is used.
Permanently Defueled Emergency Plan
    For plants that have permanently shut down and defueled, the 
proposed EP approach is based primarily on conditions that: (1) A 
postulated radiological release would not exceed the EPA early-phase 
PAGs at the exclusion area boundary for DBAs applicable to a 
permanently shutdown and defueled reactor, and (2) sufficient time 
would exist to implement mitigative actions in response to a postulated 
zirconium fire beyond-design-basis accident scenario in the SFP and, if 
warranted, for offsite officials to initiate appropriate response 
actions using all-hazards planning to protect public health and safety. 
Because of the additional time available to take mitigative actions 
and, if necessary, to initiate protective actions, many requirements 
applicable under an operating reactor emergency plan or a PSEP would 
not be required to protect public health and safety and, therefore, 
would not be applicable to licensees with sufficiently decayed spent 
fuel under a PDEP.
    The NRC is proposing two regulatory alternatives to specify when 
the transition to a PDEP may occur: (1) After a specified amount of 
spent fuel decay time that starts from the date of permanent cessation 
of operations, or (2) after an alternative timeframe based on a site-
specific analysis that shows that the fuel in the SFP cannot heat up to 
zirconium fuel cladding ignition temperature (900 degrees C) within 10 
hours under adiabatic conditions. In either case, a licensee would be 
permitted to transition to a PDEP only after the NRC's docketing of the 
licensee's certifications of permanent cessation of operations and 
permanent removal of fuel from the reactor vessel pursuant to Sec.  
50.82 or Sec.  52.110. This proposed rule specifies an acceptable decay 
time to remove the requirement for licensees to provide a site-specific 
analysis. Licensees are provided the option to submit a site-specific 
analysis proposing an alternative decay period, but such an analysis 
would be subject to NRC review and approval before a transition to a 
PDEP.
Independent Spent Fuel Storage Installation-Only Emergency Plan
    The third level of decommissioning under the proposed rule would 
occur when all spent fuel is removed from the SFP and placed in dry 
cask storage. At this point, the licensee would have an ISFSI-only 
emergency plan, or IOEP. A licensee with all of its spent fuel in dry 
cask storage that terminates its 10 CFR part 50 or 10 CFR part 52 
license must first obtain a specific 10 CFR part 72 license. 
Accordingly, the licensee would then transition to the EP requirements 
for dry cask storage in Sec.  72.32, ``Emergency Plan.'' A licensee 
maintaining its 10 CFR part 50 or 10 CFR part 52 license may opt to 
change its EP program to align it with the requirements of Sec.  72.32 
once all spent fuel is transferred to dry cask storage. These two 
categories of licensees (i.e., 10 CFR part 72 specific licensees and 10 
CFR part 50 or 10 CFR part 52 licensees with ISFSIs licensed under the 
10 CFR part 72 general license) would be permitted to adopt an IOEP, 
consistent with the EP requirements that currently exist under Sec.  
72.32(a).
All Spent Fuel Removed From Site
    This proposed rule would allow a licensee to terminate its EP 
program once all the spent fuel has been permanently removed from the 
site, because the site no longer poses any risk of a radiological 
release from the spent fuel.
3. Licensee Supporting Analyses
    Decommissioning nuclear power reactor licensees submitting requests 
for exemptions under Sec.  50.12, ``Specific exemptions,'' from EP 
regulations have performed a series of supporting analyses for NRC 
review, as described in NSIR/DPR-ISG-02, ``Interim Staff Guidance: 
Emergency Planning Exemption Requests for Decommissioning Nuclear Power 
Plants'' (ADAMS Accession No. ML14106A057). To support the exemption 
requests, these analyses must demonstrate that: (1) Any radiological 
release for applicable DBAs (e.g., fuel handling accident in the spent 
fuel storage facility, waste gas system release, and cask handling 
accident if the cask handling system is not licensed as single-failure-
proof) would not exceed the limits of EPA PAGs at the exclusion area 
boundary, and (2) mitigation strategies and guidelines exist to provide 
an integrated response capability for beyond-design-basis events. In 
addition, licensees are required to demonstrate that, in the event of a 
complete loss of SFP water inventory with no heat loss (adiabatic 
heatup), a period of at least 10 hours would be available from the time 
all cooling is lost until any zirconium fuel cladding temperature 
reaches 900 degrees C.
    Under this proposed rule, the NRC would not require licensees to 
submit these analyses to the NRC for review and approval (separately 
from existing NRC oversight processes described later in this document) 
or to certify that these analyses have been completed to support a 
change between EP levels. The NRC anticipates that a licensee would 
analyze applicable DBAs using the process under Sec.  50.59 and reflect 
the analysis in the licensee's updated FSAR. The NRC expects that 
licensees have developed and maintained mitigation strategies for 
beyond-design-basis events as required by NRC Order EA-12-049. For the 
heatup analysis, the NRC has already performed analyses of 
representative PWR and BWR spent fuel to determine the decay time 
necessary for the fuel to remain below clad ignition temperature for at 
least 10 hours assuming adiabatic heatup conditions. These analyses 
contain numerous conservatisms, such that the decay times specified in 
the rule would bound the decay time required for plants with fuel 
assemblies from the final offload to the spent fuel pool with burnup 
less than 72 GWd/MTHM and zirconium cladding to attain the 10-hour 
criterion. This particular analysis supports a transition to PDEP 
requirements, as previously described. The NRC is proposing an option 
to allow licensees to develop their own site-specific analysis for this 
transition time; however, licensees would need to submit such analyses 
to the NRC for review and approval. This proposed rule details that 
process.
    The following sections describe the proposed EP planning standards 
and requirements for each graded level of EP (i.e., PSEP, PDEP, and 
IOEP) under proposed Sec. Sec.  50.54(q) and 50.200, ``Power reactor 
decommissioning emergency plans.'' The NRC is issuing draft Regulatory 
Guide (DG) DG-1346, ``Emergency Planning for Decommissioning Nuclear 
Power Reactors'' (ADAMS Accession No. ML21347A046), for public comment 
with this proposed rule that includes guidance on one method acceptable 
to the NRC for complying with these proposed requirements. This 
regulatory guide will supersede NSIR/DPR-ISG-02 upon publication of the 
final rule. This proposed rule contains a risk-informed, consequence-
oriented, graded approach to EP for decommissioning sites that 
maintains the defense-in-depth philosophy and provides reasonable 
assurance that adequate protective measures can and will be taken in 
the event of a radiological emergency.
4. Post-Shutdown Emergency Plans
    The NRC is proposing in Sec.  50.54(q)(7) that a licensee can 
transition to a PSEP after the NRC's docketing of the licensee's 
certifications of permanent

[[Page 12271]]

