Notice2021-27565
Ada County, Idaho Fulcrum LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
December 21, 2021
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 242 (Tuesday, December 21, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 242 (Tuesday, December 21, 2021)]
[Notices]
[Page 72226]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-27565]
[[Page 72226]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 4881-031]
Ada County, Idaho Fulcrum LLC; Notice of Application Tendered for
Filing With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 4881-031.
c. Date filed: November 30, 2021.
d. Applicant: Ada County, Idaho; Fulcrum LLC.
e. Name of Project: Barber Dam Hydroelectric Project.
f. Location: On the Boise River, near the city of Boise, Ada
County, Idaho. The project does not occupy federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Nicholas Josten, 2742 St. Charles Ave., Idaho
Falls, Idaho 83404; 208-520-5135.
i. FERC Contact: Matt Cutlip, 503-552-2762, <a href="/cdn-cgi/l/email-protection#88e5e9fcfca6ebfdfce4e1f8c8eeedfaeba6efe7fe"><span class="__cf_email__" data-cfemail="deb3bfaaaaf0bdabaab2b7ae9eb8bbacbdf0b9b1a8">[email protected]</span></a>.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 31, 2022.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at <a href="http://www.ferc.gov/docs-filing/efiling.asp">http://www.ferc.gov/docs-filing/efiling.asp</a>. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
<a href="http://www.ferc.gov/doc-sfiling/ecomment.asp">http://www.ferc.gov/doc-sfiling/ecomment.asp</a>. You must include your
name and contact information at the end of your comments. In lieu of
electronic filing, you may submit a paper copy. Submissions sent via
the U.S. Postal Service must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Room 1A, Washington, DC 20426. Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. The
first page of any filing should include docket number P-4881-031. For
assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#5d1b180f1e1233313433380e282d2d322f291d3b382f3e733a322b"><span class="__cf_email__" data-cfemail="61272433222e0f0d080f04321411110e131521070413024f060e17">[email protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY).
m. The application is not ready for environmental analysis at this
time.
n. The Barber Dam Project consists of the following existing
facilities: (1) A 1,100-foot-long earthen embankment dam; (2) a 400-
foot-long, 25-foot-high concrete capped timber crib spillway section;
(3) a powerhouse containing two 1,850-kilowatt generating units; (4) a
trash sluiceway; (5) a 75-acre impoundment; (6) a 100-foot-long
concrete tailrace; (7) 120 feet of transmission line; and (8)
appurtenant facilities. The project is operated in a run-of-river mode
and generates an average of 11,900 megawatt-hours per year. The
licensee proposes to modify the existing spillway to incorporate a
variable elevation weir, and to modify the plant operating system to
control the variable weir so that water is automatically bypassed to
the Boise River when the powerhouse trips offline.
o. A copy of the application can be viewed on the Commission's
website at <a href="http://www.ferc.gov">http://www.ferc.gov</a> using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. At this time, the Commission has
suspended access to the Commission's Public Reference Room due to the
proclamation declaring a National Emergency concerning the Novel
Coronavirus Disease (COVID-19) issued on March 13, 2020. For
assistance, contact FERC Online Support.
You may also register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
Additional Study Requests due--January 2022
Issue Deficiency Letter (if needed)--January 2022
Request for Additional Information (if needed)--January 2022
Issue Scoping Document 1 for comments--April 2022
Issue Determination on Additional Study Requests--April 2022
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: December 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-27565 Filed 12-20-21; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on December 21, 2021.