New England Hydropower Company, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
November 22, 2021
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 222 (Monday, November 22, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 222 (Monday, November 22, 2021)]
[Notices]
[Pages 66294-66295]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-25404]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14634-003]
New England Hydropower Company, LLC; Notice of Application
Tendered for Filing With the Commission and Soliciting Additional Study
Requests and Establishing Procedural Schedule for Relicensing and a
Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Minor License.
b. Project No.: 14634-003.
c. Date filed: November 2, 2021.
d. Applicant: New England Hydropower Company, LLC (NEHC).
e. Name of Project: Ashton Dam Hydroelectric Project (project).
f. Location: On the Blackstone River in Providence County, Rhode
Island. No federal or tribal lands would be occupied by project works
or located within the project boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Michael Kerr, New England Hydropower
Company, LLC, 100 Cummings Center, Suite 451C, Beverly, MA 01915; Phone
at (978) 360-2547, or email at <a href="/cdn-cgi/l/email-protection#e984808a81888c85a9878c81908d9b8699869e8c9bc78a8684"><span class="__cf_email__" data-cfemail="4e23272d262f2b220e202b26372a3c213e21392b3c602d2123">[email protected]</span></a>.
i. FERC Contact: John Baummer at (202) 502-6837, or
<a href="/cdn-cgi/l/email-protection#b7ddd8dfd999d5d6c2dadad2c5f7d1d2c5d499d0d8c1"><span class="__cf_email__" data-cfemail="640e0b0c0a4a0605110909011624020116074a030b12">[email protected]</span></a>.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis
[[Page 66295]]
for a complete analysis of the application on its merit, the resource
agency, Indian Tribe, or person must file a request for a study with
the Commission not later than 60 days from the date of filing of the
application, and serve a copy of the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 1, 2022.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a>. For assistance, please contact FERC Online Support at
<a href="/cdn-cgi/l/email-protection#1a5c5f485955747673747f496f6a6a75686e5a7c7f6879347d756c"><span class="__cf_email__" data-cfemail="b8fefdeafbf7d6d4d1d6ddebcdc8c8d7caccf8deddcadb96dfd7ce">[email protected]</span></a>, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
MD 20852. All filings must clearly identify the project name and docket
number on the first page: Ashton Dam Hydroelectric Project (P-14634-
003).
m. The application is not ready for environmental analysis at this
time.
n. The proposed Ashton Dam Hydroelectric Project would consist of:
(1) An existing stone masonry gravity dam that includes: (a) A western
abutment section; (b) a 203-foot-long western spillway section with a
crest elevation of 73.6 feet North American Vertical Datum of 1988
(NAVD 88); (c) an 18-foot-long stone masonry pier that includes two 4-
foot-wide, 8-foot-high existing openings, to be modified to include a
new low-level steel bulkhead panel; (d) an existing 54-foot-long
eastern spillway section that would be replaced with a new 54-foot-long
concrete section that includes: (i) Two 19.7-foot-wide, 18.1-foot-high
log sluice gates with crest elevations of 82.1 NAVD 88; (ii) two 19.7-
foot-wide, horizontal steel trashracks sloped at 9 degrees to inflow
with 0.5-inch clear bar spacing; and (iii) two 19.7-foot-wide, 15.4-
foot-high openings; and (e) an eastern abutment section; (2) an
existing impoundment with a surface area of 11.73 acres at an elevation
of 73.6 feet NAVD 88; (3) four submersible StreamDiver Kaplan turbine-
generator units (three 189-kilowatt (kW) and one 102-kW generators)
located in the openings of the new concrete structure, with a total
installed capacity of 669 kW; (4) four new 8.1-foot-wide, 3.8-foot-high
hinged crest gates with crest elevations of 73.6 feet NAVD 88,
installed on top of the new concrete structure; (5) a new 11.5-foot-
long, 44.3-foot-wide concrete tailrace and an approximately 30- to 45-
foot-long, 44.3-foot-wide concrete apron; (6) a new 20-foot-long, 8-
foot-wide control building located on the eastern shoreline of the
Blackstone River; (7) a new step-up transformer and a 1,370-foot-long
underground transmission line connecting the project to the
distribution system owned by the Narragansett Electric Company; (8) a
new access road and parking area; and (9) appurtenant facilities.
NEHC proposes to: (1) Operate the project in a run-of-river mode
with an estimated annual energy production of approximately 2,870
megawatt-hours; (2) release a continuous minimum flow of 100 cubic feet
per second or inflow whichever is less, over the western spillway; (3)
install a downstream fish passage facility between the crest gates on
top of the new concrete structure; and (4) install an upstream eel
passage facility at the project dam.
o. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (<a href="http://www.ferc.gov">http://www.ferc.gov</a>)
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document (P-
14634). For assistance, contact FERC at <a href="/cdn-cgi/l/email-protection#e5a3a0b7a6aa8b898c8b80b69095958a9791a583809786cb828a93"><span class="__cf_email__" data-cfemail="b8fefdeafbf7d6d4d1d6ddebcdc8c8d7caccf8deddcadb96dfd7ce">[email protected]</span></a> or
call toll-free, (866) 208-3676 or (202) 502-8659 (TTY).
You may also register online at <a href="https://ferconline.ferc.gov/FERCOnline.aspx">https://ferconline.ferc.gov/FERCOnline.aspx</a> to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
Issue Deficiency Letter (if necessary)--January 2022
Request Additional Information--January 2022
Issue Scoping Document 1 for comments--March 2022
Request Additional Information (if necessary)--April 2022
Issue Acceptance Letter--April 2022
Issue Scoping Document 2--June 2022
Issue Notice of Ready for Environmental Analysis--June 2022
q. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: November 16, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-25404 Filed 11-19-21; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on November 22, 2021.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.