cessation of operations and permanent removal of all fuel from the 
reactor vessel pursuant to Sec. Sec.  50.82(a)(1) or 52.110(a). A PSEP 
provides a transition period from the EP requirements for an operating 
reactor to the PDEP requirements under proposed Sec.  50.200(b) and 
(c). The NRC is proposing regulations under new Sec.  50.200(a) that 
would clarify how the planning standards in Sec.  50.47(b) and 
requirements in appendix E to 10 CFR part 50 apply to a nuclear power 
reactor licensee's PSEP.
PSEP Staffing and Emergency Response Organization
    Currently, the following regulations govern the staffing of the 
emergency response organization (ERO):
    <bullet> Section 50.47(b)(1), which states, in part, ``Primary 
responsibilities for emergency response by the nuclear facility . . . 
have been assigned . . . and each principal response organization has 
staff to respond and to augment its initial response on a continuous 
basis.''
    <bullet> Section 50.47(b)(2), which states, in part, ``[A]dequate 
staffing to provide initial facility accident response in key 
functional areas is maintained at all times, timely augmentation of 
response capabilities is available. . . .''
    <bullet> Appendix E to 10 CFR part 50, paragraph IV.A, which 
states, in part, ``The organization for coping with radiological 
emergencies shall be described, including definition of authorities, 
responsibilities, and duties of individuals assigned to the licensee's 
emergency organization. . . .''
    This proposed rule would allow a licensee transitioning to a PSEP 
to revisit staffing levels and the staffing analysis for the ERO 
performed under paragraph IV.A.9 of appendix E to 10 CFR part 50 to 
align staffing with the reduced spectrum of credible accidents for a 
permanently shutdown and defueled nuclear power reactor facility. The 
proposed requirement in Sec.  50.200(a) would acknowledge that the 
spectrum of credible accidents requiring a response from the ERO at a 
facility that is permanently shutdown and defueled is reduced as 
compared to that for an operating plant. The principal public safety 
concern involves the potential radiological risks associated with the 
storage of spent fuel on site in the SFP. For example, the reactor, 
reactor coolant system, and reactor support systems are no longer in 
operation and have no function related to the storage of spent fuel. 
Therefore, postulated accidents involving a failure or malfunction of 
these systems are no longer applicable. As such, certain ERO positions 
and emergency functions as detailed in NUREG-0654/FEMA-REP-1, Revision 
2, Table B-1, ``Emergency Response Organization (ERO) Staffing and 
Augmentation Plan,'' may not be applicable or necessary under a PSEP. 
Commensurate with the reduced spectrum of credible accidents, proposed 
Sec.  50.200(a) would allow licensees to change ERO staffing levels 
required by existing Sec.  50.47(b)(2) within their PSEPs. Reductions 
in facility staffing may be made as long as the facility operates with 
no loss of necessary EP functions and the reductions have no impact on 
the formal offsite radiological emergency response plans that are in 
effect. In conjunction with this proposed rule, the NRC is issuing for 
public comment DG-1346, which provides guidance on ERO capabilities to 
be maintained at facilities with PSEPs when reducing staffing levels.
PSEP Emergency Action Levels
    Currently, appendix E to 10 CFR part 50, paragraph IV.C requires 
licensees to develop a set of emergency action levels (EALs) based not 
only on onsite and offsite radiation monitoring information but also on 
readings from a number of sensors that indicate a potential emergency, 
such as the pressure in containment and the response of the emergency 
core cooling system. This proposed rule would allow licensees 
transitioning to a PSEP to revise EALs consistent with the profile of a 
permanently shutdown and defueled nuclear power reactor. Proposed Sec.  
50.54(q)(8)(iii) would state that changes to EALs resulting from 
changes in plant conditions due to the transition to decommissioning 
would not be reductions in effectiveness provided that the evaluation 
under Sec.  50.54(q)(3) demonstrates that the changes do not reduce the 
capability of the licensee to take timely and appropriate protective 
actions. Given the defueled nature of facilities in decommissioning, 
EALs associated with nuclear power reactor operations (e.g., reactor 
vessel water level, core temperature, and containment radiation levels) 
and EALs for mitigation systems not associated with the SFP would no 
longer contain applicable initiating conditions. Containment parameters 
do not indicate the conditions relevant to EP at a defueled facility, 
and emergency core cooling systems would no longer be required. Other 
indications such as SFP level or temperature can be used at sites that 
have spent fuel in the SFPs. Consistent with existing requirements, 
licensees transitioning to a PSEP would still be required to maintain a 
set of EALs based on onsite radiation monitoring information and in-
plant conditions and instrumentation applicable to EP for a defueled 
reactor.
    Guidance document NEI 99-01, Revision 6, ``Development of Emergency 
Action Levels for Non-Passive Reactors'' (ADAMS Accession No. 
ML12326A805), provides EALs for non-passive operating nuclear power 
reactors, permanently defueled reactors, and ISFSIs. The NRC found NEI 
99-01, Revision 6, acceptable for use in a letter dated March 28, 2013 
(ADAMS Accession No. ML12346A463). To accompany this proposed rule, the 
NRC drafted guidance in Attachment 1 of Appendix A in DG-1346, for how 
a permanently shutdown and defueled nuclear power reactor facility 
could make a partial EAL scheme change. Notwithstanding the proposed 
changes to Sec.  50.54(q), a licensee desiring to change its entire EAL 
scheme must receive prior NRC approval in accordance with appendix E to 
10 CFR part 50, paragraph IV.B.2.
PSEP Evacuation Time Estimate Studies
    Appendix E to 10 CFR part 50, paragraph IV.3 requires licensees to 
use evacuation time estimates (ETEs) in the formulation of protective 
action recommendations (PARs) and to provide the ETEs to State and 
local governmental authorities for use in developing offsite protective 
action strategies. Licensees must update ETEs on a periodic basis in 
accordance with the requirements in Sec.  50.47(b)(10) and appendix E 
to 10 CFR part 50, paragraphs IV.4, IV.5, and IV.6. The periodicity of 
these updates together with time needed to develop and implement the 
resulting protective action strategies may exceed the expected 
transition period covered by PSEPs. Therefore, the NRC is proposing to 
add a new paragraph IV.8 to appendix E to 10 CFR part 50 to clarify 
that the ETE requirements of paragraphs IV.4, IV.5, and IV.6 would no 
longer be applicable to licensees after permanent cessation of 
operations and permanent removal of fuel from the reactor vessel. 
Existing ETE analyses would remain effective within the emergency plan 
until no longer required for licensees with PDEPs.
    Under proposed Sec.  50.54(q)(7)(ii), a licensee transitioning to a 
PSEP would need to maintain a PSEP from the date that the NRC dockets 
the licensee's certifications of permanent cessation of operations and 
permanent removal of fuel from the reactor vessel, until the spent fuel 
has decayed for a period of at least 10 months (for BWRs) or 16 months 
(for PWRs) from the date of permanent cessation of operations for

[[Page 12272]]

burnups less than 72 GWd/MTHM, unless an alternative spent fuel decay 
period is proposed by the licensee and approved by the NRC. For fuel 
with burnups greater than 72 GWd/MTHM or non-zirconium cladding, an 
alternative spent fuel decay period would be proposed by the licensee 
for approval by the NRC under Sec.  50.54(q)(7)(ii). Updates to the ETE 
during this level of decommissioning would provide limited benefit for 
the enhancement of protective action strategies or offsite evacuation 
planning. Even if the criteria for updating the ETE analysis were met 
within the timeframe for a PSEP, updating an ETE report may take 
several months of analysis. After the ETE is updated, the regulations 
in appendix E to 10 CFR part 50, paragraph IV.6 require an additional 
180 days before an updated ETE can be used to inform PARs and offsite 
protective action strategies. The additional time and effort needed to 
develop and implement a revised protective action strategy may exceed 
the time that a facility would spend with a PSEP before transitioning 
to a PDEP. Based on the NRC's review of submitted ETEs, population 
changes within a period comparable to the post-shutdown timeframe are 
unlikely to impact ETEs enough to affect the formulation of protective 
action strategies. In addition, because licensees with PDEPs would not 
be required to have preplanned PARs to provide for a prompt response to 
a radiological emergency, updates to the ETE post-shutdown would 
provide no significant benefit.
PSEP Annual Dissemination of Public Information
    Appendix E to 10 CFR part 50, paragraph IV.D.2 currently requires 
licensees to make an annual dissemination of basic emergency planning 
information to the public within the plume exposure pathway EPZ. 
Section II.G of NUREG-0654/FEMA-REP-1, Revision 2, contains criteria 
for the information that should be included in the annual dissemination 
of public information, including educational information on radiation, 
points of contact, protective measures, and information for special 
needs populations. The NRC is not proposing changes related to the 
requirement for an annual dissemination of public information for a 
PSEP because the change in the plant's operating status and the ensuing 
changes to the EP program would be appropriate information to 
communicate to the public. However, consistent with the removal of 
regulatory standards for offsite radiological emergency plans for 
decommissioning sites (including the removal of EPZ requirements) as 
discussed later in this document, licensees with PDEPs would not be 
required to provide annual disseminations of information to the public. 
In DG-1346, the NRC provides guidance on one method acceptable to the 
NRC for a final dissemination of information to the public for 
licensees with PSEPs.
PSEP Hostile Action
    In the 2011 final rule, ``Enhancements to Emergency Preparedness 
Regulations'' (76 FR 72559; November 23, 2011) (2011 EP Final Rule), 
the NRC amended its regulations to include enhancements to EP in 
response to a hostile action event. Appendix E to 10 CFR part 50, 
paragraph IV.A.7 defines ``hostile action'' as an act directed toward a 
nuclear power plant or its personnel that includes the use of violent 
force to destroy equipment, take hostages, and/or intimidate the 
licensee to achieve an end. Appendix E to 10 CFR part 50, paragraph 
IV.B.1 requires nuclear power reactor licensees to have EALs for 
hostile action, paragraph IV.E.8.d requires nuclear power reactor 
licensees to have alternative facilities that would be accessible even 
if the site is under threat of or experiencing hostile action for the 
staging of ERO personnel, paragraph IV.l requires nuclear power reactor 
licensees to develop protective actions to protect onsite personnel 
during hostile action, and paragraph IV.F.2.c.4 and paragraph IV.F.2.i 
require nuclear power reactor licensees to have hostile action 
scenarios in drills and exercises. These EP requirements related to 
hostile action are separate and distinct from the physical protection 
regulations in 10 CFR part 73, ``Physical Protection of Plants and 
Materials.''
    The NRC is proposing to maintain EP requirements related to hostile 
action for nuclear power reactor licensees transitioning to a PSEP. 
Spent fuel at a nuclear power reactor facility that has a PSEP has not 
yet undergone a significant period of decay, necessitating the 
maintenance of formal offsite radiological emergency planning. The 
potential consequences and timing of an accident are the primary 
considerations for the EP planning basis at nuclear power reactor 
facilities transitioning to a PSEP. Although NUREG-1738 did not 
evaluate the potential consequences of a sabotage event that could 
directly cause offsite fission production dispersion, the NRC did study 
the potential consequences of the zirconium fire event at different 
spent fuel decay times. Within the timeframe proposed for nuclear power 
reactor facilities transitioning to a PSEP, the study in NUREG-1738 
shows that decay time is significant when considering short-term 
radiological consequences. Additionally, maintaining EP requirements 
related to hostile action during this transitional (and time-limited) 
level of decommissioning would help both the licensee and offsite 
response organizations (OROs) avoid immediate significant changes to 
the onsite and offsite emergency plans.
PSEP Drills and Exercises
    Current regulations in appendix E to 10 CFR part 50, paragraph IV.F 
and Sec.  50.47(b)(14) include requirements for periodic drills and 
exercises for nuclear power reactor licensees. Proposed paragraph 
IV.F.2.k would require licensees to follow the biennial exercise 
requirements of appendix E, paragraph IV.F.2 once the NRC dockets the 
licensee's certifications required under Sec.  50.82(a)(1) or Sec.  
52.110(a). After the NRC dockets this certification, exercise scenarios 
would be reduced commensurate with the permanent cessation of 
operations and permanent removal of fuel from the reactor vessel to 
reflect a smaller suite of potential accident scenarios.
    Current regulations in appendix E to 10 CFR part 50, paragraph 
IV.F.2.c require that offsite radiological emergency plans for each 
site be exercised biennially with full participation by each offsite 
authority having a role under the radiological emergency plan. Proposed 
paragraph IV.F.2.k would provide that biennial exercises of offsite 
emergency plans would be required after the NRC dockets a licensee's 
certifications under Sec.  50.82(a)(1) or Sec.  52.110(a) until 
transition to a PDEP.
    However, a licensee that conducts a full participation biennial 
exercise just prior to the NRC docketing the licensee's certifications 
required under Sec.  50.82(a)(1) or Sec.  52.110(a) may not be required 
to conduct another exercise before transitioning to a PDEP. If an 
exercise is conducted as part of the 8-year exercise cycle, as required 
under appendix E to 10 CFR part 50, paragraph IV.F.2.j, after the NRC 
dockets the licensee's certifications required under Sec.  50.82(a)(1) 
or Sec.  52.110(a), but prior to transitioning to a PDEP, the scenario 
would reflect actual plant conditions.
PSEP Emergency Response Data Systems
    Appendix E to 10 CFR part 50, section VI, ``Emergency Response Data 
System,'' outlines a set of system, testing, and

