Notice2021-27060
AEP Generation Resources Inc.; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
December 15, 2021
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 238 (Wednesday, December 15, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 238 (Wednesday, December 15, 2021)]
[Notices]
[Page 71258]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-27060]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2570-034]
AEP Generation Resources Inc.; Notice of Application Tendered for
Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2570-034.
c. Date Filed: November 30, 2021.
d. Applicant: AEP Generation Resources Inc. (AEP Generation
Resources).
e. Name of Project: Racine Hydroelectric Project (Racine Project).
f. Location: The Racine Project is located at the U.S. Army Corps
of Engineers' (Corps) Racine Locks and Dam on the Ohio River near the
Town of Racine in Meigs County, Ohio. The project occupies 23 acres of
federal land administered by the Corps.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Jonathan Magalski, Environmental Supervisor
(Renewables), c/o American Electric Power Service Corporation, 1
Riverside Plaza, Columbus, OH 43215; (614) 716-2240, <a href="/cdn-cgi/l/email-protection#563c3b3b3731373a253d3f163733267835393b"><span class="__cf_email__" data-cfemail="e68c8b8b8781878a958d8fa6878396c885898b">[email protected]</span></a>
or Elizabeth Parcell, Process Supervisor, American Electric Power
Service Corporation, c/o AEP Generation Resources, Inc., 40 Franklin
Road SW, Roanoke, VA 24011, (540) 985-2441.
i. FERC Contact: Jay Summers at (202) 502-8764 or email at
<a href="/cdn-cgi/l/email-protection#771d160e5904021a1a120504371112051459101801"><span class="__cf_email__" data-cfemail="107a71693e63657d7d75626350767562733e777f66">[email protected]</span></a>.
j. This application is not ready for environmental analysis at this
time.
k. The Racine Project would use the Corps' existing Racine Locks
and Dam and consist of the following existing facilities: (1) Four
21.75-foot-wide by 60-foot-high intake openings equipped with steel
trashracks having a clear bar spacing of 5.5 inches; (2) a reinforced
concrete powerhouse located on the east end of the dam containing two
horizontal bulb generating units, with a combined capacity of 47.5
megawatts; (3) a 155-foot-long, non-overflow section of sheet pile
cells located between the powerhouse and the right abutment; (4) a
stand-alone functional replacement dam located upstream of the sheet
pile cells that consists of a drilled shaft supported concrete dam with
a drilled secant pile seepage control; (5) a 475-foot-long transmission
line; and (6) appurtenant facilities.
The Racine Project is currently operated in a run-of-release mode
using surplus water from the Corps' Racine Locks and Dam, as directed
by the Corps, and has an estimated average annual energy production of
90,364 megawatt-hours. AEP Generation Resources does not propose any
new construction and proposes to continue operating the project in a
run-of-release mode.
l. Locations of the Application: In addition to publishing the full
text of this document in the Federal Register, the Commission provides
all interested individuals an opportunity to view and/or print the
contents of this document and the full license application via the
internet through the Commission's website at <a href="http://www.ferc.gov">http://www.ferc.gov</a> using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access these documents. At this
time, the Commission has suspended access to the Commission's Public
Reference Room due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact FERC at
<a href="/cdn-cgi/l/email-protection#41070413020e2f2d282f24123431312e333501272433226f262e37"><span class="__cf_email__" data-cfemail="c88e8d9a8b87a6a4a1a6ad9bbdb8b8a7babc88aeadbaabe6afa7be">[email protected]</span></a> or call toll-free, (866) 208-3676 or (202)
502-8659 (TTY).
m. You may also register online at <a href="http://www.ferc.gov/docs-filing/esubscription.asp">http://www.ferc.gov/docs-filing/esubscription.asp</a> to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural Schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule may be made as appropriate.
----------------------------------------------------------------------------------------------------------------
Milestone Target date
----------------------------------------------------------------------------------------------------------------
Issue Deficiency Letter (if necessary)..................... December 2021.
Request Additional Information............................. January 2022.
Notice of Acceptance/Notice of Ready for Environmental May 2022.
Analysis.
----------------------------------------------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: December 8, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-27060 Filed 12-14-21; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on December 15, 2021.