Notice2021-15405
Commonwealth LNG, LLC; Notice of Application for Amendment and Establishing Intervention Deadline
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
July 20, 2021
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 136 (Tuesday, July 20, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 136 (Tuesday, July 20, 2021)]
[Notices]
[Pages 38337-38339]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-15405]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-502-001]
Commonwealth LNG, LLC; Notice of Application for Amendment and
Establishing Intervention Deadline
Take notice that on July 8, 2021, Commonwealth LNG, LLC
(Commonwealth), One Riverway, Suite 500, Houston, TX 77056, filed an
application under section 3(a) of the Natural Gas Act (NGA) requesting
an amendment to its August 20, 2019 application (2019 Application)
requesting authorization from the Commission to site, construct, and
operate a natural gas liquefaction and export facility (LNG Facility),
including an NGA Section 3 natural gas pipeline in Cameron Parish,
Louisiana. Commonwealth's LNG Facility, described in its 2019
Application included six 40,000 cubic meter full containment LNG
Storage Tanks designed with an inner and outer tank fabricated from
nine percent (9%) nickel steel which would have required a special
authorization from the Department of Transportation, Pipeline and
Hazardous Material Safety Administration (PHMSA). Commonwealth now
plans to change the design of the LNG Storage Tanks to a traditional
full-containment, modular-built, tank design with a nine percent (9%)
nickel inner tank and a concrete outer tank with carbon steel liner
which would not require a special authorization from the PHMSA.
Commonwealth also proposes to increase the net capacity of the six LNG
Storage Tanks from 40,000 to 50,000 cubic meters each (60,000 cubic
meters total), for a new total working storage volume of 300,000 for
the LNG Facility.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (<a href="http://ferc.gov">http://ferc.gov</a>) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at <a href="/cdn-cgi/l/email-protection#05434057464a6b696c6b60567075756a777145636077662b626a73"><span class="__cf_email__" data-cfemail="a0e6e5f2e3efceccc9cec5f3d5d0d0cfd2d4e0c6c5d2c38ec7cfd6">[email protected]</span></a> or call toll-free,
(886) 208-3676 or TYY, (202) 502-8659.
Any questions regarding the proposed project should be directed to
Scott Ray or Hans Verswijver, Commonwealth Projects, One Riverway,
Suite 500, Houston, TX 77056 by phone at 346-352-4444, by email at
<a href="/cdn-cgi/l/email-protection#443736253d04302125292734286a272b29"><span class="__cf_email__" data-cfemail="c8bbbaa9b188bcada9a5abb8a4e6aba7a5">[email protected]</span></a> or <a href="/cdn-cgi/l/email-protection#acc4dac9dedfdbc5c6dac9deecd8c9cdc1cfdcc082cfc3c1"><span class="__cf_email__" data-cfemail="6f07190a1d1c180605190a1d2f1b0a0e020c1f03410c0002">[email protected]</span></a>.
Pursuant to Section 157.9 of the Commission's Rules of Practice and
Procedure,\1\ within 90 days of this Notice the Commission staff will
either: Complete its environmental review and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of
[[Page 38338]]
Schedule for Environmental Review is issued, it will indicate, among
other milestones, the anticipated date for the Commission staff's
issuance of the final environmental impact statement (FEIS) or
environmental assessment (EA) for this proposal. The filing of an EA in
the Commission's public record for this proceeding or the issuance of a
Notice of Schedule for Environmental Review will serve to notify
federal and state agencies of the timing for the completion of all
necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS or EA.
---------------------------------------------------------------------------
\1\ 18 CFR 157.9.
---------------------------------------------------------------------------
Public Participation
There are two ways to become involved in the Commission's review of
this project: You can file comments on the project, and you can file a
motion to intervene in the proceeding. There is no fee or cost for
filing comments or intervening. The deadline for filing a motion to
intervene is 5:00 p.m. Eastern Time on August 3, 2021.
Comments
Any person wishing to comment on the project may do so. Comments
may include statements of support or objections to the project as a
whole or specific aspects of the project. The more specific your
comments, the more useful they will be. To ensure that your comments
are timely and properly recorded, please submit your comments on or
before August 3, 2021.