[[Page 12273]]

implementation requirements for the emergency response data system 
(ERDS). These systems transmit near-real-time electronic data directly 
between the licensee's onsite computer system and the NRC Operations 
Center. Nuclear power facilities that are shutdown permanently or 
indefinitely are currently not required to provide hardware to 
interface with the NRC receiving system under appendix E to 10 CFR part 
50, paragraph VI.2, and the NRC is not proposing any regulatory changes 
to section VI beyond minor corrections (see ``Clean-up of Regulations'' 
section in this document). Under Sec.  50.72, ``Immediate notification 
requirements for operating nuclear power reactors,'' licensees with 
PSEPs would maintain a capability to provide meteorological, 
radiological, and SFP data (e.g., level, flow, and temperature data) to 
the NRC within a reasonable timeframe following an event.
5. Permanently Defueled Emergency Plans
    Proposed Sec.  50.54(q)(7)(ii) describes the timeframe after which 
a licensee would be permitted to transition to a PDEP. As discussed in 
the ``Technical Basis for Graded Approach'' section of this document, 
the NRC concluded that after a decay period of 10 months (for BWRs) or 
16 months (for PWRs), the spent fuel cannot reasonably heat up to the 
zirconium fuel cladding ignition temperature within 10 hours. 
Therefore, the NRC is proposing that a licensee can transition to a 
PDEP after the NRC's docketing of the licensee's certifications of 
permanent cessation of operations and permanent removal of all fuel 
from the reactor vessel pursuant to Sec. Sec.  50.82(a)(1) or 52.110(a) 
and when at least 10 months (for BWR) or 16 months (for PWR) have 
elapsed since the date of permanent cessation of operations.
    Proposed Sec.  50.54(q)(7)(ii) would also allow licensees to submit 
an analysis for NRC approval demonstrating that an alternative spent 
fuel decay period would ensure that spent fuel would not heat up to 900 
degrees C in less than 10 hours under adiabatic conditions. Under the 
proposed rule, licensees would be required to submit this analysis 
under Sec.  50.90 and the analysis would need to be approved by the NRC 
in order for a licensee to transition to a PDEP in less than 10 months 
(for a BWR) or 16 months (for a PWR). While the NRC's research 
conducted to inform this proposed rule supports a required decay period 
of 10 months (for BWRs) or 16 months (for PWRs), it is possible that a 
licensee may be able to demonstrate, based on site-specific conditions, 
that a shorter decay period would still ensure that spent fuel cannot 
reasonably heat up to the zirconium fuel cladding ignition temperature 
within 10 hours; therefore, the NRC is allowing for the flexibility to 
submit an alternative decay period under proposed Sec.  
50.54(q)(7)(ii). The NRC is issuing DG-1346 for public comment in 
conjunction with this proposed rule; DG-1346 provides one method 
acceptable to the NRC for conducting the spent fuel heatup analysis.
    As demonstrated in the results of the NRC's task analysis of 
mitigation actions, ``A Human Reliability Analysis of the Spent Fuel in 
the Spent Fuel Pool of Decommissioning Nuclear Plants'' (ADAMS 
Accession No. ML16110A432), a period of 10 hours will provide 
sufficient time for plant staff to implement mitigation strategies to 
prevent spent fuel heatup damage. Additionally, as noted in the NRC's 
analysis, ``Offsite Dose Accumulation Rates Following a Hypothetical 
Spent Fuel Pool Accident'' (ADAMS Accession No. ML16110A430), even in 
the event of a highly unlikely beyond-design-basis accident leading to 
a rapid draindown of the SFP and subsequent zirconium fire, there may 
be an additional time margin of several hours beyond the 10-hour heatup 
time during which protective actions can be taken to protect the public 
before the dose levels associated with EPA PAGs would be exceeded 
offsite. Because of the additional time available to take mitigation 
actions and, if necessary, to initiate protective actions, many 
requirements applicable to licensees with PSEPs would not be applicable 
to licensees with sufficiently decayed spent fuel (i.e., licensees with 
PDEPs). The following discussion addresses the planning standards under 
proposed Sec.  50.200(b) and requirements under proposed Sec.  
50.200(c) that would be necessary to adequately protect public health 
and safety at facilities with PDEPs. The proposed requirements for 
facilities with PDEPs are consistent with the guidance contained in 
NSIR/DPR-ISG-02.
Offsite Radiological Emergency Response Plans
    Currently, Sec.  50.47(b) applies to both onsite and offsite 
radiological emergency response plans, and appendix E to 10 CFR part 50 
includes requirements for emergency plans to address offsite emergency 
response capabilities (e.g., public alert and notification systems, 
offsite PAR development, ETEs, and exercises of offsite emergency 
plans). Under this proposed rule, NRC planning standards would no 
longer be applied to offsite radiological emergency response plans for 
plants with PDEPs.
    In its review of several exemption requests, the NRC concluded that 
as long as a period of at least 10 hours is available to implement 
mitigation measures or initiate appropriate response actions offsite, 
formal offsite radiological emergency plans, required under 10 CFR part 
50, are not necessary for permanently shutdown and defueled nuclear 
power reactor licensees with a PDEP. In a hypothetical SFP accident 
scenario, 10 hours is a conservative estimate of the amount of time 
available to implement mitigation measures or to take other appropriate 
response actions. The 10 hours assumes that the spent fuel begins to 
heat up immediately after the initiating event occurs and does not 
include the expected amount of time it would take for water to drain 
from the pool. A beyond-design-basis accident that results in the water 
draining from the pool (whether a full or partial draindown) would 
likely take much longer than 10 hours because of the robust 
construction of the SFP and the large volume of water in the SFP, 
delaying the onset of heatup. Additionally, 10 hours is a conservative 
period of time during which preplanned mitigation measures to provide 
makeup water or spray to the SFP can be implemented reliably before the 
onset of a zirconium cladding ignition.
    If a release is projected to occur, 10 hours would be sufficient 
time for licensees to notify offsite agencies and for these agencies to 
initiate appropriate action to protect public health and safety. The 
NRC concludes that 10 hours provides ample time to take appropriate 
actions without the extensive preplanning and other requirements of the 
EP framework for operating plants, and, therefore, regulatory standards 
for offsite radiological emergency plans would no longer be necessary 
for the adequate protection of public health and safety. Licensees with 
PDEPs would still maintain a variety of onsite capabilities that may be 
available to support OROs in EP and response, including radiological 
training; regular coordination with OROs; radiological assessment 
capabilities; memoranda of understanding for firefighting, law 
enforcement, and ambulance/medical services; and the ability to make 
PARs upon request. For licensees with PDEPs, no action would be 
expected or required from State or local government organizations in 
response to an event at a decommissioning site other than firefighting, 
law enforcement, and ambulance/medical services. Requirements for 
licensees to maintain agreements for these services also exist

