Notice2021-27786

Venture Global Calcasieu Pass, LLC; Notice of Application To Amend and Establishing Intervention and Protest Deadline

Primary source

Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.

Published
December 23, 2021

Issuing agencies

Energy DepartmentFederal Energy Regulatory Commission

Full Text

<html>
<head>
<title>Federal Register, Volume 86 Issue 244 (Thursday, December 23, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 244 (Thursday, December 23, 2021)]
[Notices]
[Pages 72952-72954]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-27786]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP22-25-000]


Venture Global Calcasieu Pass, LLC; Notice of Application To 
Amend and Establishing Intervention and Protest Deadline

    Take notice that on December 3, 2021, Venture Global Calcasieu 
Pass, LLC (Calcasieu Pass), 1001 19th Street North, Suite 1500, 
Arlington, VA 22209, filed in the above referenced docket, an 
application pursuant to section 3 of the natural Gas Act (NGA) and Part 
153, Subpart B, of the Commission's regulations for an amendment to the 
authorizations granted by the Commission on February 21, 2019 in Docket 
No. CP15-550-000. Those actions authorized Calcasieu Pass to site, 
construct, and operate a new liquified natural gas (LNG) export 
terminal and associated facilities (Export Terminal) along the 
Calcasieu Ship Channel in Cameron Parish, Louisiana. In this amendment 
Calcasieu Pass proposes to increase the Export Terminal's peak 
achievable liquefaction capacity from 12.0 million metric tons per 
annum (MTPA) to 12.4 MTPA of LNG under optimal operating conditions. 
Calcasieu Pass states that the requested increase in peak liquefaction 
capacity reflects refinements in the conditions and assumptions 
concerning the maximum potential operations and does not involve 
construction of any new facilities nor any modification of the 
previously authorized facilities, all as more fully set forth in the 
application which is on file with the Commission and open to public 
inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (<a href="http://ferc.gov">http://ferc.gov</a>) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact FERC at 
<a href="/cdn-cgi/l/email-protection#2f696a7d6c60414346414a7c5a5f5f405d5b6f494a5d4c01484059"><span class="__cf_email__" data-cfemail="ecaaa9beafa38280858289bf999c9c839e98ac8a899e8fc28b839a">[email&#160;protected]</span></a> or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions regarding this filing should be directed to Calcasieu 
Pass' outside counsel, Patrick Nevins of Latham & Watkins, LLP, 555 
Eleventh Street NW, Suite 1000 Washington, DC 20004, telephone: (202) 
637-3363.
    Pursuant to section 157.9 of the Commission's Rules of Practice and 
Procedure,\1\ within 90 days of this Notice the Commission staff will 
either: complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or

[[Page 72953]]

issue a Notice of Schedule for Environmental Review. If a Notice of 
Schedule for Environmental Review is issued, it will indicate, among 
other milestones, the anticipated date for the Commission staff's 
issuance of the final environmental impact statement (FEIS) or 
environmental assessment (EA) for this proposal. The filing of an EA in 
the Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.9.
---------------------------------------------------------------------------

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on January 5, 2022. 
How to file protests, motions to intervene, and comments is explained 
below.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\2\ any person \3\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \2\ 18 CFR 157.205.
    \3\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\4\ and must be submitted by 
the protest deadline, which is January 5, 2022. A protest may also 
serve as a motion to intervene so long as the protestor states it also 
seeks to be an intervenor.
---------------------------------------------------------------------------

    \4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \5\ and the regulations under the NGA \6\ by the 
intervention deadline for the project, which is January 5, 2022. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------

    \5\ 18 CFR 385.214.
    \6\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed \7\ motions to intervene are automatically 
granted by operation of Rule 214(c)(1).\8\ Motions to intervene that 
are filed after the intervention deadline are untimely and may be 
denied. Any late-filed motion to intervene must show good cause for 
being late and must explain why the time limitation should be waived 
and provide justification by reference to factors set forth in Rule 
214(d) of the Commission's Rules and Regulations.\9\ A person obtaining 
party status will be placed on the service list maintained by the 
Secretary of the Commission and will receive copies (paper or 
electronic) of all documents filed by the applicant and by all other 
parties.
---------------------------------------------------------------------------

    \7\ The applicant has 15 days from the submittal of a motion to 
intervene to file a written objection to the intervention.
    \8\ 18 CFR 385.214(c)(1).
    \9\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before January 5, 2022. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP22-25-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''.
    The Commission's eFiling staff are available to assist you at (202) 
502-8258 or <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="783e1d0a1b37161411161d2b0d0808170a0c381e1d0a1b561f170e">[email&#160;protected]</a>.
    (2) You can file a paper copy of your submission. Your submission 
must reference the Project docket number CP22-25-000.
    To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    To mail via any other courier, use the following address: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.
    Protests and motions to intervene must be served on the applicant 
either by mail at: Patrick Nevins of Latham & Watkins, LLP, 555 
Eleventh Street NW, Suite 1000, Washington, DC 20004 or email (with a 
link to the document) at: <a href="/cdn-cgi/l/email-protection#44342530362d272f6a2a21322d2a370428336a272b29"><span class="__cf_email__" data-cfemail="27574653554e444c094942514e4954674b500944484a">[email&#160;protected]</span></a>. Any subsequent 
submissions by an intervenor must be served on the applicant and all 
other parties to the proceeding. Contact information for parties can be 
downloaded from the service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific

[[Page 72954]]

dockets. This can reduce the amount of time you spend researching 
proceedings by automatically providing you with notification of these 
filings, document summaries, and direct links to the documents. For 
more information and to register, go to <a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.
    Intervention Deadline: 5:00 p.m. Eastern Time on January 5, 2022.

    Dated: December 15, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-27786 Filed 12-22-21; 8:45 am]
BILLING CODE 6717-01-P


</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>
Indexed from Federal Register on December 23, 2021.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.