Removing Profile Drawing Requirement for Qualifying Conduit Notices of Intent and Revising Filing Requirements for Major Hydroelectric Projects 10 MW or Less
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Issuing agencies
Abstract
In this final rule, the Federal Energy Regulatory Commission (Commission) is amending its regulations governing the filing requirements for qualifying conduits and certain major hydroelectric power projects. Specifically, the Commission is removing the requirement that a notice of intent to construct a qualifying conduit include a profile drawing showing the source of the hydroelectric potential in instances where a dam would be constructed in association with the facility and extending the licensing requirements that currently apply to major projects up to 5 megawatts (MW) to major projects 10 MW or less, consistent with the amended definition of a small hydroelectric power project in the Hydropower Regulatory Efficiency Act of 2013.
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 148 (Thursday, August 5, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 148 (Thursday, August 5, 2021)]
[Rules and Regulations]
[Pages 42710-42715]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-15511]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Parts 4 and 5
[Docket No. RM20-21-000; Order No. 877]
Removing Profile Drawing Requirement for Qualifying Conduit
Notices of Intent and Revising Filing Requirements for Major
Hydroelectric Projects 10 MW or Less
AGENCY: Federal Energy Regulatory Commission, Department of Energy.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: In this final rule, the Federal Energy Regulatory Commission
(Commission) is amending its regulations governing the filing
requirements for qualifying conduits and certain major hydroelectric
power projects. Specifically, the Commission is removing the
requirement that a notice of intent to construct a qualifying conduit
include a profile drawing showing the source of the hydroelectric
potential in instances where a dam would be constructed in association
with the facility and extending the licensing requirements that
currently apply to major projects up to 5 megawatts (MW) to major
projects 10 MW or less, consistent with the amended definition of a
small hydroelectric power project in the Hydropower Regulatory
Efficiency Act of 2013.
DATES: This rule is effective October 4, 2021.
FOR FURTHER INFORMATION CONTACT: Heather Campbell (Technical
Information), Office of Energy Projects, Federal Energy Regulatory
Commission, 888 First Street NE, Washington, DC 20426, (202) 502-6182,
<a href="/cdn-cgi/l/email-protection#d7bfb2b6a3bfb2a5f9b2f9b4b6baa7b5b2bbbb97b1b2a5b4f9b0b8a1"><span class="__cf_email__" data-cfemail="9df5f8fce9f5f8efb3f8b3fefcf0edfff8f1f1ddfbf8effeb3faf2eb">[email protected]</span></a>.
Kelly Houff (Technical Information), Office of Energy Projects,
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426, (202) 502-6393, <a href="/cdn-cgi/l/email-protection#bed5dbd2d2c790d6d1cbd8d8fed8dbccdd90d9d1c8"><span class="__cf_email__" data-cfemail="9df6f8f1f1e4b3f5f2e8fbfbddfbf8effeb3faf2eb">[email protected]</span></a>.
John Matkowski (Technical Information), Office of Energy Projects,
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426, (202) 502-8576, <a href="/cdn-cgi/l/email-protection#d8b2b7b0b6f6b5b9acb3b7afabb3b198bebdaabbf6bfb7ae"><span class="__cf_email__" data-cfemail="d1bbbeb9bfffbcb0a5babea6a2bab891b7b4a3b2ffb6bea7">[email protected]</span></a>.
Rachael Warden (Legal Information), Office of the General Counsel,
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426, (202) 502-8717, <a href="/cdn-cgi/l/email-protection#295b484a41484c45075e485b4d4c47694f4c5b4a074e465f"><span class="__cf_email__" data-cfemail="4a382b29222b2f26643d2b382e2f240a2c2f3829642d253c">[email protected]</span></a>.
SUPPLEMENTARY INFORMATION:
I. Background
1. By this final rule, the Federal Energy Regulatory Commission
(Commission or FERC) is amending parts 4 and 5 of its regulations
governing the filing requirements for qualifying conduits and certain
major hydroelectric power projects. The Commission, under Part I of the
Federal Power Act (FPA), licenses hydropower projects that are
developed by non-Federal entities including individuals, private
entities, states, municipalities, electric cooperatives, and others.
2. The Hydropower Regulatory Efficiency Act of 2013 (2013 HREA) \1\
was signed into law on August 9, 2013. As explained below, changes
implemented in response to the 2013 HREA form the basis for these
revisions to the Commission's regulations.