[[Page 12274]]

outside of radiological EP, including the requirement for licensees to 
maintain a fire protection plan in Sec.  50.48, ``Fire protection,'' 
and physical security requirements in 10 CFR part 73. Since the 
requirements of Sec.  50.47(b) continue to apply to offsite 
radiological emergency plans during decommissioning, the NRC is 
proposing to add Sec.  50.47(f) to clarify when the 16 planning 
standards in Sec.  50.47(b) no longer apply to offsite radiological 
emergency plans.
PDEP Staffing and Emergency Response Organization
    Currently, Sec.  50.47(b)(1) and (2) and paragraph IV.A of appendix 
E to 10 CFR part 50 require licensees to maintain adequate staffing for 
initial and augmented response in the case of an emergency and to 
describe ERO responsibilities in their emergency plans. Further, 
appendix E to 10 CFR part 50, paragraph IV.A.9 requires licensees to 
conduct a detailed staffing analysis demonstrating that on-shift 
personnel assigned emergency plan implementation functions are not 
assigned responsibilities that would prevent the timely performance of 
their assigned functions as specified in the emergency plan.
    Proposed Sec.  50.200(b)(1), (b)(2), and (c)(1)(i) would include 
similar staffing requirements for licensees with PDEPs, with the 
exception of changes made to reflect the small staffing levels required 
at a decommissioning facility and the removal of formal offsite 
radiological emergency response requirements for licensees with PDEPs. 
For example, licensees with PDEPs would not have to comply with the 
requirement under appendix E to 10 CFR part 50, paragraph IV.A.3 to 
augment the ERO with staff from licensee headquarters. Because of the 
much lower risk and much slower progression of events as compared to 
operating plants, decommissioning sites typically have a level of 
emergency response that does not require response by headquarters 
personnel. Licensees would not have to identify State and/or local 
officials responsible for protective actions, as currently required 
under appendix E to 10 CFR part 50, paragraph IV.A.8 because offsite 
emergency measures are limited to onsite support provided by local 
police, fire departments, and ambulance and hospital services, as 
appropriate. Proposed Sec.  50.200(c)(1)(i) would require licensees 
with PDEPs to include in their emergency plans plant staff emergency 
assignments.
    In addition, the staffing analysis required under appendix E to 10 
CFR part 50, paragraph IV.A.9 would no longer apply to licensees with 
PDEPs. In the 2011 EP Final Rule, the NRC concluded that the staffing 
analysis requirement was not necessary for non-power reactor licensees 
because of the small staffing levels required for those facilities. For 
this same reason, licensees with PDEPs would no longer be required to 
perform this analysis under the proposed rule.
    As licensees transition to a PDEP, staffing levels may be reduced 
but must remain commensurate with the need to safely store spent fuel 
at the facility in a manner that is protective of public health and 
safety. The NRC is issuing DG-1346 for public comment in conjunction 
with this proposed rule; DG-1346 provides guidance on ERO staffing 
levels for a PDEP. Licensees with PDEPs would need to be able to 
augment on-shift capabilities within two hours after declaration of an 
emergency. The augmented staff would need to include engineering 
capability appropriate for SFP accident mitigation, but may otherwise 
be reduced.
    Currently, a licensee is required to maintain staffing levels at 
its technical support center (TSC), operational support center (OSC), 
and emergency operations facility (EOF). In accordance with NUREG-0696, 
``Functional Criteria for Emergency Response Facilities'' (ADAMS 
Accession No. ML051390358), a TSC is an onsite facility located close 
to the control room that provides plant management and technical 
support to the reactor operating personnel located in the control room 
during emergency conditions; the OSC is an onsite area separate from 
the control room and the TSC where licensee operations support 
personnel will assemble in an emergency; and an EOF is an offsite 
support facility for the management of overall licensee emergency 
response (including coordination with Federal, State, and local 
officials), coordination of radiological and environmental assessments, 
and determination of recommended public protective actions. Because of 
the low probability of DBAs or other credible events that would be 
expected to exceed the EPA PAGs offsite and the available time to 
implement mitigation measures consistent with plant conditions and, if 
necessary, to initiate response actions, licensees with PDEPs would not 
need to maintain the TSC, OSC, and EOF designated staff or dedicated 
offsite dose assessment field teams.
PDEP Emergency Classification Levels and Emergency Action Levels
    Currently, Sec.  50.47(b)(4) and appendix E to 10 CFR part 50, 
paragraphs IV.B and IV.C specify the EAL and emergency classification 
level (ECL) requirements for operating reactors. Similar to Sec.  
50.47(b)(4), the proposed PDEP planning standard under Sec.  
50.200(b)(4) would require licensees with PDEPs to establish a standard 
ECL and EAL scheme, the bases of which would include facility system 
and effluent parameters. The NRC is proposing EAL and ECL requirements 
for licensees with PDEPs that are analogous to appendix E to 10 CFR 
part 50, paragraphs IV.B and IV.C with the exceptions of the 
requirements to base EALs on offsite monitoring information and the 
appendix E to 10 CFR part 50 paragraph IV.B.1 requirement to include 
hostile action-based EALs. Because licensees with PDEPs would not be 
required to maintain formal offsite radiological emergency response 
plans and ``hostile action'' does not apply (see discussion in ``PDEP 
Hostile Action'' and ``Offsite Radiological Emergency Response Plans'' 
sections in this document), these requirements are no longer relevant 
to these facilities. However, EALs for security-based events would 
still be required.
    Under proposed Sec.  50.200(c)(1)(ii)(A), licensees with PDEPs 
would continue to be required to describe in their emergency plans the 
EALs that are used as a criterion for determining the need for 
notification and participation of governmental agencies and the EALs 
that are used for determining when and what protective measures should 
be considered within the site boundary to protect public health and 
safety. In addition, licensees with PDEPs would be required to review 
EALs with State and local governmental authorities on an annual basis. 
Under proposed Sec.  50.200(c)(1)(iii)(A), licensees with PDEPs would 
continue to be required to describe in their emergency plans the 
spectrum of emergency conditions that involve the alerting or 
activating of the total emergency organization, the communication steps 
to be taken to alert or activate personnel, EALs for notification of 
offsite agencies, and the existence of a message authentication scheme. 
Under proposed Sec.  50.200(c)(1)(ii)(B), a licensee desiring to make 
an EAL scheme change as part of the PDEP must follow the requirements 
of appendix E to 10 CFR part 50, paragraph IV.B.2.
    For facilities with PDEPs, proposed Sec.  50.200(c)(1)(iii)(A) 
would specify that only the ECLs of Notification of Unusual Event and 
Alert would apply (and not the ECLs of Site Area Emergency and General 
Emergency, which apply to operating reactors). For these facilities, 
the probability of a condition reaching the level above an emergency

[[Page 12275]]

