Notice2021-13372
Dominion Energy Questar Pipeline, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Primary source
Metadata and text below are from the Federal Register, a public-domain U.S. government work. Always verify the official published version before relying on it for any legal matter.
Published
June 24, 2021
Issuing agencies
Energy DepartmentFederal Energy Regulatory Commission
Full Text
<html>
<head>
<title>Federal Register, Volume 86 Issue 119 (Thursday, June 24, 2021)</title>
</head>
<body><pre>
[Federal Register Volume 86, Number 119 (Thursday, June 24, 2021)]
[Notices]
[Pages 33274-33276]
From the Federal Register Online via the Government Publishing Office [<a href="http://www.gpo.gov">www.gpo.gov</a>]
[FR Doc No: 2021-13372]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-457-000]
Dominion Energy Questar Pipeline, LLC; Notice of Request Under
Blanket Authorization and Establishing Intervention and Protest
Deadline
Take notice that on June 3, 2021, Dominion Energy Questar Pipeline,
LLC, (DEQP), 333 South State Street, Salt Lake City, Utah 84111 filed
in the above referenced docket a prior notice pursuant to its blanket
certificate authority granted in Docket No. CP82-491-000 \1\ and
sections 157.205, 157.208 and 157.210 of the Federal Energy Regulatory
Commission's regulations under the Natural Gas Act, requesting
authorization to construct facilities and make automation and
communication updates at the Skull Creek Compressor Station (Skull
Creek CS). The Skull Creek Expansion Project (Project) proposes to
remove a capacity constraint at Skull Creek CS and thereby restore the
operationally available capacity on Main Line (ML) 86 by 17,750 Dth/d,
while remaining within the currently certificated capacity of the
existing facilities. DEQP owns and operates Skull Creek CS, located on
ML 86, near the border of Colorado in Sweetwater County, WY. ML 86
extends perpendicularly from DEQP's ML 22/23 Junction located in Moffat
County, CO, approximately 26 miles north to the Southern Star Central
Gas Pipeline, Inc (Southern Star) interconnect located in the southeast
section of Sweetwater County, WY. The project will cause no adverse
impacts or reduction of service to any existing customers on DEQP. The
estimated cost for the Project is approximately $1,322,000, all as more
fully set forth in the request which is on file with the Commission and
open to public inspection.
---------------------------------------------------------------------------
\1\ Mountain Fuel Resources, Inc., 20 FERC ] 62,580 (1982).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (<a href="http://ferc.gov">http://ferc.gov</a>) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National
[[Page 33275]]
Emergency concerning the Novel Coronavirus Disease (COVID-19), issued
by the President on March 13, 2020. For assistance, contact the Federal
Energy Regulatory Commission at <a href="/cdn-cgi/l/email-protection#397f7c6b7a76575550575c6a4c4949564b4d795f5c4b5a175e564f"><span class="__cf_email__" data-cfemail="95d3d0c7d6dafbf9fcfbf0c6e0e5e5fae7e1d5f3f0e7f6bbf2fae3">[email protected]</span></a> or call
toll-free, (886) 208-3676 or TTY, (202) 502-8659.
Any questions concerning this application should be directed to
Mark C. Stevens, General Manager Regulatory Affairs, (804) 399-2890,
<a href="/cdn-cgi/l/email-protection#81ece0f3eaafe2aff2f5e4f7e4eff2c1e5eeece8efe8eeefe4efe4f3e6f8afe2eeec"><span class="__cf_email__" data-cfemail="305d51425b1e531e43445546555e4370545f5d595e595f5e555e554257491e535f5d">[email protected]</span></a>, Dominion Energy Services, Inc., 120
Tredegar Street-3rd Floor, Richmond, VA 23219.
Public Participation
There are three ways to become involved in the Commission's review
of this project: You can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on August 13, 2021.
How to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\2\ any person \3\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\2\ 18 CFR 157.205.
\3\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\4\ and must be submitted by
the protest deadline, which is August 13, 2021. A protest may also
serve as a motion to intervene so long as the protestor states it also
seeks to be an intervenor.
---------------------------------------------------------------------------
\4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \5\ and the regulations under the NGA \6\ by the
intervention deadline for the project, which is August 13, 2021. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at <a href="https://www.ferc.gov/resources/guides/how-to/intervene.asp">https://www.ferc.gov/resources/guides/how-to/intervene.asp</a>.
---------------------------------------------------------------------------
\5\ 18 CFR 385.214.
\6\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before August 13, 2021. The filing of a comment alone will not
serve to make the filer a party to the proceeding. To become a party,
you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP21-457-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the Commission's eFiling feature, which is located on the
Commission's website (<a href="http://www.ferc.gov">www.ferc.gov</a>) under the link to Documents and
Filings. New eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing''; or \7\
---------------------------------------------------------------------------
\7\ Additionally, you may file your comments electronically by
using the eComment feature, which is located on the Commission's
website at <a href="http://www.ferc.gov">www.ferc.gov</a> under the link to Documents and Filings.
Using eComment is an easy method for interested persons to submit
brief, text-only comments on a project.
---------------------------------------------------------------------------
(2) You can file a paper copy of your submission by mailing it to
the address below.\8\ Your submission must reference the Project docket
number CP21-457-000.
---------------------------------------------------------------------------
\8\ Hand-delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
---------------------------------------------------------------------------
First Street NE, Washington, DC 20426
The Commission encourages electronic filing of submissions (option
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or <a href="/cdn-cgi/l/email-protection" class="__cf_email__" data-cfemail="f7b1928594b8999b9e9992a4828787988583b791928594d9909881">[email protected]</a>.
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at
<a href="/cdn-cgi/l/email-protection#fc919d8e97d29fd28f88998a99928fbc98939195929593929992998e9b85d29f9391"><span class="__cf_email__" data-cfemail="bcd1ddced792df92cfc8d9cad9d2cffcd8d3d1d5d2d5d3d2d9d2d9cedbc592dfd3d1">[email protected]</span></a>, 120 Tredegar Street--3rd Floor,
Richmond, VA 23219. Any subsequent submissions by an intervenor must be
served on the applicant and all other parties to the proceeding.
Contact information for parties can be downloaded from the service list
at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at <a href="http://www.ferc.gov">www.ferc.gov</a> using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings
[[Page 33276]]
by automatically providing you with notification of these filings,
document summaries, and direct links to the documents. For more
information and to register, go to <a href="http://www.ferc.gov/docs-filing/esubscription.asp">www.ferc.gov/docs-filing/esubscription.asp</a>.
Dated: June 14, 2021.
Kimberly D. Bose,
Secretary.
[FR Doc. 2021-13372 Filed 6-23-21; 8:45 am]
BILLING CODE 6717-01-P
</pre><script data-cfasync="false" src="/cdn-cgi/scripts/5c5dd728/cloudflare-static/email-decode.min.js"></script></body>
</html>Indexed from Federal Register on June 24, 2021.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.