---------------------------------------------------------------------------
\1\ Public Law 113-23, 127 Stat. 493 (2013).
---------------------------------------------------------------------------
II. Notice of Proposed Rulemaking
3. On February 18, 2021, the Commission issued a notice of proposed
rulemaking (NOPR) proposing to: (1) Remove the requirement that a
notice of intent to construct a qualifying conduit include a profile
drawing showing the source of the hydroelectric potential in instances
where a dam would be constructed in association with the facility; and
(2) extend the licensing requirements that currently apply to major
projects up to 5 megawatts (MW) to major projects 10 MW or less,
consistent with the amended definition of a small hydroelectric power
project in the 2013 HREA.\2\ The Commission did not receive any
comments in response to the NOPR. The proposal set forth in the NOPR
and the Commission's determination are discussed below.
---------------------------------------------------------------------------
\2\ Removing Profile Drawing Requirement for Qualifying Conduit
Notices of Intent and Revising Filing Requirements for Major
Hydroelectric Projects 10 MW or Less, 86 FR 13506 (Mar. 9, 2021),
174 FERC ] 61,105 (2021).
---------------------------------------------------------------------------
III. Discussion
A. Qualifying Conduits
4. The NOPR explained that the 2013 HREA amended section 30 of the
FPA to create a subset of small conduit facilities that are
categorically excluded from the licensing and exemption requirements of
the FPA. In 2014, the Commission issued Order No. 800, which became
effective February 23, 2015, defining a ``qualifying conduit hydropower
facility'' at Sec. 4.30(b)(26) of its regulations.\3\ Subsequently,
section 30 of the FPA was amended by the
[[Page 42711]]
America's Water Infrastructure Act of 2018.\4\
---------------------------------------------------------------------------
\3\ See Revisions and Technical Corrections to Conform the
Commission's Regulations to the Hydropower Regulatory Efficiency Act
of 2013, Order No. 800, 79 FR 59105 (Oct. 1, 2014), 148 FERC ]
61,197 (2014).
\4\ Public Law 115-270, 132 Stat. 3765 (2018).
---------------------------------------------------------------------------
5. In accordance with section 30(a)(2)(A),\5\ any person, State, or
municipality proposing to construct a ``qualifying conduit hydropower
facility'' must file a notice of intent demonstrating the facility
meets the following ``qualifying criteria'': \6\
---------------------------------------------------------------------------
\5\ 16 U.S.C. 823a(a)(2)(A).
\6\ Id. 823a(a)(3)(C). The qualifying conduit hydropower
facility must also meet the requirements for a small conduit
facility as defined in section 30(a)(3)(A) of the FPA. Id.
823a(a)(3)(A).
---------------------------------------------------------------------------
<bullet> Be located on and use only the hydroelectric potential of
a non-federally owned conduit;
<bullet> have a proposed installed capacity that does not exceed 40
MW; \7\ and
---------------------------------------------------------------------------
\7\ The 2013 HREA required that qualifying conduit hydropower
facilities not exceed 5 MW. This limit was revised to 40 MW at
section 3002(2) in the America's Water Infrastructure Act of 2018
(codified at 16 U.S.C. 823a(a)(3)(C)(ii)).
---------------------------------------------------------------------------
<bullet> be proposed for construction and, as of the date of
enactment of the 2013 HREA, not be licensed under, or exempted from,
the licensing requirements of Part I of the FPA.
6. Under the 2013 HREA, as amended,\8\ the Commission is required
to determine whether proposed projects meet the criteria to be
considered qualifying conduit hydropower facilities. Qualifying conduit
hydropower facilities are not required to be licensed or exempted by
the Commission; however, the entity proposing to construct a facility
that meets the criteria must file a Notice of Intent to Construct a
Qualifying Conduit Hydropower Facility (NOI) with the Commission that
demonstrates the facility meets the qualifying criteria discussed
above.
---------------------------------------------------------------------------
\8\ Public Law 115-270, 132 Stat. 3765.
