Notice2021-20777
Mad River Power Associates; Notice of Intent To Prepare an Environmental Assessment
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
September 24, 2021
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 183 (Friday, September 24, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 183 (Friday, September 24, 2021)]
[Notices]
[Pages 53047-53048]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-20777]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3253-015]
Mad River Power Associates; Notice of Intent To Prepare an
Environmental Assessment
On November 3, 2020, Mad River Power Associates filed an
application for a subsequent license to continue operating the existing
639-kilowatt Campton Hydroelectric Project No. 3253 (project). The
project is located on the Mad River in Grafton County, New Hampshire,
and occupies approximately 0.08 acre of federal land administered by
the U.S. Forest Service.
In accordance with the Commission's regulations, on July 7, 2021,
Commission staff issued a notice that the project was ready for
environmental analysis (REA notice). Based on the information in the
record, including comments filed on the REA notice, staff does not
anticipate that licensing the project would constitute a major federal
action significantly affecting the quality of the human environment.
Therefore, staff intends to prepare an Environmental Assessment (EA) on
the application to license the project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be
[[Page 53048]]
analyzed by staff and considered in the Commission's final licensing
decision.
The application will be processed according to the following
schedule. Revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA...................... March 2022.\1\
Comments on EA............................ May 2022.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Amanda Gill
at (202) 502-6773 or <a href="/cdn-cgi/l/email-protection#87e6eae6e9e3e6a9e0eeebebc7e1e2f5e4a9e0e8f1"><span class="__cf_email__" data-cfemail="c2a3afa3aca6a3eca5abaeae82a4a7b0a1eca5adb4">[email protected]</span></a>.
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1
year of the federal action agency's decision to prepare an EA. This
notice establishes the Commission's intent to prepare an EA for the
Campton Hydroelectric Project. Therefore, in accordance with CEQ's
regulations, the EA must be issued within 1 year of the issuance
date of this notice.
Dated: September 20, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2021-20777 Filed 9-23-21; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on September 24, 2021.