classification of Alert is very low. In the event of an accident at a 
facility with a PDEP, time will be available to implement mitigation 
measures consistent with plant conditions. As stated in NUREG-1738, 
small SFP leaks or loss of cooling scenarios evolve very slowly and 
generally leave many days for recovery efforts. Offsite radiation 
monitoring would be performed as the need arises. Because of the low 
probability of DBAs or other credible events that would reasonably be 
expected to exceed the EPA PAGs and the available time to implement 
mitigation measures consistent with plant conditions and, if necessary, 
to initiate appropriate response actions offsite, facilities with PDEPs 
would not require declarations of Site Area Emergency and General 
Emergency and the associated offsite radiation monitoring systems. The 
results from the NRC's analyses previously discussed support this 
conclusion.
    Consistent with the discussion on PSEPs, EALs for nuclear power 
reactor operations (e.g., reactor vessel water level, core temperature, 
and containment radiation levels) and EALs related to mitigation 
systems not associated with the SFP would no longer be applicable for 
facilities with PDEPs. The NRC is issuing DG-1346 for public comment in 
conjunction with this proposed rule; DG-1346 provides one method 
acceptable to the NRC for EALs for facilities with PDEPs. As discussed 
previously, proposed Sec.  50.54(q)(8)(iii) describes requirements for 
decommissioning licensees to conduct reduction in effectiveness 
determinations for EAL schemes.
PDEP Emergency Assessment, Classification, and Declaration
    Currently, appendix E to 10 CFR part 50, paragraph IV.C.2 requires 
licensees to maintain the capability to assess, classify, and declare 
an emergency condition within 15 minutes. A decommissioning nuclear 
power reactor has a low likelihood of a design-basis accident or other 
credible event resulting in radiological releases requiring offsite 
protective measures, and the event progression is much slower compared 
to that for operating reactors. For these reasons, under this proposed 
rule licensees with PDEPs would not be required to assess, classify, 
and declare an emergency condition within 15 minutes. Instead, the NRC 
is proposing under Sec.  50.200(c)(1)(iii)(B) that licensees with PDEPs 
must document and maintain the capability to assess, classify, and 
declare an emergency condition as soon as possible and within 60 
minutes after the availability of indications that an EAL has been 
exceeded and must promptly declare the emergency condition as soon as 
possible following identification of the appropriate ECL. Similar to 
the requirements in appendix E to 10 CFR part 50, paragraph IV.C, 
proposed Sec.  50.200(c)(1)(iii)(B) would clarify that PDEP licensees 
must not treat the timeframe as a grace period or delay the 
implementation of response actions. The 60-minute timeframe is 
commensurate with the slower progression of a credible event resulting 
in a radiological release requiring offsite protective measures (see 
discussion of the timeframe for potential releases and mitigation 
actions at decommissioning sites in the section ``Permanently Defueled 
Emergency Plans'' in this document).
PDEP Notification Requirement to State and Local Governmental Agencies
    Currently, appendix E to 10 CFR part 50, paragraph IV.D.3 requires 
licensees to have the capability to notify OROs of an emergency 
declaration within 15 minutes. Under proposed Sec.  
50.200(c)(1)(iv)(B), licensees with PDEPs would be required to promptly 
notify State and local governmental agencies and to make this 
notification as soon as possible and within 60 minutes after declaring 
an emergency. The NRC's research and analysis shows that licensees with 
PDEPs would have sufficient time to implement mitigation measures 
consistent with plant conditions and, if necessary, for OROs to 
initiate protective actions offsite. Notifying OROs as soon as possible 
and within 60 minutes after declaring an emergency would not 
significantly impact the time available for OROs to initiate 
appropriate response actions.
PDEP Public Alert and Notification Systems
    Currently, appendix E to 10 CFR part 50, paragraph IV.D.3 requires 
licensees to demonstrate that appropriate governmental authorities have 
the capability to make a decision on alerting and notifying the public 
promptly on being informed of an emergency condition. Because of the 
low probability of DBAs or other credible events that would be expected 
to exceed the limits of EPA PAGs offsite and the available time for 
event mitigation, under this proposed rule, the public alert and 
notification system specified in appendix E to 10 CFR part 50, 
paragraph IV.D.3 would not be required for licensees with PDEPs. 
Similarly, exercises of this system, as required under appendix E to 10 
CFR part 50, paragraph IV.F.2, would no longer be required for 
licensees with PDEPs. As previously discussed, licensees with PDEPs 
would still be required to maintain the capability to notify 
responsible State and local governmental agencies within 60 minutes 
after declaring an emergency, and, based on research and analysis 
showing that there would be at least 10 hours prior to a zirconium fuel 
cladding fire for licensees with PDEPs, sufficient time would be 
available for appropriate governmental authorities to inform the public 
and initiate protective actions, if necessary. Such actions would be 
within the capabilities of offsite response organizations and would be 
similar to actions required for other hazards that do not require a 
dedicated hazard-specific offsite response capability as is the case 
for operating reactors.
PDEP Emergency Planning Zones
    Currently, Sec.  50.47(b) and (c)(2) require licensees to conduct 
emergency planning for both the shorter-term plume exposure pathway EPZ 
(generally 10 miles) and the longer-term ingestion exposure pathway EPZ 
(generally 50 miles). Appendix E to 10 CFR part 50 contains additional 
emergency planning requirements for these two types of EPZs. However, 
the maintenance of the plume exposure pathway and ingestion exposure 
pathway EPZs for licensees with PDEPs is not warranted because of the 
low probability of DBAs or other credible events that would be expected 
to exceed the EPA PAGs off site and the available time to implement 
mitigation measures. Additionally, if necessary, sufficient time would 
be available for OROs to initiate appropriate response actions even for 
a highly unlikely severe accident. Therefore, consistent with the NRC's 
determination to not require the establishment of formal offsite 
radiological emergency response plans for licensees with PDEPs, the NRC 
is proposing to eliminate the requirements that EPZs be maintained for 
licensees with PDEPs. In other words, the plume exposure pathway EPZ 
for licensees with PDEPs does not exceed the site area boundary. 
Consequently, the planning standards for PDEPs under proposed Sec.  
50.200(b) and the requirements under proposed Sec.  50.200(c) do not 
include references to the EPZs.
    The NRC is also proposing to add a new paragraph (f) to Sec.  50.47 
that would clarify that the planning standards of Sec.  50.47(b) do not 
apply to offsite radiological emergency response plans if the 
licensee's emergency plan is not required to meet these planning 
standards or if the plume exposure

[[Page 12276]]

pathway EPZ does not exceed the site area boundary.
PDEP Offsite Radiological Protective Action Recommendations
    Currently, Sec.  50.47(b) requires licensees to develop a range of 
protective actions for the plume exposure pathway EPZ for emergency 
workers and the public and to give consideration to evacuation, 
sheltering, and the use of potassium iodide. Licensees also must 
develop and put in place guidelines for the choice of protective 
actions during an emergency and develop protective actions for the 
ingestion exposure pathway EPZ. Proposed Sec.  50.200(b)(10) would 
require licensees with PDEPs to continue to develop a range of 
protective actions for emergency workers and the public but, consistent 
with the removal of regulatory standards for offsite radiological EP 
for these licensees, would not reference specific offsite protective 
actions or pre-planned activities for the public in the EPZs. The 
proposed requirement would call for protective actions directed at 
emergency workers who may have to respond to the decommissioning site 
for firefighting, law enforcement, and ambulance/medical services and 
members of the public present within the owner-controlled area during a 
radiological emergency.
    For licensees with PDEPs, pre-planned offsite protective actions to 
ensure a prompt response to a radiological emergency on site are not 
necessary given the time available for OROs to initiate appropriate 
response actions. Although the likelihood is low for events that would 
result in doses in excess of the EPA PAGs to the public beyond the 
owner-controlled area boundary based on the permanently shutdown and 
defueled status of the reactor, the proposed rule would require 
licensees with PDEPs to determine the magnitude of and continually 
assess the impact of a radiological release under proposed Sec.  
50.200(c)(1)(ii)(A), and, if a release is occurring, the licensee would 
be required to communicate that information to offsite authorities as 
soon as possible for their consideration in taking appropriate response 
actions under proposed Sec.  50.200(c)(1)(iv)(B).
    In 2001, the NRC revised its EP regulations through the 
``Consideration of Potassium Iodide in Emergency Plans'' (66 FR 5427; 
January 19, 2001) final rule to include the consideration of potassium 
iodide as a protective measure for the general public to supplement 
sheltering and evacuation in the unlikely event of a severe nuclear 
power plant accident with an offsite radioactive plume that would 
include radioactive iodine. For licensees with PDEPs, in addition to 
not needing pre-planned protective action strategies, the iodine in the 
spent fuel has decayed sufficiently such that there is no need to 
consider a supplemental potassium iodide program to counteract the 
effects of radioactive iodine on the thyroid.
PDEP Evacuation Time Estimate Studies
    Currently, licensees are required to develop and update ETEs in 
accordance with the requirements in Sec.  50.47(b) and appendix E to 10 
CFR part 50, paragraph IV.3. Paragraph IV.3 requires licensees to use 
ETEs in the formulation of PARs and to provide ETEs to State and local 
governmental authorities for use in developing offsite protective 
action strategies. Because of the low probability of DBAs or other 
credible events that would be expected to exceed the limits of EPA PAGs 
offsite and the available time for event mitigation, as well as the 
minimal expected offsite response required, the proposed rule would not 
require licensees with PDEPs to maintain ETEs (see section ``PSEP 
Evacuation Time Estimate Studies'' in this document for additional 
discussion regarding the need for ETEs post-shutdown).
PDEP Emergency Facilities and Equipment
    Currently, appendix E to 10 CFR part 50, paragraph IV.E requires 
licensees to maintain and describe adequate provisions for emergency 
facilities and equipment, including equipment at the site for personnel 
monitoring, equipment for radiological assessment, facilities and 
supplies for decontaminating onsite individuals, first aid facilities 
and medical supplies, arrangements for qualified medical service 
providers and the transportation of contaminated injured individuals, 
and arrangements for the treatment of individuals injured in support of 
licensed activities. Decommissioning licensees have not received 
exemptions or license amendments for these requirements to date, and 
the NRC has determined that licensees with PSEPs and PDEPs would still 
need to maintain these capabilities under proposed Sec.  
50.200(c)(1)(v). Appendix E to 10 CFR part 50, paragraph VI.E.8 further 
includes emergency response facility requirements for a TSC, OSC, and 
EOF.
    For licensees with PDEPs, there is no longer a need for separate, 
dedicated facilities. The functions of the control room, TSC, OSC, and 
EOF could be combined into one or more locations while still adequately 
protecting public health and safety. Proposed Sec.  50.200(c)(1)(v)(H) 
would require licensees with PDEPs to establish a facility from which 
effective direction can be given and effective control can be exercised 
during an emergency. Because of the low probability of DBAs or other 
credible events that would be expected to exceed the limits of EPA PAGs 
offsite and the available time for event mitigation, the significantly 
reduced staff, and the minimal expected response required, offsite 
response would not be required at an EOF. Onsite actions may be 
directed from the control room or other location, without the 
requirements imposed on a TSC or EOF. Proposed Sec.  50.200(b)(3) would 
remove reference to the EOF as a location for response. Additionally, 
under this proposed rule, a separate OSC would no longer be required to 
meet its original purpose of an assembly area for plant logistical 
support during an emergency. The OSC function could be incorporated 
into another facility. The NRC is issuing DG-1346 for public comment in 
conjunction with this proposed rule; DG-1346 provides one acceptable 
method for meeting the proposed emergency response facility 
requirements for PDEPs.
    Appendix E to 10 CFR part 50, paragraph IV.E.9 addresses 
requirements for emergency communications systems, plans, and 
arrangements, including communications with OROs and between the 
control room, TSC, and EOF. Proposed Sec.  50.200(c)(1)(v)(I) would 
require licensees with PDEPs to continue to maintain an onsite and an 
offsite communications system with backup power and communication plans 
with arrangements for emergencies. These arrangements would need to 
include provisions for communications with contiguous State and local 
governments, Federal emergency response organizations, NRC 
Headquarters, and the appropriate NRC Regional Office Operations 
Center. Because licensees with PDEPs may combine emergency response 
facilities, the current requirements for communication between 
emergency response facilities would not apply to these licensees. Under 
the proposed rule, communications with State and local emergency 
operations centers would be maintained to allow coordination of 
assistance onsite if required.
PDEP Hostile Action
    Under this proposed rule, hostile action requirements would not 
apply to licensees with PDEPs. The definition of ``hostile action'' in 
appendix E to 10 CFR part 50, paragraph IV.A.7 applies