---------------------------------------------------------------------------
7. The NOI must contain: An introductory statement; a statement
that the proposed project will use the hydroelectric potential of a
non-federally owned conduit; a statement that the proposed facility has
not been licensed or exempted on or before August 9, 2013; a
description of the facility proposal; project drawings; the preliminary
permit project number of the proposed facility, if applicable; and
verification in a sworn notarized statement or an unsworn statement.\9\
Specifically with respect to the project drawings, the NOI must include
a plan (or overhead view); a location map showing the facilities and
their relationship to the nearest town; and if a dam would be
constructed in association with the facility, a profile drawing showing
that the conduit, and not the dam, creates the hydroelectric
potential.\10\
---------------------------------------------------------------------------
\9\ 18 CFR 4.401.
\10\ Id. Sec. 4.401(f).
---------------------------------------------------------------------------
8. On June 18, 2015, in Soldier Canyon Filter Plant,\11\ the
Commission stated:
---------------------------------------------------------------------------
\11\ 151 FERC ] 61,228 (2015).
---------------------------------------------------------------------------
In determining whether a proposed qualifying conduit hydropower
facility meets the requirement of FPA section 30(a) that it use ``only
the hydroelectric potential of a non-federally owned conduit'' and (if
it meets the other section 30(a) requirements) is thus excluded from
the licensing requirements of the FPA, we see no reason to apply a
different, more stringent standard than was established in 1980 for
small conduit facility exemptions. We view small conduit facilities and
qualifying conduits as simply generating hydroelectricity by using the
water within a conduit operated for the distribution of water for
agricultural, municipal, or industrial consumption and not primarily
for the generation of electricity. Whether, or in what proportion, the
conduit's ability to generate hydropower is due to the conduit's
gradient or the head from an upstream dam is not relevant.\12\
---------------------------------------------------------------------------
\12\ Id. P 13.
This holding indicates that the profile drawings are no longer relevant
and should not be required as part of the NOI submittal. Consequently,
the Commission proposed to amend its regulations to remove this
requirement.
B. Major Projects Greater Than 5 MW and up to and Including 10 MW
9. Section 405 of the Public Utility Regulatory Policies Act of
1978 (PURPA) \13\ provided that certain hydropower projects that
produce 5,000 kilowatts, or 5 MW, or less of power were exempted from
the licensing requirements of Part 1 of the FPA.
---------------------------------------------------------------------------
\13\ 16 U.S.C. 2705.
---------------------------------------------------------------------------
10. In 1981, the Commission adopted the 5-MW demarcation for
certain major hydroelectric projects required to be licensed under Part
1 of the FPA to parallel PURPA's 5-MW demarcation regarding
exemptions.\14\ Part 4 of the Commission's regulations includes three
relevant licensing subparts: (1) Subpart E--Application for License for
Major Unconstructed Project and Major Modified Project (see 18 CFR
4.40); (2) Subpart F--Application for License for Major Project--
Existing Dam (see 18 CFR 4.50); and (3) Subpart G--Application for
License for Minor Water Power Projects and Major Water Power Projects 5
MW or Less (see 18 CFR 4.60; 4.61).\15\ Subparts E and F apply to
projects greater than 5 MW, and include additional filing requirements
beyond subpart G, which applies to projects less than or equal to 5 MW.
---------------------------------------------------------------------------
\14\ Regulations Governing Applications for License for Major
Unconstructed Projects and Major Modified Projects; Applications for
License for Transmission Line Only and Applications for Amendment to
License, Order No. 184, 46 FR 55926 (Nov. 13, 1981), FERC Stats. &
Regs. ] 30,308 (1981) (cross-referenced at 17 FERC ] 61,122);
Regulations Governing Applications for License for Minor Water Power
Projects and Major Water Power Projects 5 Megawatts or Less, Order
No. 185, 46 FR 55944 (Nov. 13, 1981), FERC Stats. & Regs. ] 30,309
(1981) (cross-referenced at 17 FERC ] 61,121).
\15\ The Commission has maintained a distinction between major
and minor projects based on section 10(i) of the FPA. However, the
license application procedures set forth in Sec. 4.61 of the
Commission's regulations apply to both minor projects and major
projects less than 5 MW (with the exception of Exhibit E for
unconstructed projects). These revisions do not affect minor
projects.