There are three methods you can use to submit your comments to the
Commission. In all instances, please reference the Project docket
number CP19-502-001 in your submission.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's website at <a href="http://www.ferc.gov">www.ferc.gov</a>
under the link to Documents and Filings. Using eComment is an easy
method for interested persons to submit brief, text-only comments on a
project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>)
under the link to Documents and Filings. With eFiling, you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; first select ``General'' and then select ``Comment on a
Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address below. Your written comments must reference the
Project docket number (CP19-502-001).
To mail via USPS, use the following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
To mail via any other courier, use the following address: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The Commission encourages electronic filing of comments (options 1
and 2 above) and has eFiling staff available to assist you at (202)
502-8258 or <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="87c1e2f5e4c8e9ebeee9e2d4f2f7f7e8f5f3c7e1e2f5e4a9e0e8f1">[email protected]</a>.
Persons who comment on the environmental review of this project
will be placed on the Commission's environmental mailing list, and will
receive notification when the environmental documents (EA or EIS) are
issued for this project and will be notified of meetings associated
with the Commission's environmental review process.
The Commission considers all comments received about the project in
determining the appropriate action to be taken. However, the filing of
a comment alone will not serve to make the filer a party to the
proceeding. To become a party, you must intervene in the proceeding.
For instructions on how to intervene, see below.
Interventions
Any person, which includes individuals, organizations, businesses,
municipalities, and other entities,\2\ has the option to file a motion
to intervene in this proceeding. Only intervenors have the right to
request rehearing of Commission orders issued in this proceeding and to
subsequently challenge the Commission's orders in the U.S. Circuit
Courts of Appeal.
---------------------------------------------------------------------------
\2\ 18 CFR 385.102(d).
---------------------------------------------------------------------------
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \3\ and the regulations under the NGA \4\ by the
intervention deadline for the project, which is August 3, 2021. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
the your interest in the proceeding. [For an individual, this could
include your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene.] For more information
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------
\3\ 18 CFR 385.214.
\4\ 18 CFR 157.10.
---------------------------------------------------------------------------
There are two ways to submit your motion to intervene. In both
instances, please reference the Project docket number CP19-502-001 in
your submission.
(1) You may file your motion to intervene by using the Commission's
eFiling feature, which is located on the Commission's website
(<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and Filings. New eFiling
users must first create an account by clicking on ``eRegister.'' You
will be asked to select the type of filing you are making; first select
``General'' and then select ``Intervention.'' The eFiling feature
includes a document-less intervention option; for more information,
visit <a href="https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf">https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf</a>.; or
(2) You can file a paper copy of your motion to intervene, along
with three copies, by mailing the documents to the address below. Your
motion to intervene must reference the Project docket number CP19-502-
001.
To mail via USPS, use the following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
To mail via any other courier, use the following address: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
The Commission encourages electronic filing of motions to intervene
(option 1 above) and has eFiling staff available to assist you at (202)
502-8258 or <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="d395b6a1b09cbdbfbabdb680a6a3a3bca1a793b5b6a1b0fdb4bca5">[email protected]</a>.
Motions to intervene must be served on the applicant either by mail
or email at: 1717 K Street NW, Suite 900, Washington, DC 20006 or at
<a href="/cdn-cgi/l/email-protection#bed5cdc9dbdbd0dbc7fed5d3cddbd0dbccd9c7d2dfc990ddd1d3"><span class="__cf_email__" data-cfemail="68031b1f0d0d060d112803051b0d060d1a0f1104091f460b0705">[email protected]</span></a>. Any subsequent submissions by an intervenor
must be served on the applicant and all other parties to the
proceeding. Contact information for parties can be downloaded from the
service list at the eService link on FERC Online. Service can be via
email with a link to the document.
All timely, unopposed \5\ motions to intervene are automatically
granted by operation of Rule 214(c)(1).\6\ Motions to intervene that
are filed after the
[[Page 38339]]
intervention deadline are untimely and may be denied. Any late-filed
motion to intervene must show good cause for being late and must
explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations.\7\ A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
---------------------------------------------------------------------------
\5\ The applicant has 15 days from the submittal of a motion to
intervene to file a written objection to the intervention.
\6\ 18 CFR 385.214(c)(1).
\7\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
<a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.
Intervention Deadline: 5:00 p.m. Eastern Time on August 3, 2021.
Dated: July 13, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-15405 Filed 7-19-21; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>