[[Page 12277]]

here to the capability of implementing EP during hostile action events. 
However, in the statement of considerations (SOC) for the 2011 EP Final 
Rule, the NRC excluded non-power reactors from the definition of 
``hostile action'' because a non-power reactor as defined in Sec.  
50.2, ``Definitions,'' is not a nuclear power plant, and a regulatory 
basis had not been developed to support the inclusion of non-power 
reactors in the definition of ``hostile action.'' A licensee with a 
PDEP would be similar to a non-power reactor in that both have a low 
likelihood of a credible accident resulting in radiological releases 
requiring response actions offsite. Additionally, regardless of how a 
disruption to the SFP cooling occurs, the spent fuel would take longer 
than 10 hours to heat up to ignition temperature, providing adequate 
time to coordinate a response between the ERO and law enforcement 
officials. As such, licensees with PDEPs would not fall within the 
scope of ``hostile action,'' and enhancements to EP in response to 
hostile action, such as alternative facilities for the staging of ERO 
personnel, protection of onsite personnel, and challenging drills and 
exercises involving hostile action, would not be warranted.
    Although this rationale justifies the exclusion of licensees with 
PDEPs from the definition of ``hostile action'' and its related 
requirements (including conducting hostile action exercises) as they 
apply to EP, elements for security-based events would still be 
maintained for these facilities, including EALs for security-based 
events. Under the proposed rule, licensees with PDEPs would be required 
to identify ORO resources that would respond to a security event, and 
the assistance licensees expect from those resources would be 
maintained in PDEPs. For physical security, the objective for these 
facilities relates to protection of the spent fuel against sabotage. A 
level of security commensurate with the consequences of a sabotage 
event is required and is evaluated on a site-specific basis. The 
severity of the consequences declines as fuel ages and thereby removes 
over time the underlying concern that a sabotage attack, under the 
current definition, could cause offsite radiological consequences.
PDEP Drills and Exercises
    Section 50.47(b)(14) and appendix E to 10 CFR part 50, paragraph 
IV.F provide training and drill and exercise requirements for nuclear 
power reactor licensees. Consistent with the language of Sec.  
50.47(b)(14), the proposed PDEP planning standard under Sec.  
50.200(b)(14) would require licensees with PDEPs to conduct periodic 
exercises to evaluate major portions of emergency response 
capabilities, to conduct periodic drills to develop and maintain key 
skills, and to correct deficiencies identified as a result of exercises 
and drills. The NRC is proposing new drill and exercise requirements 
for licensees with PDEPs under Sec.  50.200(c)(1)(vi) that differ from 
the existing requirements under appendix E to 10 CFR part 50, paragraph 
IV.F to account for changes in principal functional areas, offsite 
radiological emergency response requirements, offsite PAR requirements, 
and the spectrum of possible accidents.
    Similar to the requirements in appendix E to 10 CFR part 50, 
paragraph IV.F.1, proposed Sec.  50.200(c)(1)(vi)(A) would require 
licensees with PDEPs to describe in their emergency plan provisions for 
the training of employees, exercising the emergency plan by conducting 
periodic drills, and including other individuals in training and drills 
when those individuals may provide assistance in the event of a 
radiological emergency. Under the proposed rule, the emergency plan 
would be required to describe the training to be provided to several 
categories of emergency personnel, with the exception of licensees' 
headquarters support personnel. Headquarters support personnel would no 
longer be required to augment the ERO for licensees with PDEPs. 
Licensees with PDEPs would need to continue to make available a 
radiological orientation training program for local services personnel 
expected to provide support onsite. Because of the time available to 
coordinate offsite agency notification to the public, licensees with 
PDEPs would not be required to provide radiological orientation 
training to local news media persons. Similar to the requirements in 
appendix E to 10 CFR part 50, paragraph IV.F.2, proposed Sec.  
50.200(c)(1)(vi)(B) would require licensees with PDEPs to continue to 
describe provisions for the conduct of EP exercises that test the 
adequacy of timing and content of implementing procedures and methods, 
test emergency equipment and communications networks, and ensure 
emergency organization personnel are familiar with their duties. 
Licensees with PDEPs would not be required to test the public alert and 
notification system during their exercises because the system would no 
longer be required, as discussed previously in this document.
    Proposed Sec.  50.200(c)(1)(vi)(B)(1) and (2) would require 
licensees with PDEPs to conduct an exercise within two years of the 
last exercise of the onsite emergency plan conducted under paragraph 
IV.F.2.b of appendix E to 10 CFR part 50 and to continue to conduct 
subsequent biennial exercises of onsite emergency plans. Licensees with 
PDEPs would need to continue to conduct drills during the intervals 
between biennial exercises involving a combination of principal 
functional areas. The principal functional areas of emergency response 
for licensees with PDEPs would include all of the areas currently 
listed under appendix E to 10 CFR part 50, paragraph IV.F.2.b, with the 
exception of protective action development and protective action 
decision making (see discussion on protective action recommendations in 
the section ``PDEP Offsite Radiological Protective Action 
Recommendations'' in this document).
    Similar to the requirements in appendix E to 10 CFR part 50, 
paragraph IV.F.2.f, proposed Sec.  50.200(c)(1)(vi)(B)(4) would require 
licensees with PDEPs to conduct remedial exercises if the emergency 
plan is not satisfactorily tested during the biennial exercise. Like 
appendix E to 10 CFR part 50, paragraph IV.F.2.g, proposed Sec.  
50.200(c)(1)(vi)(B)(5) would require licensees with PDEPs to provide 
for formal critiques of exercises, drills, and training that provide 
performance opportunities to develop, maintain, or demonstrate key 
skills and to correct weaknesses or deficiencies identified in a 
critique.
    Proposed Sec.  50.200(c)(1)(vi)(B)(6) would require licensees with 
PDEPs to continue to use drills and exercise scenarios that provide 
reasonable assurance that anticipatory responses will not result from 
preconditioning of participants and that emphasize coordination among 
onsite and offsite response organizations. Unlike the current 
requirements under appendix E to 10 CFR part 50, paragraphs IV.F.2.b, 
IV.F.2.i, and IV.F.2.j, licensees with PDEPs would not be required to 
submit exercise scenarios 60 days before use in an exercise, 
demonstrate that exercise scenarios include a wide spectrum of 
radiological releases and events, or vary exercise scenarios across an 
eight calendar year exercise cycle to allow for the demonstration of 
responses to specified scenario elements, respectively. These 
requirements would no longer apply due to the limited types of events 
that could occur. The previously routine progression to a General 
Emergency, or even a Site Area Emergency, in nuclear power reactor site 
scenarios is not applicable for licensees with PDEPs.

[[Page 12278]]