---------------------------------------------------------------------------
11. Likewise, part 4 of Commission's regulations include two
subparts that rely on the same 5-MW limit to determine minimum filing
requirements for an application for license solely for transmission
lines that transmit power from a licensed water power projects as well
amendments to licensed water power projects: (1) Subpart H--Application
for License for Transmission Line Only (see 18 CFR 4.71); and (2)
Subpart L--Application for Amendment of License (see 18 CFR 4.201),
respectively.
12. Part 5 of the Commission's regulations rely on the 5-MW limit
to determine minimum filing requirements for applications for license
for water power projects filed and processed using the integrated
licensing process (see 18 CFR 5.18).
13. The 2013 HREA amended section 405 to increase the limit for
exemptions to 10,000 kilowatts, or 10 MW, with the goal of facilitating
the speed at which such hydropower projects could be built. Order 800
amended the Commission's regulations to reflect the 10-MW limit.\16\
---------------------------------------------------------------------------
\16\ See Revisions and Technical Corrections to Conform the
Commission's Regulations to the Hydropower Regulatory Efficiency Act
of 2013, Order No. 800, 148 FERC ] 61,197 (2014).
---------------------------------------------------------------------------
14. As a result of these changes, the Commission's limit for
license application provisions no longer parallels the limit for
exemptions. We stated in the NOPR that we continue to believe that a
parallel demarcation is appropriate to ``expedite hydropower
development by easing the burden of preparing an application for
license and by assisting the Commission in more rapid processing of
applications.'' \17\
[[Page 42712]]
Moreover, the 5-MW limit in the Commission's regulations could be
burdensome to projects greater than 5 MW and up to and including 10 MW,
in terms of the cost and time associated with the additional filing
requirements of subparts E and F.
---------------------------------------------------------------------------
\17\ Applications for License for Minor Water Power Projects and
Major Water Power Projects 5 Megawatts or Less, 46 FR 9637 (Jan. 29,
1981), FERC Stats. & Regs. ] 32,106 (1981) (cross-referenced at 14
FERC ] 61,042).
---------------------------------------------------------------------------
15. Therefore, the Commission proposed to amend parts 4 and 5 of
its regulations to extend the licensing and amendment filing
requirements that currently apply to major projects up to 5 MW to major
projects 10 MW or less, consistent with the amended definition of a
small hydroelectric power project in the 2013 HREA.\18\
---------------------------------------------------------------------------
\18\ Section 4.32(a)(5)(ii), which contains a cross-reference to
Sec. 4.61, will also be revised.
---------------------------------------------------------------------------
C. Commission Determination
16. For the reasons discussed above, the Commission adopts the
NOPR's proposal to: (1) Remove the requirement that an NOI include a
profile drawing showing the source of the hydroelectric potential in
instances where a dam would be constructed in association with the
facility; and (2) extend the licensing requirements that currently
apply to major projects up to 5 MW to major projects 10 MW or less.
IV. Regulatory Requirements
A. Information Collection Statement
17. The Paperwork Reduction Act \19\ requires each Federal agency
to seek and obtain the Office of Management and Budget's (OMB) approval
before undertaking a collection of information directed to 10 or more
persons or contained in a rule of general applicability. OMB
regulations require approval of certain information collection
requirements contained in final rules published in the Federal
Register.\20\ Upon approval of a collection of information, OMB will
assign an OMB control number and an expiration date. Respondents
subject to the filing requirements of a rule will not be penalized for
failing to respond to the collection of information unless the
collection of information displays a valid OMB control number.
---------------------------------------------------------------------------
\19\ 44 U.S.C. 3501-3521.
\20\ See 5 CFR 1320.12.
---------------------------------------------------------------------------
18. Public Reporting Burden: By revising regulations governing the
filing requirements for qualifying conduits and for major hydroelectric
power projects greater than 5 MW and up to and including 10 MW, this
final rule will modify certain reporting and recordkeeping requirements
included in FERC-500 (OMB Control No 1902-0058) \21\ and FERC-505 (OMB
Control No. 1902-0115).\22\
---------------------------------------------------------------------------
\21\ FERC-500 includes the reporting and recordkeeping
requirements for ``Application for License/Relicense for Water
Projects with More than 5 Megawatt (MW) Capacity.''
\22\ FERC-505 includes the reporting and recordkeeping
requirements for ``Small Hydropower Projects and Conduit Facilities
including License/Relicense, Exemption, and Qualifying Conduit
Facility Determination.''
