Notice2022-00812

Aspinook Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
January 18, 2022

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 87 Issue 11 (Tuesday, January 18, 2022)</title>
</head>
<body><pre>
[Federal Register Volume 87, Number 11 (Tuesday, January 18, 2022)]
[Notices]
[Page 2605]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2022-00812]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3472-024]


Aspinook Hydro, LLC; Notice of Intent To Prepare an Environmental 
Assessment

    On April 30, 2020, Aspinook Hydro, LLC filed an application for a 
new major license for the 2.78-megawatt Wyre Wynd Hydroelectric Project 
(Wyre Wynd Project) (FERC No. 3472). The Wyre Wynd Project is located 
on the Quinebaug River in New London and Windham Counties, Connecticut. 
The project does not occupy federal land.
    In accordance with the Commission's regulations, on October 6, 
2021, Commission staff issued a notice that the project was ready for 
environmental analysis (REA notice). Based on the information in the 
record, including comments filed on the REA notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to license the Wyre Wynd Project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA...................  June 2022.\1\
Comments on EA.........................  July 2022.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Kristine 
Sillett at (202) 502-6575 or <a href="/cdn-cgi/l/email-protection#7b100912080f12151e55081217171e0f0f3b1d1e0918551c140d"><span class="__cf_email__" data-cfemail="1279607b61667b7c773c617b7e7e77666652747760713c757d64">[email&#160;protected]</span></a>.
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Wyre Wynd Project. Therefore, in accordance with CEQ's regulations, 
the EA must be issued within 1 year of the issuance date of this 
notice.

    Dated: January 11, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-00812 Filed 1-14-22; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on January 18, 2022.