    The NRC is issuing DG-1346 for public comment in conjunction with 
this proposed rule; DG-1346 provides one method acceptable to the NRC 
for licensees with PDEPs to comply with the proposed drill and exercise 
requirements.
PDEP Offsite Response Organization Participation in Drills and 
Exercises
    Appendix E to 10 CFR part 50, paragraph IV.F and Sec.  50.47(b)(14) 
include requirements for periodic EP drills and exercises for 
licensees. Appendix E to 10 CFR part 50, paragraphs IV.F.2.c and 
IV.F.2.d requires offsite radiological emergency plans for each site to 
be exercised biennially with full participation by offsite authorities 
having a role under the radiological response plan. Appendix E to 10 
CFR part 50, paragraphs IV.F.2.f and IV.F.2.h address State and local 
participation in remedial exercises and refusal of State and local 
governments to participate. Because no action is required from State 
and local government organizations in response to events other than 
firefighting, law enforcement, and ambulance/medical services, the 
requirements related to ORO participation in radiological drills and 
exercises would no longer be applicable to licensees with PDEPs. 
Proposed Sec.  50.200(c)(1)(vi)(B) would remove the requirement to 
exercise offsite emergency plans once the NRC has docketed the 
licensee's certifications required under Sec.  50.82(a)(1) or Sec.  
52.110(a) and the licensee elects under Sec.  50.54(q)(7)(ii) to 
transition to a PDEP. For facilities that are located either on the 
same site or on adjacent contiguous sites to reactors that continue to 
operate, the offsite emergency plans would continue to be exercised as 
required under appendix E to 10 CFR part 50, paragraph IV.2.f, until 
all reactors at the site cease operation and transition to a PDEP. 
Similar to the requirements under appendix E to 10 CFR part 50, 
paragraph IV.2.f.e, under proposed Sec.  50.200(c)(1)(vi)(B)(3), a 
licensee with a PDEP would be required to enable any State or local 
government to participate in the licensee's drills and exercises when 
requested.
6. Independent Spent Fuel Storage Installation-Only Emergency Plans
    In order to transition to an IOEP, the NRC is proposing under Sec.  
50.54(q)(7)(iii) that licensees must have all spent fuel in dry cask 
storage. Licensees with an IOEP must follow and maintain the 
effectiveness of an emergency plan that meets the requirements in Sec.  
72.32(a).
    Licensees with 10 CFR part 72 specific licenses or under the 10 CFR 
part 72 general license may hold an IOEP. A licensee with all of its 
spent fuel in dry cask storage that terminates its 10 CFR part 50 or 10 
CFR part 52 license must first obtain a 10 CFR part 72 specific license 
before transitioning to the EP requirements already provided in Sec.  
72.32(a). A licensee maintaining its 10 CFR part 50 or 10 CFR part 52 
license, and thus its 10 CFR part 72 general license authorized under 
Sec.  72.210, ``General license issued,'' may opt to change its EP 
program to align it with the requirements of Sec.  72.32 once all spent 
fuel is transferred to dry cask storage. In addition, licensees under 
the 10 CFR part 72 general license would need to continue to comply 
with all applicable 10 CFR part 50 and 10 CFR part 52 requirements 
until the 10 CFR part 50 or 10 CFR part 52 license is terminated 
consistent with Sec.  50.82 or Sec.  52.110, respectively.
    Under proposed Sec.  50.54(q)(7)(iii), a licensee may choose not to 
comply with the EP requirements under Sec.  72.32 and may instead 
maintain a PSEP or PDEP. Licensees with dry cask storage must ensure 
that the emergency plan includes an appropriate EAL scheme.
    The NRC is issuing DG-1346 for public comment in conjunction with 
this proposed rule; DG-1346 provides guidance on transitioning to and 
maintaining an IOEP.
7. All Spent Fuel Removed From Site
    During the fourth level of decommissioning, the proposed rule would 
allow a licensee to terminate its EP program under proposed Sec.  
50.54(q)(7)(iv) or proposed Sec.  72.44(f). Once all spent fuel has 
been permanently removed from the site, the site no longer poses any 
risk of a radiological release. The licensee must then continue to 
follow its PSDAR submitted under Sec.  50.82 until decommissioning is 
completed.
8. Changes to Emergency Plans
    Existing Sec.  50.54(q)(2) requires nuclear power reactor licensees 
to follow and maintain the effectiveness of an emergency plan that 
meets the planning standards in Sec.  50.47(b) and the requirements in 
appendix E to 10 CFR part 50. In addition, Sec.  50.54(q)(3) contains 
the conditions under which the licensee may make changes to its 
emergency plan without prior application to and approval by the NRC, 
provided that the changes do not reduce the effectiveness of the plan 
and that the plan, as changed, continues to meet the standards in Sec.  
50.47(b) and the requirements in appendix E to 10 CFR part 50. The NRC 
is proposing to add several new paragraphs that, similar to Sec.  
50.54(q)(2) and (3), would reference the requirements that emergency 
plans for decommissioning nuclear power reactors must meet and the 
process for making these plan changes. In particular, proposed Sec.  
50.54(q)(7) would reference the applicable emergency plan requirements 
after the NRC dockets a licensee's certifications under Sec.  
50.82(a)(1) or Sec.  52.110(a), and proposed Sec.  50.54(q)(8) would 
stipulate the conditions under which decommissioning nuclear power 
reactor licensees may make changes to their emergency plans without 
prior approval by the NRC. The NRC also would revise Sec.  50.54(q)(1) 
to clarify that the definitions in paragraph (q) apply to only 
paragraph (q).
    The existing change process under Sec.  50.54(q) does not establish 
whether a proposed change would impact the agency's determination that 
there is reasonable assurance that a licensee can and will take 
adequate protective measures in the event of a radiological emergency; 
the change process establishes only whether the licensee has the 
authority to implement the proposed change without prior NRC approval. 
The change process uses the characteristic ``reduction in 
effectiveness'' to exclude from the requirement to seek prior NRC 
approval those changes that would likely not reduce the effectiveness 
of the licensee's emergency plan. Because these changes would not 
reduce the effectiveness of the plan, the NRC expects that the changes 
should not have an impact on the agency's reasonable assurance 
determination. A licensee's determination that a proposed change would 
reduce the effectiveness of the emergency plan does not mean that the 
licensee could not or would not implement adequate protective measures 
to protect public health and safety in the event of a radiological 
accident, but only that prior NRC review is required to evaluate the 
impact of the change on the reasonable assurance determination. As part 
of routine oversight, the NRC screens emergency plan changes, including 
EAL changes, and reviews a sample of changes documented in reports 
submitted under Sec.  50.54(q)(5) that could potentially reduce 
effectiveness. These reviews do not constitute the NRC's approval of 
the plan changes, and all such changes remain subject to future 
inspection and enforcement actions. The NRC documents its approval of 
plan changes under Sec.  50.54(q)(4) in its decisions to grant license 
amendment requests.

[[Page 12279]]

    The licensee cannot properly evaluate a proposed change to the 
emergency plan if it has not considered the basis for the NRC's 
approval of the original plan or the basis for any subsequent changes 
to the plan--whether those changes were approved by the NRC or 
implemented by the licensee without prior NRC approval under Sec.  
50.54(q). Regulatory Guide (RG) 1.219, Revision 1, ``Guidance on Making 
Changes to Emergency Plans for Nuclear Power Reactors'' (ADAMS 
Accession No. ML16061A104), describes a method that the NRC considers 
acceptable to implement the requirements in Sec.  50.54(q) as they 
relate to EP and specifically to making changes to emergency response 
plans. As provided in RG 1.219, the licensee should consider its 
licensing basis to inform a Sec.  50.54(q) evaluation, and, 
principally, applicable regulatory requirements, which are binding on 
the licensee unless the NRC explicitly exempts the licensee from them. 
The NRC is issuing DG-1346 for public comment in conjunction with this 
proposed rule to provide guidance for decommissioning nuclear power 
reactors in evaluating changes to emergency plans under proposed Sec.  
50.54(q).
    The change process is meant to ensure that emergency plans are 
maintained up to date and that the level of planning does not fall 
below the standards to which the licensee has committed. The 
regulations in Sec.  50.54(q) define ``reduction in effectiveness'' as 
a change in an emergency plan that results in reducing the licensee's 
capability to perform an emergency planning function in the event of a 
radiological emergency. ``Emergency planning function'' is currently 
defined as a capability or resource necessary to prepare for, and 
respond to, a radiological emergency, as established in the planning 
standards of Sec.  50.47(b) and the elements of appendix E to 10 CFR 
part 50, section IV. The NRC is proposing to remove the references to 
the planning standards of Sec.  50.47(b) and appendix E to 10 CFR part 
50 from this definition because this proposed rule would establish 
alternative emergency planning standards under proposed Sec.  50.200, 
and the NRC does not consider the references essential to the 
definition.
    When the NRC considers exemptions from EP requirements for a 
decommissioning nuclear power reactor licensee, the NRC considers 
whether there are special circumstances present as defined in Sec.  
50.12(a)(2). In particular, the NRC determines whether application of 
the EP regulations for which exemptions are under consideration in the 
particular circumstances would not serve their underlying purpose or 
are not necessary to achieve their underlying purpose, which is to 
provide reasonable assurance that adequate protective measures can and 
will be taken in the event of a radiological emergency. Once the NRC 
grants a licensee exemptions from EP requirements, the exempted 
regulations no longer apply to the licensee. The licensee may need to 
submit a separate license amendment request if the planned changes 
conflict with an element of the current licensing basis. If not, the 
licensee need not submit a separate license amendment request for NRC 
approval of the emergency plan changes unless the plan changes go 
beyond those resulting from the exemptions granted. The NRC intends 
that this proposed rule would establish clear regulatory requirements 
for EP, reducing the need to request certain exemptions. As such, the 
NRC is proposing to add Sec.  50.54(q)(8) to establish the process for: 
(1) Transitions from one decommissioning level's EP planning standards 
and requirements to the next level's EP planning standards and 
requirements, and (2) changes to emergency plans within a 
decommissioning level.
    In considering a graded approach to EP, the NRC recognizes that a 
transition between the EP planning standards and requirements of each 
decommissioning level is not equivalent to making changes to the 
emergency plan within a level. The transition between the EP planning 
standards and requirements of each decommissioning level is 
fundamentally a licensee's commitment to a different set of EP 
standards and associated emergency planning functions, and the change 
process should facilitate this transition.
    For transitions from one decommissioning level to the next, the NRC 
would require licensees to establish emergency plans that meet the EP 
planning standards and requirements of the next level. The transition 
is optional, and a licensee that maintains its current level of 
emergency planning would satisfy the requirements of the next level; 
however, doing so would mean maintaining emergency planning functions 
above the commensurate level of planning for the risk involved. Under 
the proposed Sec.  50.54(q)(8), a licensee would be able to make 
changes to the emergency plan to commit to the EP planning standards 
and requirements of the next decommissioning level (i.e., PSEP, PDEP, 
or IOEP) using the Sec.  50.54(q)(3) change process, but would only 
need to consider whether the changes meet the next level's planning 
standards and requirements. Licensees making changes to their emergency 
plans to commit to the EP planning standards and requirements of a 
decommissioning level would not be required to determine if the changes 
are reductions in effectiveness. Instead, the NRC would have already 
made this determination through its issuance of the regulations 
promulgating the EP planning standards and requirements of the 
decommissioning levels. The NRC's proposed regulatory approach to 
transitions between EP decommissioning levels does not go beyond the 
authority currently granted to licensees to make changes to their 
emergency plan under Sec.  50.54(q)(3). Additionally, any change to the 
emergency plan that is not made to comply with the EP planning 
standards and requirements of the next decommissioning level would 
require a licensee to make a determination as to whether the change 
would be a reduction in effectiveness.
    After the Three Mile Island accident in 1979, the NRC issued a 
final rule (45 FR 55402; August 19, 1980) (1980 EP Final Rule) that 
included Sec.  50.54(u), which required licensees to upgrade their 
emergency plans to meet the then-new planning standards of Sec.  
50.47(b) and requirements in appendix E to 10 CFR part 50 and to submit 
those plans to the NRC. In the 2011 EP Final Rule, the NRC removed and 
reserved Sec.  50.54(u). The NRC's proposed approach to transitions 
between EP planning standards and requirements of decommissioning 
levels is analogous to the approach taken by the NRC when the 16 EP 
planning standards went into effect in 1980 (see ``Reasonable Assurance 
and Offsite Radiological Emergency Preparedness'' section in this 
document). Under this approach, the NRC would not be relinquishing its 
oversight authority, as some commenters on the ANPR and draft 
regulatory basis supposed. As proposed, Sec.  50.54(q)(8)(i) would 
require initial emergency plan changes made to transition between EP 
decommissioning levels to be submitted to the NRC at least 60 days 
prior to implementation, and emergency plans would remain subject to 
future inspection and enforcement. The proposed submittal is not 
intended to be a licensing action. It would provide a current copy of 
the emergency plan to the NRC prior to implementation in support of 
future inspection activities. This submittal would provide an 
opportunity for the NRC to assure that the licensee maintains the 
effectiveness of its emergency plan. Subsequent emergency plan changes 
would need to follow the