---------------------------------------------------------------------------
19. These revisions to the Commission's regulations will align the
filing requirements for qualifying conduits with Commission precedent
and align the filing requirements for major projects greater than 5 MW
and up to and including 10 MW to be consistent with the amended
definition of a small hydroelectric power project in the 2013 HREA.
Both revisions represent a slight decrease in the reporting
requirements and burden information for FERC-500 and FERC-505.
20. The estimated burden and cost for the requirements affected by
this final rule follow.
Changes Due to the Final Rule in Docket No. RM20-21-000
--------------------------------------------------------------------------------------------------------------------------------------------------------
Numbers of
Numbers of responses \23\ Total number Avg. burden hrs. & cost per Total annual burden hours &
respondents per respondent of responses response \24\ total annual cost
(1) (2) (1) x (2) = (4)............................. (3) x (4) = 5
(3)
--------------------------------------------------------------------------------------------------------------------------------------------------------
FERC-500............................ 3 1 3 320 hours/$26,560 reduction..... 960 hours/$79,680 reduction.
FERC-505............................ 8 1 8 10 hours/$830 reduction......... 80 hours/$6,640 reduction.
-------------------------------------------------------------------------------------------------------------------
Total........................... .............. .............. 11 ................................ 1,040 hours/$86,320 reduction.
--------------------------------------------------------------------------------------------------------------------------------------------------------
21. Titles: FERC-500 (Application for License/Relicense for Water
Projects with More than 5 Megawatt (MW) Capacity) and FERC-505 (Small
Hydropower Projects and Conduit Facilities including License/Relicense,
Exemption, and Qualifying Conduit Facility Determination).
---------------------------------------------------------------------------
\23\ We consider the filing of an application or notice of
intent to be a ``response.''
\24\ Commission staff estimates that the industry's skill set
and cost (for wages and benefits) for FERC-500 and FERC-505 are
approximately the same as the Commission's average cost. The FERC
2020 average salary plus benefits for one FERC full-time equivalent
(FTE) is $172,329/year (or $83.00/hour).
---------------------------------------------------------------------------
22. Action: Revisions to information collections FERC-500 and FERC-
505.
23. OMB Control Nos.: 1902-0058 (FERC-500) and 1902-0115 (FERC-
505).
24. Respondents: Municipalities, businesses, private citizens, and
for-profit and not-for-profit institutions.
25. Frequency of Information: Ongoing.
26. Necessity of Information: The revised regulations remove the
Commission's requirement for notices of intent to construct a
qualifying conduit to include a profile drawing, consistent with
Commission precedent, and align the Commission's filing requirements
for major projects greater than 5 MW and up to and including 10 MW to
be consistent with the amended definition of a small hydroelectric
power project in the 2013 HREA. The revised regulations affect only the
number of entities that would file applications with the Commission for
these two project types and reduce information collection requirements.
27. Internal Review: The Commission has reviewed the revisions and
has determined that they are necessary. These requirements conform to
the Commission's need for efficient information collection,
communication, and management within the energy industry. The
Commission has assured
[[Page 42713]]
itself, by means of internal review, that there is specific, objective
support for the burden estimates associated with the information
collection requirements.
28. Interested persons may obtain information on the reporting
requirements by contacting the Federal Energy Regulatory Commission at
one of the following methods:
<bullet> USPS at: Federal Energy Regulatory Commission, Ellen
Brown, Office of the Executive Director, 888 First Street NE,
Washington, DC 20426.
<bullet> Hard copy communication other than USPS: Federal Energy
Regulatory Commission, Ellen Brown, Office of the Executive Director,
12225 Wilkins Avenue, Rockville, Maryland 20852.
<bullet> email to: <a href="/cdn-cgi/l/email-protection#d490b5a0b597b8b1b5a6b5bab7b194b2b1a6b7fab3bba2"><span class="__cf_email__" data-cfemail="abefcadfcae8c7cecad9cac5c8ceebcdced9c885ccc4dd">[email protected]</span></a>.
<bullet> phone: (202) 502-8663, or by fax: (202) 273-0873.
29. Please send comments concerning the collection of information
and the associated burden estimates to: Office of Information and
Regulatory Affairs, Office of Management and Budget [Attention: Federal
Energy Regulatory Commission Desk Officer]. Due to security concerns,
comments should be sent directly to <a href="http://www.reginfo.gov/public/do/PRAMain">www.reginfo.gov/public/do/PRAMain</a>.
