Georgia-Pacific Consumer Operations LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Georgia-Pacific Consumer Pipeline Abandonment Project

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
February 7, 2022

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 87 Issue 25 (Monday, February 7, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 25 (Monday, February 7, 2022)]
[Notices]
[Pages 6858-6860]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-02499]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP22-16-000]


Georgia-Pacific Consumer Operations LLC; Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Proposed Georgia-
Pacific Consumer Pipeline Abandonment Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental document, that will discuss 
the environmental impacts of the Georgia-Pacific Consumer Operations 
LLC (GPC) Pipeline Abandonment Project (Project) involving abandonment 
and removal of interstate natural gas transmission facilities by GPC in 
Louisiana and Arkansas. The Commission will use this environmental 
document in its decision-making process.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies regarding the project. As part of the National Environmental 
Policy Act (NEPA) review process, the Commission takes into account 
concerns the public may have about proposals and the environmental 
impacts that could result from its action whenever it considers the 
issuance of an authorization. This gathering of public input is 
referred to as ``scoping.'' The main goal of the scoping process is to 
focus the analysis in the environmental document on the important 
environmental issues. Additional information about the Commission's 
NEPA process is described below in the NEPA Process and Environmental 
Document section of this notice.
    By this notice, the Commission requests public comments on the 
scope of issues to address in the environmental document. To ensure 
that your comments are timely and properly recorded, please submit your 
comments so that the Commission receives them in Washington, DC on or 
before 5:00 p.m. Eastern Time on March 3, 2022.
    Comments may be submitted in written form. Further details on how 
to submit comments are provided in the Public Participation section of 
this notice.
    Your comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues they need to evaluate in the environmental document. Commission 
staff will consider all written comments during the preparation of the 
environmental document.
    If you submitted comments on this project to the Commission before 
the opening of this docket on November 16, 2021, you will need to file 
those comments in Docket No. CP22-16-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of workspace 
needed to abandon the proposed facilities. The company would seek to 
negotiate a mutually acceptable agreement. You are not required to 
enter into an agreement. However, if the Commission approves the 
project, the Natural Gas Act conveys the right of eminent domain to the 
company. Therefore, if you and the company do not reach an agreement, 
the pipeline company could initiate condemnation proceedings in court. 
In such instances, compensation would be determined by a judge in 
accordance with state law. The Commission does not subsequently grant, 
exercise, or oversee the exercise of that eminent domain authority. The 
courts have exclusive authority to handle eminent domain cases; the 
Commission has no jurisdiction over these matters.
    Georgia-Pacific provided landowners with a fact sheet prepared by 
the FERC entitled ``An Interstate Natural Gas Facility On My Land? What 
Do I Need To Know?'' which addresses typically asked questions, 
including the use of eminent domain and how to participate in the 
Commission's proceedings. This fact sheet along with other landowner 
topics of interest are available for viewing on the FERC website

[[Page 6859]]

(<a href="http://www.ferc.gov">www.ferc.gov</a>) under the Natural Gas Questions or Landowner Topics 
link.

Public Participation

    There are three methods you can use to submit your comments to the 
Commission. Please carefully follow these instructions so that your 
comments are properly recorded. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or <a href="/cdn-cgi/l/email-protection#70361502133f1e1c191e15230500001f020430161502135e171f06"><span class="__cf_email__" data-cfemail="773112051438191b1e191224020707180503371112051459101801">[email&#160;protected]</span></a>.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) 
under the link to FERC Online. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) 
under the link to FERC Online. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (CP22-
16-000) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    Additionally, the Commission offers a free service called 
eSubscription which makes it easy to stay informed of all issuances and 
submittals regarding the dockets/projects to which you subscribe. These 
instant email notifications are the fastest way to receive notification 
and provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. Go to <a href="https://www.ferc.gov/ferc-online/overview">https://www.ferc.gov/ferc-online/overview</a> to register for eSubscription.

Summary of the Proposed Project

    GPC proposes to abandon in-place approximately 19.5 miles of eight-
inch-diameter natural gas transmission pipeline and auxiliary 
facilities that originate from the out-of-service DCP Midstream (DCPM) 
Transfer Station in Union Parish, Louisiana to a point approximately 
one mile east of GPC's Crossett Facility in Ashley County, Arkansas. 
Additionally, GPC proposes to abandon by removal all aboveground 
features associated with the 19.5 miles of pipeline.
    The GPC Pipeline has been disconnected from all gas pipeline 
sources. GPC proposes to permanently abandon the pipeline by purging 
the pipeline, and filling it with inert gas or flowable fill, 
consistent with federal pipeline safety abandonment regulations at 49 
CFR 192.727, and any other required federal, state, or local 
requirements.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
<a href="http://www.ferc.gov">www.ferc.gov</a> using the link called ``eLibrary''. For instructions on 
connecting to eLibrary, refer to the last page of this notice. At 
this time, the Commission has suspended access to the Commission's 
Public Reference Room due to the proclamation declaring a National 
Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact 
FERC at <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="0e484b5c4d41606267606b5d7b7e7e617c7a4e686b7c6d20696178">[email&#160;protected]</a> or call toll free, (886) 208-3676 
or TTY (202) 502-8659.
---------------------------------------------------------------------------