[[Page 12280]]

existing change control process under Sec.  50.54(q)(3) and (4). 
Hearing rights would not attach to transitions between EP 
decommissioning levels; however, the public has the opportunity to 
comment on the graded EP planning standards and requirements themselves 
in response to this proposed rule and the drafts of the supporting 
guidance documents. In addition, all emergency plan changes submitted 
under Sec.  50.54(q)(5) and proposed Sec.  50.54(q)(8) would be 
publicly available.
    In addition to the general requirements in proposed Sec.  
50.54(q)(8)(i) governing transitions between EP decommissioning levels, 
proposed Sec.  50.54(q)(8) would address changes specific to SSCs and 
EALs. Proposed Sec.  50.54(q)(8)(ii) would specify that, for SSCs that 
are no longer needed to provide support for an emergency planning 
function (as defined under proposed Sec.  50.54(q)(1)(iii)), a licensee 
may make a determination under Sec.  50.54(q)(3) that emergency plan 
changes are not a reduction in effectiveness if the updated FSAR 
demonstrates that these SSCs are no longer required to be in service 
due to the decommissioning status of the facility. Proposed Sec.  
50.54(q)(8)(iii) would state that changes to EALs based on plant 
conditions that are not physically achievable or instrumentation that 
is no longer in service due to the transition to decommissioning are 
not reductions in effectiveness provided that a Sec.  50.54(q)(3) 
evaluation demonstrates that the change does not reduce the capability 
of taking timely and appropriate protective actions. The NRC is 
proposing these requirements to provide clarity on Sec.  50.54(q)(3) 
evaluations and alleviate the burden on licensees from submitting 
emergency plan changes that result from SSCs and instrumentation that 
are no longer required to be in service due to decommissioning.
    After the implementation of a PSEP, PDEP, or IOEP, licensees would 
be required by proposed Sec.  50.54(q)(7)(i) to continue to follow and 
maintain the effectiveness of the plan and by proposed Sec.  
50.54(q)(8)(i)-(iii) to comply with the change process described under 
existing Sec.  50.54(q)(3) and (q)(4). Therefore, licensees would be 
allowed to make changes to these emergency plans without prior 
application to and approval by the NRC, provided that the changes would 
not reduce the effectiveness of the plan and that the plan, as changed, 
would continue to meet the EP planning standards and requirements for 
the applicable decommissioning level. Current Sec.  50.54(q)(5) would 
require decommissioning licensees to submit to the NRC a report of each 
such change within 30 days after the change is put into effect. And, 
consistent with current requirements, decommissioning licensees would 
have to submit changes that would reduce the effectiveness of the plan 
for prior NRC review and approval in accordance with Sec.  50.54(q)(4) 
so that the NRC could make the requisite reasonable assurance 
determination. For subsequent emergency plan changes once all fuel is 
in dry cask storage (i.e., for changes to an IOEP), proposed Sec.  
50.54(q)(8)(i) would allow licensees to follow the change process under 
Sec.  72.44(f).
    The proposed amendments to the regulatory change process are 
necessary because:
    <bullet> The regulation in existing Sec.  50.54(q)(2), which 
provides that a licensee must follow and maintain the effectiveness of 
the emergency plan, should continue to apply in order to ensure that 
emergency plans are followed and kept up to date.
    <bullet> The existing Sec.  50.54(q) change process and the 
associated regulatory guidance currently do not address how a licensee 
could change its emergency plans to comply with the emergency plan 
standards as the licensee transitions to each level of decommissioning.
    <bullet> This proposed rule would allow the NRC to maintain, 
through a regulatory change process, reasonable assurance that a 
licensee can and will take adequate protective measures in the event of 
a radiological emergency.
    The proposed amendments to Sec.  50.54(q), and related regulatory 
guidance, would ensure that licensees would maintain the effectiveness 
of the emergency plans. Emergency plans that comply with the proposed 
graded EP planning standards and requirements would continue to provide 
reasonable assurance that adequate protective measures can and will be 
taken in the event of a radiological emergency. Any plan that did not 
meet these standards and requirements and, if applicable, the reduction 
in effectiveness criterion, would be subject to inspection and 
enforcement actions. The proposed approaches to transitioning between 
EP decommissioning levels and to making emergency plan changes within 
decommissioning levels would provide an efficient and effective 
regulatory change process and would promote consistent and predictable 
implementation and enforcement.
9. Program Element Review Under Sec.  50.54(t)
    Under current Sec.  50.54(t), licensees must conduct reviews of EP 
program elements either: (1) At intervals not to exceed 12 months or 
(2) as necessary, based on an assessment by the licensee against 
performance indicators and as soon as reasonably practicable after a 
change occurs in personnel, procedures, equipment, or facilities that 
potentially could adversely affect EP. If a licensee chooses the second 
option, it must still review all program elements at least once every 
24 months. For several reasons, the proposed rule would provide 
decommissioning licensees with an alternative approach to reviewing EP 
program elements.
    First, the NRC expects licensees to remain in the first level of 
decommissioning (i.e., with a PSEP) for less than 24 months, and the 
scope of a PSEP is largely unchanged from the scope of an operating 
reactor's emergency plan. Conversely, the second level of 
decommissioning (i.e., licensees with a PDEP) will involve more 
significant changes, and the NRC anticipates that licensees would 
remain in the second level of decommissioning for a longer period of 
time. Therefore, in order to support program continuity and minimize 
changes during the transition to a PDEP, the NRC is proposing to amend 
Sec.  50.54(t) such that, starting after licensees enter the second 
level of decommissioning, licensees would be able to conduct program 
element reviews under Sec.  50.54(t) at intervals not to exceed 24 
months (rather than 12 months) without conducting an assessment against 
performance indicators. The NRC is proposing to add new Sec.  
50.54(t)(3) to remove the requirement to conduct periodic EP program 
element reviews once all fuel is in dry cask storage (i.e., the third/
IOEP level of decommissioning), consistent with the EP requirements for 
ISFSIs under 10 CFR part 72.
10. Reasonable Assurance and Offsite Radiological Emergency 
Preparedness
    The regulations in Sec. Sec.  50.47 and 50.54, ``Conditions of 
licenses,'' prescribe how the NRC will make licensing decisions or take 
appropriate enforcement actions by using findings of reasonable 
assurance that adequate protective measures can and will be taken to 
protect public health and safety in the event of a radiological 
emergency. Every 10 CFR part 50 or 10 CFR part 52 license includes as a 
condition of the license the requirements of Sec.  50.54(s)(2)(ii) and 
(s)(3) regarding findings and determinations of reasonable assurance.

[[Page 12281]]

The NRC has the authority and responsibility to make licensing findings 
on the overall adequacy of onsite and offsite emergency planning and 
preparedness. Commensurate with the NRC's responsibility to make such

[…truncated; see source link]
Indexed from Federal Register on March 3, 2022.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.