Comments submitted to OMB should be sent within 30 days of publication
of this notification in the Federal Register and should refer to FERC-
500 (OMB Control No 1902-0058) and FERC-505 (OMB Control No. 1902-
0115).
B. Environmental Analysis
30. The Commission is required to prepare an Environmental
Assessment or an Environmental Impact statement for any action that may
have a significant effect on the human environment.\25\ Excluded from
this requirement are rules that are clarifying, corrective, or
procedural, or that do not substantially change the effect of
legislation or the regulations being amended.\26\ This final rule
revises the filing requirements for qualifying conduit projects and the
filing requirements for license applications for major hydroelectric
projects with an installed capacity of 10 MW or less. Because this
final rule is procedural and does not substantially change the effect
of the regulations being amended, preparation of an Environmental
Assessment or Environmental Impact Statement is not required.
---------------------------------------------------------------------------
\25\ Regulations Implementing the National Environmental Policy
Act of 1969, Order No. 486, 52 FR 47897 (Dec. 17, 1987), FERC Stats.
& Regs. ] 30,783 (1987) (cross-referenced at 41 FERC ] 61,284).
\26\ 18 CFR 380.4(a)(2)(ii).
---------------------------------------------------------------------------
C. Regulatory Flexibility Act
31. The Regulatory Flexibility Act of 1980 (RFA) \27\ generally
requires a description and analysis of final rules that will have
significant economic impact on a substantial number of small entities.
The RFA mandates consideration of regulatory alternatives that
accomplish the stated objectives of a rulemaking and minimize any
significant economic impact on a substantial number of small
entities.\28\ In lieu of preparing a regulatory flexibility analysis,
an agency may certify that a final rule will not have a significant
economic impact on a substantial number of small entities.\29\
---------------------------------------------------------------------------
\27\ 5 U.S.C. 601-612.
\28\ Id. 603(c).
\29\ Id. 605(b).
---------------------------------------------------------------------------
32. The Small Business Administration's (SBA) Office of Size
Standards develops the numerical definition of a small business.\30\
The SBA size standard for electric utilities is based on the number of
employees, including affiliates.\31\ Under SBA's current size
standards, a hydroelectric power generator (NAICS code 221111) \32\ is
small if, including its affiliates, it employs 500 or fewer people.\33\
The Commission, however, currently does not require information
regarding the number of individuals employed by hydroelectric
generators to administer Part 1 of the Federal Power Act and therefore
is unable to estimate the number of small entities under the SBA
definition. Regardless, the Commission anticipates that this final rule
will affect few entities.
---------------------------------------------------------------------------
\30\ 13 CFR 121.101.
\31\ Id. Sec. 121.201.
\32\ The North American Industry Classification System (NAICS)
is an industry classification system that Federal statistical
agencies use to categorize businesses for the purpose of collecting,
analyzing, and publishing statistical data related to the U.S.
economy. United States Census Bureau, North American Industry
Classification System, <a href="https://www.census.gov/eos/www/naics/">https://www.census.gov/eos/www/naics/</a>.
\33\ 13 CFR 121.201 (Sector 22--Utilities).
---------------------------------------------------------------------------
33. As noted earlier, the final rule will only affect entities
filing notices of intent to construct a qualifying conduit in instances
where a dam would be constructed in association with the facility and
entities filing licensing or amendment applications for major
hydroelectric projects with an installed capacity of greater than 5 MW
and up to and including 10 MW. From 2013 to 2020, the Commission
received approximately 140 total notices to construct qualifying
conduits and 18 applicable licensing applications. The revisions will
eliminate the filing requirement for profile drawings and reduce the
filing requirements for major hydroelectric projects with an installed
capacity greater than 5 MW and up to and including 10 MW, thus reducing
the burden on small hydro developers going forward.
34. Accordingly, pursuant to section 605(b) of the RFA, the
Commission certifies that this final rule would not have a significant
economic impact on a substantial number of small entities.
D. Document Availability
35. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (<a href="http://www.ferc.gov">http://www.ferc.gov</a>). At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the March 13, 2020 proclamation declaring
a National Emergency concerning the Novel Coronavirus Disease (COVID-
19).