Land Requirements for Construction

    The total surface disturbance associated with the Project is 
expected to be 2.8 acres; of this 2.2 acres are associated with the 
road and railroad crossings and 0.65 acres are associated with the 
removal of the aboveground structures. All of the land disturbing 
activities would be temporary. The areas where soils are disturbed will 
be stabilized as soon as practicable and seeded with native grasses. 
GPC intends to retain its existing right-of-way easement.

NEPA Process and the Environmental Document

    Any environmental document issued by the Commission will discuss 
impacts that could occur as a result of the construction and operation 
of the proposed project under the relevant general resource areas:
    <bullet> Geology and soils;
    <bullet> water resources and wetlands;
    <bullet> vegetation and wildlife;
    <bullet> threatened and endangered species;
    <bullet> cultural resources;
    <bullet> land use;
    <bullet> environmental justice;
    <bullet> air quality and noise; and
    <bullet> reliability and safety.
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project and make recommendations on 
how to lessen or avoid impacts on the various resource areas. Your 
comments will help Commission staff identify and focus on the issues 
that might have an effect on the human environment and potentially 
eliminate others from further study and discussion in the environmental 
document.
    Following this scoping period, Commission staff will prepare an 
Environmental Assessment (EA). The EA will present Commission staff's 
independent analysis of the issues. A Notice of Schedule for the 
Preparation of an Environmental Assessment will be issued. The EA may 
be issued for an allotted public comment period. The Commission would 
consider timely comments on the EA before making its decision regarding 
the proposed project. Any EA will be available in electronic format in 
the public record through eLibrary \2\ and the Commission's natural gas 
environmental documents web page (<a href="https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents">https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents</a>). If eSubscribed, you 
will receive instant email notification when the environmental document 
is issued.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the environmental document.\3\ Agencies that would like 
to request cooperating agency status should follow the instructions for 
filing comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Section 1501.8.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office(s), 
and to solicit their views and those of other government agencies, 
interested Indian tribes, and the public on the project's potential 
effects on historic properties.\4\

[[Page 6860]]

The environmental document for this project will document findings on 
the impacts on historic properties and summarize the status of 
consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at title 36, Code of Federal Regulations, part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project and includes a mailing address with their 
comments. Commission staff will update the environmental mailing list 
as the analysis proceeds to ensure that Commission notices related to 
this environmental review are sent to all individuals, organizations, 
and government entities interested in and/or potentially affected by 
the proposed project.
    If you need to make changes to your name/address, or if you would 
like to remove your name from the mailing list, please complete one of 
the following steps:
    (1) Send an email to <a href="/cdn-cgi/l/email-protection#c681a7b596b4a9aca3a5b287a2a2b4a3b5b585aea7a8a1a386a0a3b4a5e8a1a9b0"><span class="__cf_email__" data-cfemail="9ed9ffedceecf1f4fbfdeadffafaecfbededddf6fff0f9fbdef8fbecfdb0f9f1e8">[email&#160;protected]</span></a> stating your 
request. You must include the docket number CP22-16-000 in your 
request. If you are requesting a change to your address, please be sure 
to include your name and the correct address. If you are requesting to 
delete your address from the mailing list, please include your name and 
address as it appeared on this notice. This email address is unable to 
accept comments.

OR

    (2) Return the attached ``Mailing List Update Form'' (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number 
in the ``Docket Number'' field. Be sure you have selected an 
appropriate date range. For assistance, please contact FERC Online 
Support at <a href="/cdn-cgi/l/email-protection#b3f5d6c1d0fcdddfdaddd6e0c6c3c3dcc1c7f3d5d6c1d09dd4dcc5"><span class="__cf_email__" data-cfemail="72341700113d1c1e1b1c17210702021d000632141700115c151d04">[email&#160;protected]</span></a> or (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of all formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at <a href="https://www.ferc.gov/news-events/events">https://www.ferc.gov/news-events/events</a> along with 
other related information.

    Dated: February 1, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-02499 Filed 2-4-22; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>