36. From the Commission's Home Page on the internet, this
information is available on eLibrary. The full text of this document is
available on eLibrary in PDF and Microsoft Word format for viewing,
printing, and/or downloading. To access this document in eLibrary, type
the docket number excluding the last three digits of this document in
the docket number field.
37. User assistance is available for eLibrary and the Commission's
website during normal business hours from the Commission's Online
Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at
<a href="/cdn-cgi/l/email-protection#31575443525e5f5d585f54424441415e434571575443521f565e47"><span class="__cf_email__" data-cfemail="dbbdbea9b8b4b5b7b2b5bea8aeababb4a9af9bbdbea9b8f5bcb4ad">[email protected]</span></a>, or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
<a href="/cdn-cgi/l/email-protection#65151007090c064b1700030017000b0600170a0a0825030017064b020a13"><span class="__cf_email__" data-cfemail="324247505e5b511c4057545740575c5157405d5d5f72545740511c555d44">[email protected]</span></a>.
E. Effective Date and Congressional Notification
38. These regulations are effective October 4, 2021. The Commission
has determined, with the concurrence of the Administrator of the Office
of Information and Regulatory Affairs of OMB, that this rule is not a
``major rule'' as defined in section 351 of the Small Business
Regulatory Enforcement Fairness Act of 1996. This rule is being
submitted to the Senate, House, Government Accountability Office, and
Small Business Administration.
List of Subjects in 18 CFR Parts 4 and 5
Administrative practice and procedure, Electric power, Reporting
and recordkeeping requirements.
By direction of the Commission.
[[Page 42714]]
Issued: July 15, 2021.
Debbie-Anne A. Reese,
Deputy Secretary.
In consideration of the foregoing, the Commission amends parts 4
and 5, chapter I, title 18, Code of Federal Regulations, as follows:
PART 4--LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT
COSTS
0
1. The authority citation for part 4 continues to read as follows:
Authority: 16 U.S.C. 791a-825r; 42 U.S.C. 7101-7352.
0
2. In Sec. 4.32, revise paragraph (a)(5)(ii) to read as follows:
Sec. 4.32 Acceptance for filing or rejection; information to be made
available to the public; requests for additional studies.
(a) * * *
(5) * * *
(ii) License for a minor water power project and a major water
power project 10 MW or less: Sec. 4.61;
* * * * *
0
3. In Sec. 4.40, revise paragraph (a) to read as follows:
Sec. 4.40 Applicability.
(a) Applicability. The provisions of this subpart apply to any
application for an initial license for a major unconstructed project
that would have a total installed capacity of more than 10 megawatts,
and any application for an initial or new license for a major modified
project with a total installed capacity more than 10 megawatts. An
applicant for license for any major unconstructed or major modified
water power project that would have a total installed generating
capacity of 10 megawatts or less must submit application under subpart
G of this part (Sec. Sec. 4.60 and 4.61).
* * * * *
0
4. In Sec. 4.50, revise paragraphs (a)(1) and (3) to read as follows:
Sec. 4.50 Applicability.
(a) * * *
(1) Except as provided in paragraph (a)(2) of this section, the
provisions of this subpart apply to any application for either an
initial license or new license for a major project--existing dam that
is proposed to have a total installed capacity of more than 10
megawatts.
* * * * *
(3) An applicant for license for any major project--existing dam
that would have a total installed capacity of 10 megawatts or less must
submit application under subpart G of this part (Sec. Sec. 4.60 and
4.61).
* * * * *
0
5. Revise the heading to subpart G to read as follows:
Subpart G--Application for License for Minor Water Power Projects
and Major Water Power Projects 10 Megawatts or Less
0
6. In Sec. 4.60, revise paragraphs (a)(2) and (3) and (b) to read as
follows:
Sec. 4.60 Applicability and notice to agencies.
(a) * * *
(2) Any major project--existing dam, as defined in Sec.
4.30(b)(16), that has a total installed capacity of 10 MW or less; or
(3) Any major unconstructed project or major modified project, as
defined in Sec. 4.30(b)(15) and (14) respectively, that has a total
installed capacity of 10 MW or less.
(b) Notice to agencies. The Commission will supply interested
Federal, state, and local agencies with notice of any application for
license for a water power project 10 MW or less and request comment on
the application. Copies of the application will be available for
inspection at the Commission's Public Reference Room. The applicant
shall also furnish copies of the filed application to any Federal,
state, or local agency that so requests.
* * * * *
0
7. In Sec. 4.61, revise paragraphs (a)(3), (b) introductory text,
(d)(1) introductory text, and (d)(2) introductory text to read as
follows:
Sec. 4.61 Contents of application.
(a) * * *
(3) Each application for a license for a water power project 10
megawatts or less must include the information requested in the initial
statement and lettered exhibits described by paragraphs (b) through (f)
of this section, and must be provided in the form specified. The
Commission reserves the right to require additional information, or
another filing procedure, if data provided indicate such action to be
appropriate.
(b) * * *
Before the Federal Energy Regulatory Commission
Application for License for a [Minor Water Power Project, or Major
Water Power Project, 10 Megawatts or Less, as Appropriate]
* * * * *
(d) * * *
(1) For major unconstructed and major modified projects 10 MW or
less. Any application must contain an Exhibit E conforming with the
data and consultation requirements of Sec. 4.41(f), if the application
is for license for a water power project which has or is proposed to
have a total installed generating capacity greater than 1.5 MW but not
greater than 10 MW, and which:
* * * * *
(2) For minor projects and major projects at existing dams 10 MW or
less. An application for license for either a minor water power project
with a total proposed installed generating capacity of 1.5 MW or less
or a major project--existing dam with a proposed total installed
capacity of 10 MW or less must contain an Exhibit E under this
paragraph (d)(2). See Sec. 4.38 for consultation requirements. The
Environmental Report must contain the following information:
* * * * *
0
8. In Sec. 4.71, revise paragraphs (b)(1) and (2) to read as follows:
Sec. 4.71 Contents of application.
* * * * *
(b) * * *
(1) For any transmission line that, at the time the application is
filed, is not constructed and is proposed to be connected to a licensed
water power project with an installed generating capacity of more than
10 MW--Exhibits A, B, C, D, E, F, and G under Sec. 4.41;
(2) For any transmission line that, at the time the application is
filed, is not constructed and is proposed to be connected to a licensed
water power project with an installed generating capacity of 10 MW or
less--Exhibits E, F, and G under Sec. 4.61; and
* * * * *
0
9. In Sec. 4.201, revise paragraphs (b)(1) and (3) through (5) to read
as follows:
Sec. 4.201 Contents of application.
* * * * *
(b) * * *
(1) For amendment of a license for a water power project that, at
the time the application is filed, is not constructed and is proposed
to have a total installed generating capacity of more than 10 MW--
Exhibits A, B, C, D, E, F, and G under Sec. 4.41;
* * * * *
(3) For amendment of a license for a water power project that, at
the time the application is filed, is not constructed and is proposed
to have a total installed generating capacity of 10 MW or less, but
more than 1.5 MW--Exhibits F and G under Sec. 4.61, and Exhibit E
under Sec. 4.41;
(4) For amendment of a license for a water power project that, at
the time the
[[Page 42715]]
application for amendment is filed, has been constructed, and is
proposed to have a total installed generating capacity of 10 MW or
less--Exhibit E, F, and G under Sec. 4.61; and
(5) For amendment of a license for a water power project that, at
the time the application is filed, has been constructed and is proposed
to have a total installed generating capacity of more than 10 MW--
Exhibits A, B, C, D, E, F, and G under Sec. 4.51.
* * * * *
Sec. 4.401 [Amended]
0
10. In Sec. 4.401, remove paragraph (f)(3).
PART 5--INTEGRATED LICENSE APPLICATION PROCESS
0
11. The authority citation for part 5 continues to read as follows:
Authority: 16 U.S.C. 792-828c, 2601-2645; 42 U.S.C. 7101-7352.
0
12. In Sec. 5.18, revise paragraph (a)(5)(i) to read as follows:
Sec. 5.18 Application content.
(a) * * *
(5) * * *
(i) License for a minor water power project and a major water power
project 10 MW or less: Sec. 4.61 of this chapter (General
instructions, initial statement, and Exhibits A, F, and G);
* * * * *
[FR Doc. 2021-15511 Filed 8-4-21; 8:45 am]
BILLING CODE 6717-01-P